1 / 10

US CMS Silicon Tracker : Schedule

US CMS Silicon Tracker : Schedule. J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004. Components. “If they come, we will build it” We do not have direct control but in the past year we have exerted a major influence.

malia
Download Presentation

US CMS Silicon Tracker : Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. US CMS Silicon Tracker : Schedule J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004

  2. Components “If they come, we will build it” • We do not have direct control but in the past year we have exerted a major influence. • Problems with components, many of which were found in the US, led to delays of varying lengths • Module breakage in transport → 2 months • Hybrid Cable problem → +3 months • ST Sensor issues → +5 months • ST sensors are the greatest concern

  3. Current situation • 7000 thick sensors have been ordered from HPK • This was a major achievement in which the US was very active • HPK must know by July if we want to increase this order in order to maintain CMS production without interruption. • This will depend upon whether STM is qualified or not • The agreement with ST • Produce 1000 sensors with final processing by May • CMS to determine if these sensors are acceptable according to a barrage of strict tests • IV,CV with vacuum - Full strip test - Long term test for 72 hours - Proton irradiation of sensors and test structures • Module construction OB1 and OB2 in the US • Studied for sensor related defects, e.g. CMN, unstable current, irradiation of modules, etc. • If acceptance rate <98% order shifts 100% HPK • This plan was presented to STM on March 31st

  4. HPK & STM Dynamic Sharing • HPK plans to reach 1500 sensors/month in July • HPK plan below was established in January at production site in Japan

  5. Front end hybrids As of 3/31/04 1062 good Hy accepted 581 assembled with PA I expect yield to stabilize at ≥ 90%

  6. Rods • Component issues here as well • OptoHybrids • Large quantities already shipped directly to CERN • Frames • 150 delivered • CCU modules are the main issue now. • Require 100/month • Will be reached within 3 months • Mounting/cabling at CERN • Can reach production rate of 50 rods/month • US could conceivably help here if necessary

  7. A Battle Hardened Schedule

  8. US Module Production(as determined by A. Cattai, J. Incandela, S. Schael) • This is our current module production schedule: • USA module final production • TOB modules: Early June 2004 to May 2005 • TEC modules: Late June 2004 to mid-April 2005 • Paced by sensors • Our colleagues appreciate that we must get all sensors for US production according to a schedule, with significant contingency, that allows us to complete all modules in FY05

  9. Other Considerations • Rods are expected to keep pace with module assembly • Schedule for integration of rods on wheels has slipped • US involvement in I&C was scheduled for second half of FY04. • Now expect no significant US involvement before second half of FY04 • Most system integration will likely occur in FY06 – our M&O start year • Also, having developed extremely high production capacities, we have recently analyzed all systems for potential failures that would lead to downtime in production • Ordered and stocked critical spares of fabrication tooling and equipment • Cross-training fabrication personnel to maintain depth at each station • Additional satellite processing capacity in Mexico • Specialized testing and diagnostics capabilities at UC Riverside • Particularly important to remove this work from the production lines where it could be a distraction, leading to disruptions

  10. Conclusions • A last round of problems surfaced in late FY03 early FY04 • More delays have resulted • A Major US push - intense, concentrated, exhausting - with similar contributions by many groups in the tracker collaboration got us over the final hurdles for modules • Schedule is the first in which I have a high degree of confidence • Based on component production rates that have been demonstrated by our vendors and module production rates that we have comfortably demonstrated • We also have explicit fallback plans and contingency • 5 months contingency remain for completion in FY05 • We can survive ‘typical’ production problems • A very serious problem could jeopardize our FY05 target

More Related