MOD_42_10v2 : Changes to the Single Ramp Up Rate and the Single Ramp Down Rate Calculation

MOD_42_10v2 : Changes to the Single Ramp Up Rate and the Single Ramp Down Rate Calculation. Single Ramp Rate. MSP Software uses A single ramp rate based on time to ramp between min & max outputs Generator Units can specify: 5 ramp up rates over 4 ranges and 5 ramp down rates over 4 ranges.

ilori
Download Presentation

MOD_42_10v2 : Changes to the Single Ramp Up Rate and the Single Ramp Down Rate Calculation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MOD_42_10v2 : Changes to the Single Ramp Up Rate and the Single Ramp Down Rate Calculation

  2. Single Ramp Rate • MSP Software uses • A single ramp rate based on time to ramp between min & max outputs • Generator Units can specify: • 5 ramp up rates over 4 ranges and 5 ramp down rates over 4 ranges. • Dwell times describe output levels at which ramping must pause. RAMP DOWN RAMP UP Output (MW) Availability Slope = Single Ramp Up Rate Slope = Single Ramp Down Rate Min Stable Generation Dwell Times Time

  3. MW RUR3 Ramp up Break Point RUR2 Ramp up Break Point RUR1 MINGEN Load up Break Point 2 Load up Break Point 1 Block Load Time SoakTime 2 Soak Time 1 Dwell Time 2 Dwell Time 1 LUR1 LUR2 LUR3 Single Ramp up Rate Real-Time Availability

  4. MW RUR3 Ramp up Break Point RUR2 Ramp up Break Point RUR1 MINGEN Time Dwell Time 2 Dwell Time 1 Single Ramp up Rate Real-Time Availability Single Ramp up Rate

  5. Single Ramp up Rate The Single Ramp up Rate calculation is: = (Max(Availability) – Min(Minimum Generation))/RampUpTime The Single Ramp Down Rate calculation is: = (Max(Availability) – Min(Minimum Generation))/RampDownTime

  6. MW Real-Time Availability RDR3 Ramp Down Break Point 2 RDR2 Ramp Down Break Point 1 RDR1 MINGEN DLR2 Deloading Break Point DLR1 Time Dwell Time 2 Dwell Time 1 Single Ramp down Rate

  7. MW Real-Time Availability (MAXGEN) RDR3 Ramp Down Break Point 2 RDR2 Ramp Down Break Point 1 RDR1 MINGEN Time Dwell Time 2 Dwell Time 1 Single Ramp down Rate Single Ramp down Rate

  8. Overview of Changes in the T&SC

  9. Single Ramp up Rate – proposed changes The Single Ramp up Rate calculation is: If max(AAuh) <= MinGenTOD then (MaxGenTOD – max(min(Minimum Stable Generation), MinGenTOD))) /RampUpTime else (max(AAuh) – max(min(Minimum Stable Generation), MinGenTOD))) /RampUpTime And similarly for the Single Ramp Down Rate.

More Related