An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress and Status Performing Arts Complex

  2. Progression

  3. Theatre Stage 6.25.2013 Company Switches installed a/v cable installed Theatrical cable installed 7.17.2013 Orchestra lift is operational Stage floor installation in progress Coiling fire door at back of stage installed

  4. Theatre Seating Area 6.25.13 drywall complete Tape, bed and float complete First coat of paint installed Knee wall rough in complete 7.17.2013 Wood panels at proscenium wall complete Tape, bed and paint ongoing at knee walls

  5. Recital Hall Seating Area 6.25.2013 Wall have been painted Wood panels at East and West wall complete 7.17.2013 Currently installing perforated Wall Panels Knee wall tape, bed and paint ongoing Eurospan acoustical panel track installed

  6. Recital Hall Lobby 6/25/13 Drywall complete Tape, bed and paint complete Reveals at the wall panels ongoing 7.17.2013 Fixture installation ongoing Wood panel installation ongoing

  7. Theatre Lobby • 7.17.2013 • LEVEL 5 FLOAT AND PRIMER COMPLETE • WOOD PANEL INSTALLATION AT THEATER LEVEL ONGOING • CEILINGS COMPLETE AT STAIR A & B • TERRAZZO ONGOING AT STAIR B 6.25.2013 Drywall complete Tape & bed radius wall complete Prime paint at balcony level Glass rail vertical posts installed

  8. Women’s Restroom - 109 6.25.2013 terrazzo complete 7.17.2013 Light fixtures installed Wall coverings installed Concrete lavs installed

  9. Southeast Elevation 6.25.2013 Face brick and cast stone complete at elevator tower Face brick and cast stone complete at the pavilion Plaster soffit at the east arcade complete 7.17.2013 Planters at east entry installed Monument stairs installed at east entry Moon street sub grade complete west side. Curb, gutter and bus lane installed on west side of moon]

  10. Northeast Elevation 6.25.2013 Entry plaster nearly complete Moon street grade work 90% complete Contech detention unit ongoing 7.17.2013 Contechdetention unit nearly complete Installation of revised sub grade on east side of moon ongoing

  11. Northwest Elevation 6.25.2013 pavers complete at North arcade Plaster at the mansard roof complete Aluminum trellis complete 7.17.2013 Light poles installed and operating Tree installation ongoing

  12. Southwest Elevation 6.25.13 Paver installation ongoing Ribbon curb for pavers complete 7.17.2013 Sound door installation ongoing Tree installation ongoing