Microsoft Project 基本步骤
DESCRIPTION
Microsoft Project 基本步骤. 1 、创建项目 2 、创建与编辑项目任务 3 、建立任务关系 4 、资源和成本管理 5 、总览与打印项目. 创建项目. 设置文件属性(文件→属性→摘要) 输入项目工作时间(工具→更改工作时间) 增加项目属性(项目→项目信息). 创建与编辑项目任务. 输入任务列表(在甘特图视图中输入) 任务概述(摘要任务、升序或降序) 输入任务工期(任务信息). 建立任务关系. 链接任务 直接输入. 资源和成本管理. 输入资源(视图→资源工作表) 给任务分配资源(视图→甘特图→任务信息→资源 或 工具→ 分配资源)
1 / 7
Download Presentation
Microsoft Project 基本步骤
An Image/Link below is provided (as is) to download presentation
Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.
Content is provided to you AS IS for your information and personal use only.
Download presentation by click this link.
While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.
During download, if you can't get a presentation, the file might be deleted by the publisher.
E N D
Presentation Transcript
Microsoft Project基本步骤 1、创建项目 2、创建与编辑项目任务 3、建立任务关系 4、资源和成本管理 5、总览与打印项目
创建项目 • 设置文件属性(文件→属性→摘要) • 输入项目工作时间(工具→更改工作时间) • 增加项目属性(项目→项目信息)
创建与编辑项目任务 • 输入任务列表(在甘特图视图中输入) • 任务概述(摘要任务、升序或降序) • 输入任务工期(任务信息)
建立任务关系 • 链接任务 • 直接输入
资源和成本管理 • 输入资源(视图→资源工作表) • 给任务分配资源(视图→甘特图→任务信息→资源 或 工具→ 分配资源) • 显示成本表(视图→表→成本) • 优化资源(视图→资源工作表) • 优化进度(项目→项目信息→完工日期)
总览与打印项目 • 视图→报表