integrated program office briefing to shared processing operations steering committee l.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Integrated Program Office Briefing to Shared Processing Operations Steering Committee PowerPoint Presentation
Download Presentation
Integrated Program Office Briefing to Shared Processing Operations Steering Committee

Loading in 2 Seconds...

play fullscreen
1 / 20

Integrated Program Office Briefing to Shared Processing Operations Steering Committee - PowerPoint PPT Presentation


  • 148 Views
  • Uploaded on

Integrated Program Office Briefing to Shared Processing Operations Steering Committee. CAPT Craig Nelson Major Markus Sorrells Mr. Bill Devens November 28, 2001. AGENDA. NPOESS Program Status COPC/SPOSC NPOESS Topics Other COPC/SPOSC TOPICS. NPOESS Program Status.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Integrated Program Office Briefing to Shared Processing Operations Steering Committee' - ira


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
integrated program office briefing to shared processing operations steering committee

Integrated Program OfficeBriefing toShared Processing Operations Steering Committee

CAPT Craig Nelson

Major Markus Sorrells Mr. Bill Devens

November 28, 2001

agenda
AGENDA
  • NPOESS Program Status
  • COPC/SPOSC NPOESS Topics
  • Other COPC/SPOSC TOPICS
npoess program status
NPOESS Program Status
  • Significant Activities Since April 01 COPC/SPOSC
    • NPOESS Sensors
      • CMIS – BSS Contract
      • APS – Now Part of NPOESS Baseline – DoD Applications
    • Field Terminal MOA Signed
  • NPOESS Acquisition Schedule
    • IORD Validation Status
      • AFROC – 25 Oct 01 – Successfully Briefed
      • JROC – 13 Dec 01 – On Track
    • TRD v.6 Status – CCB 26 Nov – Release Jan 02
    • RFP for EMD/TSPR Contract – Release Feb 02
  • Issues
    • FY 02 DoD Budget Uncertainty
    • Potential Cost/Schedule Impacts

3

instruments in development production phase

Visible/IR Imaging Radiometer

Suite

(VIIRS)Raytheon

Instruments inDevelopment/Production Phase

Cross-track IR Sounder (CrIS)

[Engineering Development Unit]

ITT

Conical-scanning Microwave

Imager/Sounder

(CMIS)Boeing

Advanced Technology Microwave Sounder (ATMS)

[NASA/GSFC Notional Design]

Aerojet

Ozone Mapping & Profiler Suite (OMPS)

[Artist Conception]

Ball

satellite transition schedule 27 august 2001 slopes indicate 10 90 need npoess gap 6c

F16

F18

F20

C3

WindSat/Coriolis

F17

F19

M

N

16

C2

N’

EOS-Aqua

Satellite Transition Schedule(27 August 2001)Slopes indicate 10-90% need (NPOESS GAP 6c)

99

00

01

02

03

04

05

06

07

08

09

10

11

12

13

14

15

16

17

18

CY

----------------10 Year Mission Life-------------------

0530

NPOESS

DMSP

F15

NPOESS

NPOESS

C1

DMSP

0730 - 1030

POES

METOP

EOS-Terra

Local Equatorial Crossing Time

NPP

NPOESS

POES

1330

Earliest Need to back-up launch

Mission

Satisfaction

Earliest Availability

S/C

Deliveries

5

S/C delivery interval driven by 15 month IAT schedule

Last Modified: Aug 27, 2001

primary centers of responsibility pcr
Primary Centers of Responsibility (PCR)
  • PCR….A component concept of IDPS CONOPS
    • Used to optimize NPOESS R&D efforts
      • Each Central provided NPOESS R&D resources
        • Evolutionary Algorithm R&D (EARD) resources
        • EARD Programmer/Manager
    • PCR regarded as NPOESS authority on EDR
      • Ultimate source for the “official” EDRs/archived EDRs
        • Designates/serves as source for the ancillary data set
        • Controls the IDPS configuration used to produce the “official” set of EDRs for which it is PCR
    • Impacts engineering design
slide8

PCR Selection Drives Design Decision

or

(Notional)

AFWA X

X

NESDIS

ADS/CLASS

X FNMOC

Ancillary Data Sets

or

Environmental Data Records?

X NAVOCEANO

Increase NESDIS processing capacity?

Or

Purchase cross-country communications (and how much?)

slide9

PCRs and SCRs for 55 EDRs

NESDIS/OSDPD

Atmospheric Soundings

Mechanism

to

arbitrate

PCR/SCR

allocation?

AFWA

Visible & IR Mapped Cloud Imagery & Analysis

55

EDRs

Which Central

to be PCR?

* Secondary Central

of Responsibility?

For which EDRs?

NAVOCEANO

Multichannel

SST & Altimetry

FNMOC

Microwave

Imagery

* SCRs collaborate with and test PCR recommended algorithm changes

status of idps conops
Status of IDPS CONOPS
  • Nearing completion…awaiting inputs
    • Held a Centrals Conclave at IPO, 1-3 May
    • Recently received consolidated inputs from follow-up Centrals’ July TIM
    • Received Central IDPS CONOPS Appendices from NAVO and FNMOC…awaiting AFWA and NESDIS
    • Data Distribution Servers at Centrals
      • IPO has Tasked PDRR Contractors to Conduct Feasibility Studies and Provide ROM
      • Impacts Short Term Storage Issue
gao review of npoess
GAO Review of NPOESS
  • Requested by House Committee on Science
  • Study Initiated in August 2001
  • Overall Objectives
    • Evaluate the status, plans, and technical and programmatic risks associated with NPOESS acquisition and operations
    • Identify challenges in managing the vast streams of data from NPOESS satellites
    • Determine whether the IPO is effectively applying lessons learned from prior NOAA satellite acquisition efforts
  • Entrance meetings with NWS and IPO in August
  • Numerous meetings with IPO to discuss all 3 objectives
  • No definitive schedule for completion of review
    • Draft report may be available for spring Congressional hearings after release of FY 2003 PB
gao review of npoess12
GAO Review of NPOESS
  • Current GAO Review Team focus is on objective #2
  • Reviews initiated in November with DoD and NOAA
    • COL Jamilkowski is DoD POC
  • GAO Team to visit METOC OPCs (FNMOC, NAVO, AFWA, NCEP/NESDIS)
  • Focus of discussions on satellite data utilization
    • Current DMSP/POES data management overview
      • Data flow from satellites through center to end users and archives
      • Current uses of satellite data
      • Current center processing capacity and storage
    • Plans for NPOESS data management
      • Plans to "grow" the centers’ capacity, storage, and numerical models to get ready for NPOESS increased data volumes
      • Budget plans for growing these capabilities
gao review of npoess13
GAO Review of NPOESS
  • GAO Team request for information from OPCs
    • Current data flow architecture for DMSP data
    • DMSP/POES and NPOESS portions of a current information technology architecture (ITA) and target ITA
    • Migration plans for reaching the target ITA
    • Plans to assimilate NPOESS data into weather models
    • Plans and budget information supporting efforts to "grow" the centers’ infrastructure & models
satellite data assimilation
Satellite Data Assimilation
  • COPC requested IPO to “lead and fund a vigorous data assimilation plan”
  • IPO agrees with COPC precepts
    • Effective assimilation of satellite data into operational products is important to success of future satellite programs (NPOESS/GOES-R) --- However
      • IPO is not authorized nor funded to develop satellite data assimilation techniques as part of approved program
  • IPO has provided >$3M over last 5 years for satellite data assimilation experiments and development of techniques for processing data from precursor instruments
    • NCEP, OSDPD, AFRL, NRL, and academic institutions
    • (AIRS, MODIS, SSM/IS, WindSat)
  • IPO will provide up to $500K annually to the Joint Center for Satellite Data Assimilation
    • Funding contingent upon integration of DoD OPCs (FNMOC, NAVO, AFWA) into the JCSDA
other copc sposc topics
OTHER COPC/SPOSC TOPICS
  • Assignment of Primary & Secondary Centers of Responsibility
    • Bill Devens
  • Formal Response to COPC Data Assimilation Request
    • CAPT Nelson

16

ipo sensor algorithm risk reduction contract status

11/97

1/99

11/97

11/98

1/99

11/98

IPO Sensor/Algorithm Risk Reduction Contract Status

SFR System Functional Review

SFR System Functional Review

PDR Preliminary Design Review

CFI Call For Improvement

CDR Critical Design Review

First Unit Delivery

CrIS Cross-track IR Sounder

3/98

12/98

4/99

5/99

2/02

3/04

OMPS Ozone Mapping & Profiler Suite

8/98

2/99

3/02

(Sensor)

5/03 (Algorithm)

6/04

GPSOS GPS Occultation Sensor

6/98

N/A

1/03

3/06

6/04

VIIRS Visible/IR Imager Radiometer Suite

10/99

5/00

6/00

2/02

CMIS Conical Microwave Imager Sounder

8/99

2/01

3/01

1/03

12/05

17

milestone ii prod preparation schedule
Milestone II/Prod Preparation Schedule

Jun 00

Aug 00 Dec 00

Dec 00 Mar 01

May 01 Dec 01

June 01 Jan 02

Aug 01 Nov 01

June 01 Jan 02

Sep 01 Feb 02

Jan 01 Jul 02

Feb 02 Aug 02

  • Activity
  • Integrated Operational Requirements Document
      • IORD changes by JARG Complete
      • Senior User Advisory Group Approval
      • JROC Approval
      • IORD approved by JARC
  • Technical Requirements Document
      • TRD w/CMIS down-select changes
      • Final TRD based on Validated IORD
  • EMD/Production Request for Proposals
      • Final RFP Release
      • Source Selection Decision
  • EXCOM EMD/Production Milestone
      • Defense Acquisition Board & EMD Award

Revised

document status
Document Status
  • IORD II in Review
    • JROC scheduled for 13 Dec 01
  • COBRA: Analysis of Alternatives due Jun 02
    • Guidance Received from OSD(PA&E)
    • Cost analysis pending completion of the POE
  • SAMP in Review
    • DOC/NASA/SAF comments are minor and anticipate easy resolution
    • OSD has taken issue with combined EMD/Production strategy
    • Anticipated SAMP signature date of Dec 01
  • TEMP
    • 1997 signed TEMP being updated using quarterly IPT meetings
    • Anticipate TEMP signature date by Aug 02
  • CARD: Latest draft released 12 Nov 01
  • Program Office Estimate
    • Estimate under review/refinement
    • Reconciliation with Component Cost Analysis anticipated in Dec 01
summary
Summary
  • EMD award slipped due to late delivery of requirements document
  • Restructured PDRR
    • Moved work forward to protect NPP CDR (system PDR)
    • Deferred some work to post award to “create” funds
  • Today -
    • Requirements approval on track
    • EXCOM approval on track
    • No impediment to Aug 02 EMD award
  • FY02 budget cuts cause massive restructure of program
    • Will result in program slip
    • Jeopardizes NPP, Windsat; slips NPOESS C-1 & causes coverage gap