180 likes | 402 Views
Agenda. Benefits of Change AuditKey ChallengesBusiness Case ReportingOverall AssessmentsCollaborative WorkingKey SuccessesQ
E N D
1. Barclays Internal AuditHow can you help Change Programmes to deliver…? BANKING AND FINANCIAL SERVICES INTERNAL AUDIT GROUP
30th January 2008
Chrissie Renyard – Audit Manager
2. Agenda Benefits of Change Audit
Key Challenges
Business Case Reporting
Overall Assessments
Collaborative Working
Key Successes
Q&A’s Strategic Change
Project Failure Statistics
Examples of Project Failure
Key reasons for Project Failure
Change Audit – Mission
Key Project Management Risks
Key Project Lifecycle Risks
3. Strategic Change Boards are increasingly making commitments to achieve business results through programme outcomes
These commitments are delivered through projects with project outputs articulated as benefits in a business case
For those organisations that measure benefits, on average they are 25% behind their original portfolio commitment
Only 2% of organisations achieved targeted benefits all the time
In addition to the the top line being affected customers are often impacted by the costs of failure!
Source: KPMG Assurance Services
4. Project Failure Statistics Across all industries, project performance is generally poor:
53% of all projects are delivered late, over budget & with reduced benefits
18% of all projects fail - cancelled prior to completion
Only 52% of required features & functions make it to the released product
56% of firms wrote off at least one project with average loss incurred of 8m
60% of firms experienced difficulty in identifying key project requirements
Only 29% of all projects succeed - on time and on budget with the required features and functions
Source: Deloitte Assurance Services
5. Examples of Project Failure The Channel Tunnel
Initial cost £4 billion - final cost £7.5 billion
Canary Wharf
Initial cost £1.7 billion - final cost £2.8 billion
Euro Disney
Initial cost £1.3 billion - final cost £2.3 billion
Swanwick Air Traffic Control Centre
Initial cost £300 million - final cost £600 million
The ‘state of the art’ operation delivered six years late!
6. From The TimesJanuary 29, 2008 Taxpayers face £500m bill for BAE projects Two of BAE Systems’ flagship projects have experienced a massive budget blowout over the past two years, leaving British taxpayers facing a £500 million bill. BAE was forced to write off £800 million in 2003 after delays to Astute and Nimrod, the coastal surveillance aircraft, became so severe that the contracts had to be renegotiated. According to the select committee, the four Astute submarines will now cost £3.79 billion against an initial budget of £2.58 billion, a 47 per cent increase. The six Daring-class destroyers will cost £6.46 billion compared with an initial estimate of £5.47 billion, an increase of 18 per cent. The destroyers will enter service two years late and the submarines at least six years late. James Arbuthnot, the committee chairman, said: “We do not understand precisely where these extra costs are coming from and we are disappointed that the MoD has failed to limit the increases. We want more clarification on why these projects are getting more expensive.”