Dive into the material and work-in-progress turnover days data for March 2014 at a power plant. Explore the decrease in material costs compared to February 2014 and the reasons behind it, including adjustments in electronic, mechanical, magnetic, and small plate materials. Discover insights from the inventory aging and structure analysis for the month.
E N D
一電廠2014/03/31(材料+WIP)存貨週轉天數 ※ 2014年3月材料金額: 230,547KNTD ; 2014年2月材料金額: 247,283KNTD 。 2014年3月 與 2014年2月相比較,材料金額減少:16,736 KNTD。 ※ 主要原因說明: 陸續消化春節前後物料供應之BUFFER庫存 。減少金額如下: ____電子料: 9,231KNTD; ____機構類: 4,228KNTD ; ____磁性類: 1,515KNTD ; ____小板: 5,339KNTD。