slide1 l.
Skip this Video
Loading SlideShow in 5 Seconds..
Building Commissioning: Cx 101 PowerPoint Presentation
Download Presentation
Building Commissioning: Cx 101

Loading in 2 Seconds...

  share
play fullscreen
1 / 20
Download Presentation

Building Commissioning: Cx 101 - PowerPoint PPT Presentation

lexiss
119 Views
Download Presentation

Building Commissioning: Cx 101

- - - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

  1. Building Commissioning: Cx 101 Brock Graham, Gilbane Building Co. Michael Gannon, BVH Integrated Services November 15, 2010

  2. Building Commissioning… Where did it come from ? ASHRAE ? LEED ? Federal Gov’t ? USGBC ? ASME/ANSI ?

  3. The United States Navy … U.S.S. Theodore Roosevelt (CVN 71) Commissioned October 1986

  4. Building Commissioning… What is it? Retro-commissioning (existing buildings) Re-commissioning (existing buildings) Commissioning (new construction)

  5. Building Commissioning… What is it? The short answer: Building commissioning (new construction) is construction quality assurance

  6. Building Commissioning… Different ‘levels’ of Cx (and cost)… Minimal: Start-up & troubleshooting Typical: LEED Cx on Steroids: HPB & ASHRAE Guideline 0

  7. Commissioning: Why do it? • High performance building standards require…buildings to perform. • Commissioning provides the assurance that buildings are built and perform as intended.

  8. Commissioning Process Overview: • Design Phase • Construction Phase • Acceptance Phase • Occupancy Phase

  9. Design Phase: • Review or assist in development of • OPR and BOD • Peer review • Sometimes at many stages (SD, DD, CDs) • Initial schedule development (CM) • Commissioning Specification • Very important!

  10. Construction Phase: • Submittal reviews • Develop Cx Plan • Kick-off with installing contractors • Installation observation • Contractors fill out pre-functional checklists

  11. Construction Phase (cont.): • Further develop schedule with GC / CM • Pre-balancing meeting • Proactive Field Quality Control • Installation observation • Witness some testing • O&Ms submitted and reviewed

  12. Construction Phase (cont.): • Prefunctional checklists – developed by CxA, filled out by contractors • Not to be confused with functional test sheets • Manufacturer’s start-up of equipment

  13. Acceptance Phase: • Functional testing begins (when systems are complete!) • A ‘test case’ system can be commissioned to let contractors know what to expect • This should be coordinated and witnessed by CxA, not installing contractors. • Deficiencies recorded and tracked by CxA

  14. Acceptance Phase (cont.): • Contractors correct deficiencies and notify CxA of correction • CxA retests and records results • Contractor-provided Owner training is organized and verified • Validation (if called for) follows functional testing

  15. Occupancy Phase: • Functional testing continues (realistically) • CxA develops Systems Training Manual (aka the Recommissioning Manual) • Owner personnel trained by CxA • Final commissioning report produced

  16. Occupancy Phase: • Deferred (seasonal) testing • End-of-Warranty Review • Post-occupancy performance verification • Needs to be addressed in design phase (e.g. are enough ATC points and / or energy meters specified to capture all usage)

  17. Commissioning Scoping • Identify Cx Scope clearly • Typical systems include: • All HVAC (some sampling possible) • Plumbing (DHW, CA, Pumps, etc) • Electrical (lighting controls, E-power and E-lighting, etc) • Other systems: • Fire alarm, fire protection • Security, data, PA, envelope, elevators…

  18. Commissioning Scoping • Peer Reviews • Early docs (SD, DD) don’t have as much to review • Allow time in schedule for reviews and doc updates by EOR

  19. Commissioning Scoping • How much should you expect to pay? • 0.5% to 3% of total construction cost • 3 to 5% of total operating cost (retro) to 5% of total construction cost (validation) • 2 to 3% of mechanical systems cost + 1 to 2% of electrical systems cost • It Depends on the CxA scope, as defined by the Owner

  20. Questions?