HF FE schedule. Ulrich Heintz Brown University. QIE10 production. June 2014: submitted engineering run includes QIE10 and QIE11 chips September 2014 : expect delivery of chips One wafer will be packaged for preproduction boards December 2014: bench testing complete
E N D
HF FE schedule Ulrich Heintz Brown University Ulrich Heintz - HF FE schedule
QIE10 production • June 2014: submitted engineering run • includes QIE10 and QIE11 chips • September 2014: expect delivery of chips • One wafer will be packaged for preproduction boards • December 2014: bench testing complete • February 2015: packaged chips delivered • April 2015: robot chip testing complete • production QIE10 ASICs available for shipment Ulrich Heintz - HF FE schedule
prototype phase • backplane & crates • done – start production of backplanes following today’s review • QIE cards • July 2014: revised QIE card design complete • September 2014: preproduction QIE cards (US) • November 2014: preproduction QIE cards from Turkey/Brazil • ngCCM • September 2014: IGLOO2 mezzanine design complete • October 2014: preproduction ngCCM • calib module • September 2014: prototype of pulser and light distribution system • December 2014 – electronics system review of HF FE Ulrich Heintz - HF FE schedule
production phase • January 2015 – start of production • frontend crates & backplanes (Brazil) • April 2015 – could be earlier (backplane design ready/crates are off the shelf) • QIE cards (Brazil & Turkey) • need packaged and tested QIE10 chips (April 2015??) • July 2015 – QIE cards at CERN • acceptance testing at CERN bat. 904 • calibration system (Brazil) • April 2014 – light mixer shipped to Brazil (US) • July 2015 – calib modules at CERN • ngCCM(US) • August 2015 – ngCCMs at CERN Ulrich Heintz - HF FE schedule
burn-in and installation phase • August 2015 assemble crates in bat. 904 • Aug – Dec 2015 burn-in • December 2015 start installation • February 2016 installation complete • March 2016 commissioning complete Ulrich Heintz - HF FE schedule