An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. pawel de barbaro Sx5hcal status, plans June 8, 2006

  2. 1. water cooling • hb is completed • he is completed • ho: hooked up, need to turn on YB+2 • need to hook up yb0 and yb1 to HB system, • we will use HB+ sectors 12 and 13 when boxes are installed

  3. 2. N2 inertion • install reducers on HB • he: hookup between wall and manifold, install reducers • ho: yb1 and yb0 needs special solution • need to verify pressure of N2 in sx5 (andre lyonnet)

  4. 3. high voltage • hb done, all the way to gb • he: cables from green barrack to splice box need to be installed • HO: also at the end going thru splice box, until magnet close, it goes thru independent p. supply

  5. 4. dcs • HB+ dcs testeed on thursday afternoon • need to connect HE+ to dcs computer in gb

  6. LV on HBmtcc turned on

  7. 5. low voltage-hardware • still short of one 3016 and one 3486 (we will temporarily borrowed one 3016 from HE+/near to HB+) • all five racks need to be air-cooled, two HE racks are already Ok, other 3 need to be closed • we will pull 48V power cable straight from bb to YB+2 • still to bring cables from p. panel on the wall to easy crate

  8. 6. low-voltage-pvss • first version exists, german preparing upgrade • there is no framework for 3486. • delay swap to central dcs, until it is completely ready • we need to get info on pump room from central dcs pvss

  9. 7. source drivers • software on dcs completed • need to connect HE+ driver to air pressure • cable from interface box to PC can not be screwed in, need to attach it • air driver on HB+ needed to be removed, until TK cabling is done

  10. 8. laser • would like to test it within a week, next priority after LV is done • clean up laser hut (ZEC?) • key for laser room, laza has the number, one needs to request key from natasha in cms secretariat

  11. 9. dss • if our dcs is dead (no heart beat in 2min) central dss will send signal to stop LV • if temp too high, we cut of LV (sergey prepares the device from HE-)

  12. 10. sx5-bbgb cabling • what we need to do: • HV for HE+, entire HO • buy 200m of PMA tube, 4cm dia, divisable

  13. 11. beyond HTR inputs • jeremy coming this weekend to work on switching to central daq

  14. 12. grounding • laza prepared prototype version of grounding, work in progress

  15. 13. HO/HE specific issues • yb+1 rbx ready to be installed • yb0 will be taken out today • after water test, install N2 inertion block • vladimir is doing LV, HV and DCS, OF for YB0, YB1 • special calibration units should be on YB0, YB1

  16. 14. cable preparations • TTC cables for HO on-detectors (part number 0265) were supposed to be 35m, they are only 30m long. • for now, we are installing 4m extensions. we need to decide what do to on final installation.

  17. 15. test beam • look for cables for two phi sectors to plug into two RBXes • we need to decide if are we using MTP-MTP or MTP-LC • R1 and R2 goes to one RBX, R0 has its one RBX • we need LV cable for R1 and R0 boxes, arjan will define the lengths