Far Experimental Hutches. David Saenz Project Manager. Far Experimental Hall Hutches. Scope Design Status/Deliverables Schedule Estimated Construction Cost Present Status Summary. Scope. Approximately 7,800sf of new facilities for three Hutches, Control Rooms and Common Rooms

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Far Experimental Hutches' - kirti


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
far experimental hutches

Far Experimental Hutches

David Saenz

Project Manager

far experimental hall hutches
Far Experimental Hall Hutches
  • Scope
  • Design Status/Deliverables
  • Schedule
  • Estimated Construction Cost
  • Present Status
  • Summary
scope
Scope
  • Approximately 7,800sf of new facilities for three Hutches, Control Rooms and Common Rooms
  • Current approved specifications are well defined and present no major challenges
scope cont d
Scope – Cont’d

1 ton capacity cranes

Radiation protection

Standard door sizes

Existing common floor

Standard wall/ceiling finishes

No acoustic requirements

  • Utilities (MEP)
    • Process chilled water
    • Chilled water
    • Compressed air @ 100psi
    • HVAC 72°± 1 °F
    • RH 45% ± 10%
    • 24” cable trays
    • Standard lighting
    • Surface mounted conduits
    • Standard 110V and 208V outlets
engineering specification documents
Engineering Specification Documents
  • LCLS ESD’s approved by key stake-holders.
    • ESD 1.9-112
      • Hutch 4
    • ESD 1.9-113
      • Hutch 5
    • ESD 1.9-114
      • CXI Room
    • ESD 1.9-115
      • XCS Room
    • ESD 1.9-116
      • Common Room
    • ESD 1.9-117
feh looking west
FEH (looking west)

Existing utility systems in place

feh floor plan section by dga
FEH Floor Plan/Section by DGA

Floor Plan

Building Section

design status
Design Status
  • Design was awarded Oct 10, 08
  • Title I completed on Nov 6, 08
    • Internal design review currently in process and will be completed on 11/13/2008
  • Title II 60% scheduled for Jan 15, 09
  • Title II 90% scheduled for Feb 25, 09
  • Title II 100% scheduled for Mar 4, 09
design deliverables
Design Deliverables

√ Existing Conditions Report

√ 30% Design Review

√ Structural Design Review

√ Preliminary Cost Estimate

60% Design Review

Detailed Cost Estimate

90% Design Review

Engineering Coordination Presentation

Updated Cost Estimate

100% Design Review

Final Cost Estimate

Issue of Issue For Construction (IFC) documents

Value Engineering

  • All deliverables are expected to be provided on time!
  • Sufficient quantity of deliverables are established to manage progress and complete development
construction schedule
Construction Schedule
  • 9 months including pre-construction activities to commence Mar 09 and complete Dec 09
  • Need to revise schedule to reflect construction award Mar 09 for major packages
estimated construction cost
Estimated Construction Cost
  • Initial estimate provided by AE valued at $3.6M
    • Includes direct and in-direct cost and escalation
  • Strategy for construction delivery method is consistent with expectations
    • Design → Bid → Build
  • Current WBS (1.9.3.14.2) budget is $4.1M (including contingency)
summary
Summary
  • Design parameters are clearly defined
  • Sufficient quantity of deliverables are in process
  • Title I complete
  • Title II in process
  • AE firm has provided alternatives solutions for higher priced items i.e. structural steel