RMS Update to TAC

RMS Update to TAC. September 4, 2008. RMS Update to TAC. August 13 RMS Meeting Summary: http://www.ercot.com/calendar/2008/08/20080813-RMSRMS Voting Items: RMGRR062, AMIT Requested Change to Letter of Authorization Response (update)

margaretan
Download Presentation

RMS Update to TAC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RMS Update to TAC September 4, 2008

  2. RMS Update to TAC • August 13 RMS Meeting Summary: • http://www.ercot.com/calendar/2008/08/20080813-RMSRMS • Voting Items: • RMGRR062, AMIT Requested Change to Letter of Authorization Response (update) • RMGRR063, Mass Transition Revisions Resulting from June 2008 Lessons Learned Workshop (vote) • RMGRR064, Correcting Retail Market Guide for Leapfrog process to Synch up with ERCOT’s system logic (Vote) • SLA Update • AMIT Update • ATF Taskforce • MARS Task Force

  3. RMS Update to TAC • RMGRR062, AMIT Requested Change to Letter of Authorization Response (update) • Requested the TDU wires charges information be excluded from the 12 months usage response information • Due to concerns from multiple market segments about the exclusion, the RMGRR was remanded back to the AMIT for further discussion.

  4. RMS Update to TAC • RMGRR063, Mass Transition Revisions Resulting from June 2008 Lessons Learned Workshop (vote) • Clarifies processes for Mass Transitions to the POLR • Improves clarity and consistency of process • Potential to reduce time Customer is on POLR

  5. RMS Update to TAC • RMGRR064, Correcting Retail Market Guide for Leapfrog process to Synch up with ERCOT’s system logic (Vote) • Correcting/updating the RMG’s documented process will allow Market Participants to better manage the appropriate resolution for Inadvertent Gains when a third Competitive Retailer (leapfrog scenario) is involved.

  6. RMS Update to TAC • RMS requests TAC Affirmative Vote on • RMGRR063 , Mass Transition Revisions Resulting from June 2008 Lessons Learned Workshop and, • RMGRR064, Correcting Retail Market Guide for Leapfrog process to Synch up with ERCOT’s system logic VOTE

  7. RMS Update to TAC • ERCOT 2009 SLA Update • Considerations: • Expanded maintenance windows from 12 to 15 hours on weekend 1 and 2 (reduced from proposed 18 hrs.) • Move Release window from week 2 to week 4 based on less market transaction activity • Reduce Outage window form 36 down to 30 hours • 4 months each year have 5 weekends so add a 12 hour maintenance window • TDTWG to consider in September, RMS will consider in October

  8. RMS Update to TAC • Advanced Metering Implementation Team (AMIT) • Settlement • Interim solution to support 15 minute settlement by July 2009 • MARS Task Force created to address • Long term consideration • ERCOT initiated RFP earlier this summer • Evaluate use of Central Repository rather than multiple TDU locations and methods of communication. • Joint ERCOT and Market Participant selection process • Web Portal Host (s) • Business Requirements and Use Cases have been Defined • RFP in development stage

  9. RMS Update to TAC • AMIT SeptemberSchedule • 3 – Project #5 – Retail Market Interface (RMI) Project • Wed: 9:30-5:30 • Location: ERCOT {7620 Metro Center Dr., Austin, TX 78744} • *16-17 – Project #4 – Retail Market Interface (RMI) • Tue: 9:30-5:30 • Wed: 9:30-5:30 • Location: Public Utility Commission, CHR {1701 N. Congress Ave, Austin TX, 78701} • 22-23 – Project #5 – Retail Market Interface (RMI) • Mon: 9:30-5:30 • Tue: 8:30-4:30 • Location: ERCOT {7620 Metro Center Dr., Austin, TX 78744} • 29-30 – Project #4 – Home Area Network (HAN) • Mon: 9:30-5:30 • Tue: 8:30-4:30 • Location: ERCOT {7620 Metro Center Dr., Austin, TX 78744}

  10. RMS Update to TAC • Acquisitions Task Force (ATF) • ISSUE: No process for transitioning a large number of ESIIDs from one REP to another due to an acquisition. Such a process would allow a REP who is in financial difficulty to sell their ESIIDs to another REP and then quickly transition their Customers to the purchasing REP. This ability could reduce the number of Mass Transitions to POLR experienced by the Market. • PROPOSED SOLUTION: Develop a process for transitioning large numbers of ESIIDs from one REP to another due to a merger or acquisition by leveraging the existing functionality at ERCOT.

  11. RMS Update to TAC • MARS Task Force • Issues: • Start/Stop time on Move-ins/Move-outs • Billing impacts • Settlement and data extract impact • Communication process of 15 minute data from TDSP to ERCOT • DRG with Advanced metering communication, settlement and data extract • Solution: The Market has an objective to support the AMIT defined interim solution by July1, 2009. ERCOT has indicated time to accomplish of 12-14 months from the date of initiation. The focus inherent with a single objective process team is necessary and requires perspective and involvement of ERCOT as well as both the Retail and Commercial Markets.

  12. RMS Update to TAC • On the Agenda for September 10 • Vice-Chair Election • CWG Draft Recommendation for Market Credit Risk Standard Consideration • Revision Requests for Retail Market Guide • Update to Disconnect and Reconnect for Non-Pay • Update to Safety Net Move- In • Adjustments to Market Test Plan for 2008-09 • Review ERCOT 2009 SLA proposal • Review of ERCOT 2nd Q2008 Performance Measures Activity Report

  13. Questions?