1. Transition to SuperJANET5 Roland Trice
r.trice@ukerna.ac.uk
2. MANs Meeting June 2006 SuperJANET5 Transition 2 Introduction Acceptance Testing
Transition Timetable
Transition Process
3. MANs Meeting June 2006 SuperJANET5 Transition 3 Acceptance Testing Core testing complete
Agilent testers
Detailed reports from Verizon
Quality audit at each C-PoP
In person, by ULCCs senior engineers
Time consuming but necessary
Core network has been accepted
4. MANs Meeting June 2006 SuperJANET5 Transition 4 Acceptance Testing Circuit acceptance tests
C-PoP QA by the NOSC
Connection of 4200s to the Junipers
Testing using sweep-pings around looped circuits
Not likely to be complete until 3rd week of July
Acceptance Testing at the RNEPs
Not practical for NOSC staff to supervise
RNOs are asked to do so on UKERNAs behalf
5. MANs Meeting June 2006 SuperJANET5 Transition 5 Acceptance Testing Check fibre installation against scope of work
You should have full spec in your installation pack
Tell Rolly & Eddie if you dont
SuperJANET5 Network Rollout, RNEP Requirements
The facilities you need to provide
Acceptance Process for Regional Networks
Circulated this week
Details need revising
6. MANs Meeting June 2006 SuperJANET5 Transition 6 Rack Layout
7. MANs Meeting June 2006 SuperJANET5 Transition 7 Plan B
8. MANs Meeting June 2006 SuperJANET5 Transition 8 RNO Acceptance Test Verizon will perform QA
Auditor will liaise with RNO staff
Audit in the presence of the RNO
Both parties sign off the audit
RNO should make sure that the audit IS done
Confirm that your site is left safe and tidy
Confirm that the audit is completed diligently
9. MANs Meeting June 2006 SuperJANET5 Transition 9 RNO Acceptance Test RNO is not:
Expected to verify each item on the check list
Warranting that the installation is fit for purpose
Please please please leave lawyers out of this
If there are issues:
Tell Rolly
Who will tell Verizon
Please sign off any snagging when it is complete
10. MANs Meeting June 2006 SuperJANET5 Transition 10 Transition Timetable Changed to the originally published timetable
Delays in circuit delivery
Newts, wayleaves, asbestos, small digging teams
Majority of circuits tested by 3rd week in July
Critical mass necessary before testing
Avoids repeated visits to C-PoPs
There may need to be further changes to the timetable
11. MANs Meeting June 2006 SuperJANET5 Transition 11 Transition Timetable Transition should begin on 18th July
If you can go early, thats good
Timetable on UKERNA web pages
If its a piece of cake
I will re-timetable to move three RNs a week
Contingency slots every 2nd or 3rd week
If its a trip to the dentist
Thursday mornings will be used to clear the backlog
Will decide in October
12. MANs Meeting June 2006 SuperJANET5 Transition 12 Transition Timetable UKLight and non-RN connections will move during clearing
If transition has not started before clearing
Timetable Tuesday and Thursday transition slots
Weekend or evening transitions are not on the agenda
UKERNA reserves the right to move RNs during clearing
13. MANs Meeting June 2006 SuperJANET5 Transition 13 Transition Timetable 18/07 NorMAN (possible) C&NLMAN (possible)
25/07 NNW (possible) EMMAN (possible)
1/08 SCOLOCATE, Contingency
07/08 Clearing Starts
08/08 EastNET, Contingency
15/08 EastNET, Contingency
26/09 NNW, Kentish MAN
03/10 EastMAN, LeNSE unicast, Contingency
05/10 LeNSE multicast
10/10 ClydeNET, C&NLMAN, Contingency
14. MANs Meeting June 2006 SuperJANET5 Transition 14 Transition Timetable 12/10 LeNSE multicast contingency
17/10 AbMAN, Wales MAN, Contingency
24/10 FaTMAN, LMN, Contingency
31/10 SWERN, UHI, Contingency
07/11 NorMAN, MidMAN, Contingency
14/11 EMMAN, NIRAN, Contingency
21/11 YHMAN, TVN, Contingency
28/11 Contingency, Contingency
05/12 Contingency, Contingency
12/12 Contingency, Contingency
15. MANs Meeting June 2006 SuperJANET5 Transition 15 Transition Arrangements Connect up as soon as circuits and routers ready
PING tests to confirm circuit availability
Set things up in advance
Hot cut from SJ4 to SJ5
Once you have moved over, Baoyu will arrange to have the BAR decommissioned and removed within a month or so
16. Questions?