1 / 25

April 25, 2012

ODOT Planners Meeting. April 25, 2012. Purpose of Project.

isi
Download Presentation

April 25, 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ODOT Planners Meeting April 25, 2012

  2. Purpose of Project Improvemobility and safety for people and freight for local, regional, and through travel across the Willamette River in the Salem-Keizer metropolitan area while alleviating congestion on the Center Street and Marion Street Bridges and on the connecting highway and arterial street system. The following areas are of specific concern: • Reducing congestion compared to current conditions at the existing bridgeheads to facilitate the flow of vehicles and freight through the downtown area and east-west freight movement through the Salem-Keizer metropolitan area • Remediating safety and operational deficiencies on the existing bridges and in the study area in locations where crash rates are higher than average

  3. Review of DEIS Alternatives • No Build Alternative • 3 bridge crossing locations; 8 Build Alternatives • Crossing locations: • Existing Bridges Crossing Location (2A& 2B) • Hope to Tryon Crossing Location (3) • Hope to Pine/Hickory Crossing Location (4A - 4E)

  4. DEIS Alternatives: Crossing Locations

  5. No Build Alternative • Alternative 1 (No Build): Examines how the transportation system will operate in the future without building another bridge. • Used as a baseline to compare and measure the other alternatives

  6. Existing Bridges Crossing Location • Alternative 2A (widen existing bridges): Adds two new lanes to the Marion Street Bridge (plus a connection to the future Marine Drive NW) and one new lane to the Center Street Bridge • Alternative 2B (north of existing bridges): New bridge between the Marion and Union Street Bike/Pedestrian bridges

  7. Alternative 2A (widen existing bridges)

  8. Alternative 2B (north of existing bridges)

  9. Hope to Tryon Crossing Location • Alternative 3 (Hope to Tryon): New bridge from Wallace Road NW and Hope Avenue NW to Tryon Avenue NE and the Salem Parkway NE, including connections to the Liberty/Commercial Street NE couplet

  10. Alternative 3 (Hope to Tryon)

  11. Hope to Pine/Hickory Crossing Location • Alternative 4A (Hope to Liberty via Pine/Hickory): New bridge from the Wallace Road NW and Hope Avenue NW to Pine/ Hickory Street NE and the Liberty/Commercial Street NE couplet

  12. Alternative 4A: (Hope to Liberty via Pine/Hickory)

  13. Hope to Pine/Hickory Crossing Location • Alternative 4B (4A + 2A): New bridge (4A) plus widen existing bridges (2A)

  14. Alternative 4B (4A + 2A)

  15. Hope to Pine/Hickory Crossing Location • Alternative 4C (4A + Direct Connections to Salem Parkway & OR 22): New bridge (4A), but Pine/Hickory Street NE extends to Broadway Street NE and has a direct connection to Salem Parkway NE with elevated and direct connection to OR 22 and Marine Drive NW

  16. Alternative 4C (4A + Direct Connections to Salem Parkway & OR 22)

  17. Hope to Pine/Hickory Crossing Location • Alternative 4D (4C with shortened Pine/Hickory couplet): Same as Alternative 4C but the bridge connection to Pine/ Hickory Street NE would touch down at Liberty Street NE (not Broadway Street NE)

  18. Alternative 4B (4C with shortened Pine/Hickory couplet)

  19. Hope to Pine/Hickory Crossing Location • Alternative 4E (4C minimizes impact to Wallace Marine Park): New bridge (4C) but with modified connection to OR 22 to minimize impacts to Wallace Marine Park

  20. Alternative 4E (4C minimizes impact to Wallace Marine Park)

  21. Cost Estimates (2015) • 2A - $148 million • 2B - $388 million • 3 - $501 million • 4A - $306 million • 4B - $451 million • 4C - $692 million • 4D - $687 million • 4E - $708 million

  22. Next Steps • DEIS public hearings May 8 and 17 • DEIS public comment period closes June 18 • Identification of a locally preferred alternative • Development of a finance strategy – to include public opinion survey

  23. Decision Process

  24. Decision Process – Locally Preferred Alternative

  25. Decision Making Structure