Financial Report 3 Nicosia 27th September 2013 Michaela Novotna InnoFunFinancialManager JAIP novotna@jaip.cz
What was done Report was finished on time – 23th September 2013 12 partners reported their costs Total amount reported – EUR 191 023,47
Budget changes Each partner proposed the requirements, how to change their budget It was till 10 % of shifting between items in total The budget of UK CEED was transfered to the budget of Opportunity Peterborough EC signed new Application Form just with 13 partners
4th reporting period Duration: 1. 7. 2013 – 31. 12. 2013 Deadline for certificates: 15th February Partners with Pilot action: spending cost for EQUIPMENT asap!!