1 / 21

European Energy Megaprojects Report Results from a Multi-Case Study

by Dr. Giorgio Locatelli Dipl.-Ing. Paul Littau. European Energy Megaprojects Report Results from a Multi-Case Study. Content. 1. Introduction. 2. Research Questions & Methodology. 3. Results. 4. Conclusions. Introduction.

kolton
Download Presentation

European Energy Megaprojects Report Results from a Multi-Case Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. by Dr. Giorgio Locatelli Dipl.-Ing. Paul Littau European Energy MegaprojectsReport Results from a Multi-Case Study

  2. Content 1. Introduction 2. Research Questions & Methodology 3. Results 4. Conclusions

  3. Introduction • Megaprojects: extremely large-scale investment projects – typically: more than EUR 0.5 billion • In EU Megaprojects planned, or are in the execution or delivered • Many of them are power plants and capital intensive • Because of bad performance the EU financed the COST Research project aiming "to understand how megaprojects can be designed and delivered more effectively to ensure their effective commissioning within Europe" • This document present the methodology used in the COST action and the results related to the Energy group

  4. Content 1. Introduction 2. Literature & Methodology 3. Results 4. Conclusions

  5. Literature & Methodology • Megaproject have high degree of uniqueness, "white elephant" • Megaproject usually are late and over budget (Cantarelli et al., 2012) • Few of them are successful (Giezen, 2012) • Once completed usually provide benefit less than what was expected (Flyvbjerg, 2006) • Still not clear which aspects make a project successful

  6. Literature & Methodology • Cross case analysis (REF) • Protocol • Definition of a common template for all the researchers involved • For each project data collection according to the template • Competition of the template areas with enough data • General overview at project level and lesson learned • Data organisation in an excel spread sheet • Statistical analysis (Fisher exact test) • Result analysis • Investigation of the most relevant variables. • Eisenhardt (1989):“researchers should stop adding cases when theoretical saturation is reached […] incremental learning is minimal because the researchers are observing phenomena seen before […] the incremental improvement in its quality is minimal.”

  7. Content 1. Introduction 2. Literature & Methodology 3. Results 4. Conclusions

  8. Results

  9. Results: delayplanning Correlations: • more than 50% share of the client is under government control (p-value 17%)correlates with not delaying in planning phase • A possible explanation: if the main shareholder is the government itself, then its plans are very likely to meet requirements of local and regional authorities. • the client and owner are different (p-value 5%), correlate with not delaying in planning phase • (Possible explanation and CASE).

  10. Results:delayconstruction (1/3) Correlations: • the presence of one major stakeholder (p-value: 5%) • Possible Explanation: HERE Examples: • Flamanville 3: main contractor, EDF (Électricité de France) is client and project owner and caused authorities to stop construction works for a month. • Olkiluoto3 (nuclear power plant): turnkey contractor Areva was responsible for problems that led to construction delays

  11. Results: delayconstruction(2/3) Correlations: • Project is supported financially by the EU correlated to not delaying in construction phase (p-value 7%). • Possible explanation: demanding approval process required by the European Union before funding an energy project could motivate the EPC-company to increase the quality of plans and cost estimations • Examples: • Andasol project • AnholtOffshore project.

  12. Results: delayconstruction(3/3) Correlations: • Tough physical environmental conditions are correlated to not delaying in construction phase (p-value 18%). • Possible explanation: tough physical environmental conditions are (explanation + CASE)…

  13. Results: overbudget Correlations: • Project has been delayed by the authority (p-value 20%) Example: • Moorburgpower plant project: problems with the environmental requirements, led to a construction of an additional cooling tower which caused a huge cost increase • fact that the project is a nuclear power plant (p-value 17%). • Possible explanation is provided by G. Locatelli & M. Mancini (2012): Flamanvilleand Olkiluoto 3 showing that the budget overrun is mainly caused by too low original estimations

  14. Results Common sense independent variables not correlated • Some independent variables are presented which surprisingly do not correlate to common-sense-expectations regarding the performance of megaprojects. • First of a kind (FOAK) • FOAK-megaprojects tend to be over budget and delay (REF), • In sample one might expect that FOAK-megaprojects in the energy sector also might perform badly. But results are showing, that … • Thus, XY proofs that • Mono cultural • Mono cultural are expected to perform better, because of cultural barriers (Anbari et al., 2004). • Analysed sample does not show relevant correlations

  15. Results Common sense independent variable not correlated (continued) • The project is modular • Modular projects are expected to reduce project complexity (especially in megaprojects) and thus increase project performance (REF). • Analysis: no such correlation • Local residents were involved in the project • In many cases: local residents try to stop the project • Communicating with critical stakeholders and to integrating them into the project could should increase their support of the project • Not found any relevant correlation

  16. Results – Don‘tdo‘s

  17. Content 1. Introduction 2. Literature & Methodology 3. Results 4. Conclusions

  18. Conclusions • Despite the media coverage focused on projects over budget and late there is a clear evidence that it is possible to successfully deliver energy megaprojects in Europe • The statistical analysis shows which project characteristics are correlated to project performance • Internal and external stakeholders play a major role toward project success • A well designed project governance is critical success factor

  19. Further developments • To deep the analysis among the statistical correlated variable to investigate the causation. • Test 3 level (e.g. the different technologies) using the chi-squared test. • Enlarge the analysis to the infrastructure life cycle with a particular focus on the benefit delivered. • There are several specific areas (like stakeholders management and governance) deserving a specific investigations. A further step in the research should be the cross-case analysis on them.

  20. References Anbari, F. T., Khilkhanova, E. V., Romanova, M. V., & Umpleby, S. A. (2004). Cross Cultural Differences and their Implications for Managing International Projects. Journal of International Business Ethics. Flyvbjerg, B. (2006). From nobel prize to project management: getting risk right. Project management Institute, 37(3), pp. 5-15. Giezen, M. (2012). Keeping it simple? A case study into the advantages and disadvantages of reducing complexity in mega project planning, International Journal of Project Management, Volume 30, Issue 7, October 2012, Pages 781-790. Cantarelli, C.C., Flyvbjerg, B., Buhl, S.L. (2012). Geographical variation in project cost performance: the Netherlands versus worldwide, Journal of Transport Geography, Volume 24, September 2012, Pages 324-331, Eisenhardt, K. M. (1989). Building Theories from Cases. The Academy of Management Review , Vol. 14, No. 4 (Oct., 1989), pp. 532-550

  21. END

More Related