This management report covers the progress and deviations of all three projects at Assimila Limited, outlining delays and reasons behind them, including recruitment and compassionate leave issues. It provides an overview of the current situation and project status.
E N D
Management report Zofia StottJon Styles Assimila Limited
Overview • KO 27 March 2012 • All three projects making good progress • Work packages remain relevant, achievable within resources available • All contracts signed • Deviations since KO relate to schedule • Delay in PM1 by 3 months • Projects are ~3 months behind initial schedule • Main reason: recruitment • Additional delay in “Interfacing EO” project due to Professor Lewis compassionate leave • WP3.1 EO-LDASV1 software development