Lab # 2. Creating a Task List. Task. Tasks are the most basic building blocks of any project Task represent the work to be done to accomplish the goals of the project Task describe project work in terms of sequence, duration and resource requirements. Task.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Lab # 2' - kelly-kirk


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
lab 2

Lab # 2

Creating a Task List

slide2
Task
  • Tasks are the most basic building blocks of any project
  • Task represent the work to be done to accomplish the goals of the project
  • Task describe project work in terms of sequence, duration and resource requirements
slide3
Task
  • Each task has a unique ID number, but it does not necessarily represent the order in which task occur
  • By default the task start date is the same as the project start date and the one day for the duration
task duration
Task Duration
  • Task duration is the amount of time you expect it will take to complete the task
  • You can work with task duration on the scale of hours, days and weeks (m,h,d,w,mo)
  • The question mark in the duration field indicates that the duration is an explicit estimate
task duration1
Task Duration
  • 8/80 rule suggests that task duration between 8 hours and 80 hours are generally sized to a manageable duration
milestone
Milestone
  • Milestones are significant events that are either reached within the project or imposed itself
  • It represented as task with zero duration
summary task
Summary task
  • It is helpful to organize groups of closely related tasks that represent a major portion of the project’s work into phases
  • For the summary task you can’t edit it’s duration , start date or other calculated value directly
top down bottom up planning
Top- Down & Bottom– Up Planning
  • Top- Down Planning from general to specific
  • Bottom– Up Planningfrom specific to general
linking tasks
Linking tasks
  • Sequence: is the second task must occur later than the first task
  • Dependency: is the second task can occur only if the first task is completed
  • Predecessor successor
linking tasks1
Linking tasks
  • Finish-to- start FS
  • Start- to- start SS
  • Finish-to- finish FF
  • Start-to- finish SF
documenting task
Documenting task
  • You can record additional information about task in a note
  • There are three types of note : task notes, resource notes and assignment notes