This review provides a detailed analysis of the contingency factors and cost estimates for the Department of Energy's Coherent Light Source Project. It includes information on construction management, owner-initiated changes, and construction contingency analysis. The report also highlights the construction schedule, delays, and mitigation plans.

Download Presentation

Department Of Energy Review Linac Coherent Light Source Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Department Of Energy ReviewLinac Coherent Light Source Project Conventional FacilitiesManagement and Organization J. Albino

  2. Cost to Go at WBS Level 3

  3. Basis of Estimate - ETC

  4. Contingency Analysis • CONSTRUCTION CONTINGENCY • QUALITY OF DESIGN • 2-5 % OF CONSTRUCTION COST – USE 3% • CONSTRUCTION MANAGEMENT • 3-7 % OF CONSTRUCTION COST – USE 4% • OWNER-INITIATED CHANGES • 5-? % OF CONSTRUCTION COST – USE 8%

  5. CONTINGENCY ANALYSES

  6. CF Construction Phase • Cost/Schedule Performance • CPI = 1.03 • Title III Awarded Amount: $63,972,680 • Obligated Funds: $10,592,451 • SPI = 1.01 • NTP: 01Aug06 • Commence Sitework: 01Sep06 • Beam Line Beneficial Occupancy: 8Feb08 • Contract Close-out: 18Aug08 • Contract Administration • Submittals • Received: 32 • Approved: 18 • RFI: • Received: 55 • Closed: 55

  7. CF Construction (cont.) • Field Change Orders: • Authorized with NTE: 10 • Not-to-exceed sum: $100,000 • Pending: 2 • Estimate: $275,000

  8. Schedule • Delays • Bid Groups 1 and 2 Evaluation – 2 months (NTP 01AUG06) • Re-sequence Beam Transfer Hall – 2 months • Weather Contingency – 2 month • Schedule Mitigation • Develop Early Occupancy Dates • Baseline Construction on Shorter Duration

  9. LCLS CF Construction Schedule Jan 07 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Aug 08

  10. BASELINE FRAG-NET (BEAMLINE)

  11. Level 3 Milestones

  12. Level 3 Milestones

  13. Next 6 Months • CONSTRUCTION • Complete Site Grading • Excavate Undulator Hall tunnel • Excavate Near Experimental Hall, Pour base slab • Excavate and Pour Central Utility Plant base slab • Excavate and Pour Fixed End Enclosure • Form and Pour Beam Dump Slab-On-Grade

  14. Next 6 Months (cont.) • CONSTRUCTION (cont.) • Form and Pour Beam Transfer Hall Slab-On-Grade • Begin Access Tunnel • ADMINISTRATION • Delete Central Lab Office Complex • Complete CF Project Management Documents • Timely Submittal Processing • Process Changes • Enforce Safety Plan • Enhance Coordination with Technical Systems • Monitor Contractor

  15. CF Construction Organization

  16. Issues (and Mitigation) • Encountering Remnant Utilities • Surveys to locate active utilities • Coordination with CEF to review historical records • Trenching to locate abandoned and unmapped utilities • Site Security and Safety • Signing and Fencing • Communication with SLAC residents • All-hands Bulletin • Active Enforcement • Construction Delays • Mitigation Plans in advance • Work-arounds and Re-sequencing • Contingency Plans

  17. Issues (and Mitigation) cont. • CLOC De-scoping • Thorough Scrubbing of CLOC scope items • Definition of Scope Reduction Interfaces • Coordination and Negotiation with CM/GC • Technical Systems Construction Tolerances • Definition of Needs in concert with Tech. Systems • Coordination with Trade Contractor to meet spec. • Preparation of Work Plans to accomplish goals • Increasing Market Costs • Maximize Forward Pricing • Minimize Change Orders • Use Volume Purchasing where practical • Disputes and Claims • Quickly Address Claims • Implement Dispute Review Board Process • Prepare and Use an Issues Resolution Ladder

  18. Summary • Good Progress on all fronts since last review. • CF staff has been strengthened to ensure adequate experience is integrated in all requirements • Continue to Value Engineer • Interface with SLAC, Tech. Systems, CM/GC • Support TCCo and Construction to prevent delays – keep to the schedule. • Complete Development of tools for CF Staff • Team is in place to safely construct the LCLS “house”!