1 / 0

Performance Based Maintenance Contracting in Tennessee (Experience One Year In)

Performance Based Maintenance Contracting in Tennessee (Experience One Year In). September 28, 2013 Greg Duncan, Assistant Chief Engineer of Operations Anaheim , CA. Performance Based Maintenance Contract.

jalena
Download Presentation

Performance Based Maintenance Contracting in Tennessee (Experience One Year In)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Performance Based Maintenance Contracting in Tennessee(Experience One Year In)

    September 28, 2013 Greg Duncan, Assistant Chief Engineer of Operations Anaheim, CA
  2. Performance Based Maintenance Contract 103.65 Miles (533 Lane Miles) of I-65, I-24, and SR-840 in Bedford, Rutherford, Williamson, and Wilson Counties
  3. CNL-500: Performance Based Maintenance Contract Activities Covered Areas of work required for this project shall include, but are not limited to, routine maintenance, minor repairs, collision damage repairs, and emergency repairs for the following items as detailed in the Performance Criteria or other provisions contained elsewhere in this contract: Travel Pavements Shoulders Drainage Roadside Bridge (What our County and Bridge Crews would do.) Snow and Ice Control Traffic Services Extraordinary Maintenance
  4. Performance Based…… Contractor paid based on 24 monthly weighted MRI’s. Specified to mow 4 times per year and remove litter 6 times per year. Snow and Ice activities paid by the hour. Timely performance standards compelled through the SP 108B Reduction in monthly pay for mileage removed for rehabilitation.
  5. Competition and Cost Comparison
  6. Existing Condition