Operating Reserve Min Run Time Violation & Partial Self Schedule Continued Discussion and Vote. Shannon L. Hann Markets Committee Meeting August 9, 2004. Agenda. Min Run Time Violation Review of what has happened since last MC discussion Review of current OR Treatment
E N D
Operating ReserveMin Run Time Violation &Partial Self ScheduleContinued Discussionand Vote Shannon L. Hann Markets Committee Meeting August 9, 2004
Agenda • Min Run Time Violation • Review of what has happened since last MC discussion • Review of current OR Treatment • Proposed OR Treatment of each type of Min Run Time Violation • Partial Self-Schedule • Explanation • Example
Actions since last MC Meeting • Reviewed proposed changes taking into account Participant’s comments • Met with MMM to discuss gaming concerns • Re-examined the four different scenarios of when a generator doesn’t complete min run time
Presented to MC on 7/13 Current • If a generator does not complete its minimum run time it is set ineligible for RT Operating Reserve Credits (Startup, No Load, Incremental Energy).
Scenarios Presented to MC on 7/13 • Generator requests to waive it’s Min Run Time, and the ISO system operators agree to the shut down • ISO orders unit to come offline for reliability before min run period is completed • Unit trips off line before completing min run period • Unit request to waive it’s Min Run Time and ISO system operators do not agree to shut down.
Example: Partial Startup Costs • Generator completed 3 out of 4 hours of it's Minimum Run Time before coming offline. • If the early shutdown was approved or ordered by the ISO, the unit remains eligible for the entire Startup cost. • If the early shutdown was a trip, the unit will remain eligible for a portion of it's Startup cost as follows: • Startup costs = (Hours On/ Min Run Time * Startup) • Startup costs = ( 3 / 4 * $1,000) = $750.00 • If the early shutdown was requested by Participant and not granted by ISO: Unit is flagged Failure to Follow (pro-rated Startup, no No-Load and no IE.)
Partial Self Schedule (SS) • Current • Any hour that contains a single self-scheduled MW is considered ineligible for Operating Reserve Credit. • Proposed • Provide Operating Reserve Credit eligibility for MW’s that are pool scheduled above a unit’s Self-Schedule. New eligibility will only apply to incremental energy. It will not apply to Startup and No Load. • Benefit • Allows generators to receive Operating Reserve Credit for MWs dispatched at the Pool’s discretion.