Understanding and Managing Project Costs Session 7. Review of Session 6. Labor Cost is the combination of wages, fringe benefits, and taxes Labor cost variances are caused by: Environmental conditions Management errors Subcontractor delay Supplier delay Owner/Architect delay

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Understanding and Managing Project Costs Session 7' - jock


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
review of session 6
Review of Session 6
  • Labor Cost is the combination of wages, fringe benefits, and taxes
  • Labor cost variances are caused by:
    • Environmental conditions
    • Management errors
    • Subcontractor delay
    • Supplier delay
    • Owner/Architect delay
    • Unforeseen delays

An AGC Construction Learning Tool

subcontractor delay
Subcontractor Delay
  • Subcontractor not available for work activities
  • Subcontractor not prepared for the work activity
  • Subcontractor without appropriate labor or size of crew
  • Subcontractor performance of defective work

An AGC Construction Learning Tool

subcontractor delay4
Subcontractor Delay
  • Late inspection of subcontractor’s work
  • Unsafe subcontractor work practices
  • Subcontractor disruption of work activities

An AGC Construction Learning Tool

cost impact by subcontractors
Cost Impact by Subcontractors
  • Exclusions, non-covered work
  • Additional non-compensated work by subcontractor
  • Additional work required by your crew
  • Subcontractor default

An AGC Construction Learning Tool

managing subcontractors during the bid period
Managing Subcontractors During the Bid Period
  • Cover all areas with subcontractor bids
  • Exclude non-responsible subcontractors
  • Carefully analyze subcontractors and their relationship to the work
  • Note:The bid period is short and chaotic. Estimators try to avoid problems, but some slip through.

An AGC Construction Learning Tool

managing subcontractors during buy out prior to award of subcontracts
Managing Subcontractors during “Buy-Out” (prior to award of subcontracts)
  • Include all subcontract work in the project subcontracts
  • Don’t duplicate work in subcontracts
  • Include all special clauses and requested exclusions in subcontracts
  • Write scope statement to be understood by field management

An AGC Construction Learning Tool

managing subcontractors during buy out prior to award of subcontracts8
Managing Subcontractors during “Buy-Out” (prior to award of subcontracts)
  • Supply the subcontractor with the following information:
    • List of submittals and shop drawings required, and when they are required
    • Construction schedule showing their work
    • Notification of pre-construction meeting

An AGC Construction Learning Tool

managing subcontractors prior to the start of their work
Managing Subcontractors Prior to the Start of Their Work
  • Meetings
    • Notify of all applicable meetings
    • Provide meeting minutes
    • Update on progress and changes
  • Advise on schedule progress
  • Conduct an on-site orientation meeting

An AGC Construction Learning Tool

subcontractor orientation
Subcontractor Orientation
  • Jobsite storage of material and equipment
  • Location for trailers
  • Jobsite access, parking
  • Jobsite security issues
  • Subcontractor’s schedule
  • Coordination with other work
  • Safety program
  • Introduction to key jobsite personnel

An AGC Construction Learning Tool

activity subcontractor orientation
Activity: Subcontractor Orientation
  • Topics for Orientation:
    • Jobsite access
    • Storage of material
    • Schedule for work
    • Weather protection
    • Coordination with other work
    • Safety
    • Jobsite security
    • Clean-up
    • Communication channels

An AGC Construction Learning Tool

activity subcontractor orientation12
Activity: Subcontractor Orientation
  • Subcontracts to Examine:
    • Structural steel, joist and deck erection
    • Roofing, roof insulation, and flashing
    • Building electrical
    • Building plumbing
    • Overhead doors
    • Windows/storefront
    • Painting

An AGC Construction Learning Tool

managing subcontractors while they are on the job
Managing Subcontractors While They Are on the Job
  • Meeting at start of work between superintendent and subcontractor foreman:
    • Quality of work expected
    • Coordination with other work
    • Expectations for clean-up
    • Hours of work
    • Security aspects
    • Safety program
    • Access and equipment usage

An AGC Construction Learning Tool

documenting subcontractors
Documenting Subcontractors
  • Document subcontractor activity
  • Document material delivery to site
  • Document when subcontractors are not available
  • Document in reports and with photographs

An AGC Construction Learning Tool

changes to subcontracts
Changes to Subcontracts

An AGC Construction Learning Tool

managing subcontractors before they leave the jobsite
Managing Subcontractors Before They Leave the Jobsite
  • Discussion between superintendent and subcontractor foreman:
    • Inspection of work, plan for remedial work
    • Work remaining to be completed, plan to complete it
    • Acceptance of finishes by other subs
    • Cleaning of work, and waste disposal
    • Protection of work in place

An AGC Construction Learning Tool

managing subcontractors before they leave the jobsite17
Managing Subcontractors Before They Leave the Jobsite
  • Discussion between superintendent and subcontractor foreman:
    • Delivery of spare materials and parts
    • Delivery of O&M materials and instruction
    • Schedule for any additional work
    • Arrange for completion of punch list work

An AGC Construction Learning Tool

activity case study subcontractor management
Activity: Case Study, Subcontractor Management
  • Building envelope needs to be complete by October 7 to avoid interference with Tenant Improvements Contract
  • Read subcontractor action descriptions
  • Discuss, in groups, what could have been done to avoid the problems

An AGC Construction Learning Tool

activity case study subcontractor management19
Activity: Case Study, Subcontractor Management

An AGC Construction Learning Tool

using on the job what you learned today
Using on the Job What You Learned Today
  • Jobsite Assignment
    • What costs have subcontractor problems caused on your project?
    • Who had to pay for the costs?
    • What delays were caused by subcontractors? What costs due to delay?
    • What portion of your time do you spend managing subcontractors?
    • Would communicating your expectations reduce subcontractor problems?

An AGC Construction Learning Tool

using on the job what you learned today21
Using on the Job What You Learned Today
  • To get ready for Session 8:
    • Read Session 8
    • What risks are being taken with your current job?
    • What costs can occur from these risks?
    • How are the risks being managed on your project?

An AGC Construction Learning Tool