LHC Tech Stop July 2011

LHC Tech Stop July 2011. Action plan for major stops (+multi instrum & other works). Empty QRL_C. SAM DFB. SAM DFB. Deg Pump. 1.8K. Refill QRL. 15mbar. RF. 1.8K. 70mbar. 15mbar. ? Test ? repump <50mbar. RF. Powering Quench. Powering Quench. SAM DFB. SAM DFB. Deg Pump.

Download Presentation

LHC Tech Stop July 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Tech Stop July 2011 Action plan for major stops (+multi instrum & other works) Empty QRL_C SAM DFB SAM DFB Deg Pump 1.8K Refill QRL 15mbar RF 1.8K 70mbar 15mbar ? Test ? repump <50mbar RF Powering Quench Powering Quench SAM DFB SAM DFB Deg Pump Deg Pump ? 1.8K Ref. CP7 Ref. 70mbar 15mbar LHCCryo - TechStop July 2011

  2. And reality … Specific oil injection (22bar) to balance axial forces, Need to send more oil than pass through to screws ! Major finding: the screw compressor (P8, oil filters clogging mid June) was found damaged, with bearings showing exceptional stress About 35’000 hrs, bearings calculated for 70’000 hrs Inlet (4bar) • Similar case than P4_Xmas: • Series problem ? • Too much axial force ? Confirmed by observations on oil circuit => Decision to treat similar compressors a.s.a.p Outlet (20bar) LHCCryo - TechStop July 2011

  3. Compressor station of LHC 18 kW@ 4.5 K Bldg: 15 x 45 X 9 Pinput : 4.5 MW Cool: 500 m3/h Noise: 105 dBA Pipe & fittings redone with larger diameters P8(1) done this Tech Stop, 2nd to factory, P4(1) & P18(2) done in shadow of P8 recovery, P6 to be done latest at Next Tech Stop LHCCryo - TechStop July 2011

  4. P8 configuration, week-end Extra flow Until compressor repaired! Limitations Validated for P2 (TS) ! Leaky HX (Jan’11) TuA (Spring11) 6CV215 valve (P2) Tests for relocation CCs CCs QUI Sector 81 Sector 78 Some minimum flexibility recovered during Tech Stop LHCCryo - TechStop July 2011

  5. LHC Tech Stop July 2011 Tentative d’illustration des activités Cryo LHC Empty QRL_C SAM DFB DFB SAM  Deg Pump 1.8K Refill QRL 15mbar 15 mbar 70 mbar CP CP  RF  1.8K 70mbar 15mbar Re-pump ? Test ? repump <50mbar New CP  70 mbar 15mbar RF 1.8K UPS Powering Quench Powering Quench    SAM DFB SAM DFB Deg Pump Deg Pump ? 1.8K Ref. CP7 Ref. 70mbar 15mbar  Rev2: P5_UPS effect + refinement 12/34 Rev3: QRL_12 test stopped earlier + P4/P18 QSCB oil pipes LHCCryo - TechStop July 2011

  6. Status & Forecasts Overall situation under control, checking singularities here and there P8: Should be back Friday evening (22h t.b.c) Special: ALL triplets + D4Q5_R4 emptied, warmed-up 25K, pumped VAC LHCCryo - TechStop July 2011