An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Cell Controller Pilot Project (CCPP):From Surviving System Black-Outto Market Support • Energinet.dk • Spirae Inc • Energynautics GmbH • SE MARTENSEN – DE – Session 4 – 1221

  2. CCPP: Background • Blackout experience due to transmission system failure • Large amount of Distributed Energy Resources in Denmark • Further increasing share of renewable energy sources in the future MARTENSEN – DE – Session 4 – 1221

  3. CCPP: Objectives • Surviving transmission system black-out by safely transitioning into island operation • TSO support: Virtual Power Plants for active and reactive power independently • DNO Support: Advanced voltage control • Platform for market aggregators of distributed generation resources MARTENSEN – DE – Session 4 – 1221

  4. CCPP: The Pilot Cell • 60 kV grid cell below one 150/60 kV transformer • 13 each 60/10 kV substations with tap changer controlled transformers • 5 CHP plants / 15 synchronous generators, total installed capacity of 32.5 MW • 47 Danish-style wind turbines, total installed capacity of 37 MW • Rural area, villages and small cities (>1000 km²) MARTENSEN – DE – Session 4 – 1221

  5. CCPP: Project Status • Started in 2005 • Field Tests with reduced-sized Cell in 2008 • Grid-connected and island functions • Field tests using the entire Cell in 2010 • Grid-connected functions • Final field tests using the entire Cell in 2011 • Grid-connected and island functions MARTENSEN – DE – Session 4 – 1221

  6. CC Functions: Market Operations • To be used by Power Balance Authorities • Group and dispatch of CHPs or Wind Turbines • Multiple Markets: • Day-ahead scheduling • Merit order dispatch based on price information • Up-regulation and down-regulation • Automatic dispatch validation against power system/component limits MARTENSEN – DE – Session 4 – 1221

  7. CC Functions: DNO Voltage Control • Conventional distribution systems use only transformer tap changers for voltage control. • The Cell Controller uses reactive power setpoints of distributed energy resources first, where available. • Reduced wear on tap changers • Smoother voltage for consumers and generators MARTENSEN – DE – Session 4 – 1221

  8. CC Functions: TSO Virtual Power Plants • Controlled load flow at single point of connection • Active Power VPP • Automatic asset dispatch to meet setpoint • Disables Market Operations • Reactive Power VPP • Uses assets dispatched by other means • Reduces voltage control to tap changer control • Consideration of local system/component limits MARTENSEN – DE – Session 4 – 1221

  9. CC Functions: Emergency Island • Based on receipt of external trigger signal • Balance load and generation • Load/generation shedding if necessary • Open the Cell circuit breaker (within <5 seconds) • Automatic voltage & frequency control in island • Automatic load restoration • Resynchronization MARTENSEN – DE – Session 4 – 1221

  10. Field Tests 2010: DNO Voltage Control MARTENSEN – DE – Session 4 – 1221

  11. Field Tests 2010: Reactive Power VPP MARTENSEN – DE – Session 4 – 1221

  12. Field Tests 2010: Active Power VPP MARTENSEN – DE – Session 4 – 1221

  13. Conclusions • All originally envisioned functions implemented and tested in simulations and in the field • Grid-connected functions working in 2010 • Minor improvements for 2011 • Grid-connected functions comprehensively field tested in May 2011 with success • Island functions to be field tested in June 2011 MARTENSEN – DE – Session 4 – 1221

  14. Outlook • Cell Controller Pilot Project is concluded with final field tests 2011. • Possible further deployment of the Cell Controller system on the island of Bornholm • Future distribution systems will provide further/improved distributed control resources that can be utilized by the Cell Controller. MARTENSEN – DE – Session 4 – 1221