Nationwide Differential Global Positioning System (NDGPS) Status. Presentation to : Civil GPS Service Interface Committee (CGSIC) U.S. States and Localities Subcommittee (USSLS) USCG ISC New Orleans July 8, 2008 Timothy A. Klein Senior Policy Advisor/RITA NDGPS Coordinator NDGPS@dot.gov.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Nationwide Differential Global Positioning System (NDGPS) Status' - jonny


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Nationwide differential global positioning system ndgps status
Nationwide Differential Global Positioning System (NDGPS) Status

Presentation to:

Civil GPS Service Interface Committee (CGSIC)

U.S. States and Localities Subcommittee (USSLS)

USCG ISC New Orleans

July 8, 2008

Timothy A. Klein

Senior Policy Advisor/RITA NDGPS Coordinator

NDGPS@dot.gov


Brief program history
Brief Program History Status

  • Inland NDGPS Augmentation Developed as Extension of Maritime DGPS

    • Provides real-time differential correction; proven sub-meter accuracy; 99%+ availability

    • Provides single coverage on the ground over 92% of CONUS and double coverage over 65% of CONUS

    • Authorized in 1988 (P.L. 105-66); operated by U.S. Coast Guard under multiagency MOA

    • DOT funded from multiple agencies under FRA program management ($53M, FY98-06)


Brief program history 2
Brief Program History (2) Status

  • The NDGPS Assessment

    • FY07: “zeroed out” of FRA budget

    • October 2006: PNT EXCOM action – “DOT complete assessment of the need for inland component of NDGPS”

    • FY07/08: RITA assessment in support of EXCOM action

      • Federal Register Notice

      • Independent Assessment (ARINC)

      • Letter to Agencies

    • Recommendations accepted by ESG; 01/23/08

    • Endorsed by EXCOM; 03/20/08


National space based pnt execcom action
National Space-Based PNT ExecCom Action Status

  • Action: DOT complete assessment of the need for inland component of NDGPS

    • Final resolution to be determined by:

      • interagency requirements

      • level of support

    • If there were no transportation requirements or other Federal user requirements, DOT intended to develop decommissioning plan for NDGPS

    • DOT cost share with other agencies possible if there is a transportation requirement


Assessment affirms requirements
Assessment Affirms Requirements Status

  • Assessment affirms operational requirements for inland NDGPS

    • Transportation operational requirements:

      • Federal Highway Administration (FHWA)

        • on behalf of state and local DOT stakeholders

        • routine use in Federal-Aid Program

        • survey, construction, quality, asset management

      • Federal Railroad Administration (FRA)

        • safety system requirements (positive train control, track defect location)

      • Association of American Railroads

        • baseline reference for positive train control

      • National Governor’s Association

        • use by state DOTs, resource management


Assessment affirms requirements 2
Assessment Affirms Requirements (2) Status

  • Assessment affirms operational requirements for inland NDGPS

    • Other Federal operational requirements:

      • Department of Agriculture (NCRS, Forest Service)

        • High-accuracy positioning/repeatability

        • Fire services and enforcement

      • Department of Commerce (NOAA – NWS, NGS)

        • Continuously Operating Reference Stations

        • Weather forecasting

      • Department of the Interior (BLM, NPS, USGS)

        • High-accuracy positioning

        • Fire services and enforcement

      • Numerous natural resource stakeholders


Assessment affirms requirements 3
Assessment Affirms Requirements (3) Status

  • Assessment affirms operational requirements for inland NDGPS

    • State/local and private sector operational requirements:

      • Civil GPS Services Interface Committee (CGSIC) U.S. States and Localities Subcommittee

        • State Departments of Transportation, Natural Resources, Environmental Protection, Agriculture, Parks

        • Multiple states and counties also responded

      • Private/Non-Profit Requirements

        • U.S. GPS Industry Council

        • National Precision Farming Association

        • Professional Land Surveyors


Assessment affirms requirements 4
Assessment Affirms Requirements (4) Status

  • Assessment results affirm research needs for inland NDGPS

    • Transportation research requirements:

      • Federal Highway Administration (FHWA)

      • Federal Railroad Administration (FRA)

      • Association of American Railroads

      • Alliance of Automobile Manufacturers

      • Advocates for Highway and Auto Safety

  • Assessment affirms no other existing PNT augmentation meets accuracy requirements for multiple terrestrial applications


Recommendations accepted by esg
Recommendations Accepted by ESG Status

  • Ratify inland NDGPS as a national utility

    • Reaffirm DOT sponsorship

    • Determine funding required to deploy IOC/FOC

  • DOT to lead interagency team to develop new program and business plan

    • Jointly develop a fund-sharing mechanism among Federal Agencies with requirements

    • Inclusion in Department/Agency FY10 budgets required

      • System at risk due to deferred equipment refresh

      • Free of user fees, per U.S Space-Based PNT Policy


Nationwide differential global positioning system ndgps status

NDGPS Funding, FY 08-09 Status

  • DOT/RITA FY08 Funding = $4.6M

    • RITA agreed to be interim program sponsor

    • Existing system operations and Maintenance

      (O&M) only

    • No construction/expansion/upgrade for NDGPS sites in FY 07/08

    • Pass-through to U.S. Coast Guard for O&M

  • DOT/RITA FY09 Funding = $4.6M

    • Pass-through to U.S. Coast Guard for O&M

    • Insufficient to meet O&M requirements


Nationwide differential global positioning system ndgps status

Projected NDGPS Funding Needs: StatusFY09 + Recapitalization[USCG+DOT Estimates]

  • FY09 Shortfall

    • $4.6M as placeholder; insufficient for O&M

    • Shortfall ~ $0.8M

  • Recapitalization (required in FY09 for any operational scenario)

    • $3.5M

      • Equipment refresh required for ongoing operations (deferred maintenance)

      • Three years behind Maritime DGPS

      • Future estimates based on completing recapitalization (proven reduced O&M costs)

  • Total Additional Need: $4.3M


Nationwide differential global positioning system ndgps status

Projected NDGPS Funding Needs: FY10 and Outyears Status[USCG+DOT Estimates]

  • Current System; no build-out

    • $5.9M average annual operations and maintenance (O&M) only

  • Complete Initial Operating Capability (IOC) – 8 sites

    • $3.4M capital costs

    • $6.2M annual (O&M)

  • Complete Full Operating Capability (FOC) – 20 sites

    • $19.0M capital costs

    • $6.5M annual O&M