Upgrade of the vertical test station with new improved inserts for existing cryostats

Upgrade of the vertical test station with new improved inserts for existing cryostats. Technical seminar - 5 th June 2014 Vincent Roger - TE-MSC-TF. Outlook. Introduction Part I – General description Part II – The new insert of the Long station 2.1 Design stage 2.2 Safety file

Download Presentation

Upgrade of the vertical test station with new improved inserts for existing cryostats

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Upgrade of the vertical test station with new improved inserts for existing cryostats Technical seminar - 5th June 2014 Vincent Roger - TE-MSC-TF

  2. Outlook Upgrade of the vertical test station in SM18 Introduction Part I – General description Part II – The new insert of the Long station 2.1 Design stage 2.2 Safety file 2.3 Follow up of the production Part III – The future inserts 3.1 Projects progress 3.2 The insert of the Cluster D Conclusions

  3. Introduction • In order to increase our capacity of testing magnets, current leads and diode stacks, several projects have been set up to realise new insert or to update them. With these new inserts we will gain also in : • Flexibility • Cooling Time • Handling & operation • In a general way, the purpose of an insert is to : • Support mechanically the magnet or other devices • Connect electrically this device to the power supply via the current leads • Cool down the device from 293 K to 4.2 K or 1.9 K Upgrade of the vertical test station in SM18

  4. Inserts already in use in SM18 The insert used to test the diode stacks The insert used to test current leads The design of these inserts were simple since they work at 4.2 K : No exchangers and instrumentations No λ plate No tie holdings and helium guards Upgrade of the vertical test station in SM18

  5. Inserts in progress • The second insert of the long station • The insert of the Siegtal station • The insert of the Auxiliary station • The insert of HFM • The insert of the Cluster D Upgrade of the vertical test station in SM18

  6. Part I – General description 4.2 K helium bath GHe/ LHeexchanger 1.9 K helium bath Upgrade of the vertical test station in SM18 Top plate λ plate LHe / LHeexchanger Magnet

  7. Cryogenic devices To reach 1.9 K, two thermal exchangers are needed : • The GHe / LHeexchangerused to reach 1.9 K (using gaz helium at verylow pressure vapoursaturised and JT valve) • The LHe / LHeexchangerused to cool the main helium bath to 1.9 K by conduction GHepumping Command of the Joule Thomson valve Instrumentations GHe / LHeexchanger LHe / LHeexchanger Upgrade of the vertical test station in SM18

  8. Use of a PLC & Operation A PLC (Programmable Logic Controller) has been set up in order to manage automaticallycryogenicdevices for standard operations as cool down or warm up but especially to guaranteefacilities and staff safety. Upgrade of the vertical test station in SM18

  9. Part II – The new insert of the Long station 2.1 Design stage In order to reduce the delay between two magnet tests on the long station, it has been decided to design a new insert. This insert is NOT a copy of the existing insert, cryogenic performance have been improved, and instrumentations have been automatized. Group project of 9 peoples: Follow up : TE-MSC-TF Design : EN-MME-EDM Manufacturing : EN-MME-FS Cryogenic devices : TE-CRG-ME Safety : DGS-SEE-SI Upgrade of the vertical test station in SM18

  10. Design of the existing insert Upgrade of the vertical test station in SM18

  11. Main improvements • A new GHe/ LHeexchangerto increase the helium flow • A new LHe/ LHeexchangerto increase its surface • A new GHeoutflow on the safety line • Automatize the safety valve on the λ plate • Use new instrumentation boxes • Use an helium guard on the tie holdings to prevent leak • Use of a new standard valves for the LHe inflow Upgrade of the vertical test station in SM18

  12. Design of the new insert Upgrade of the vertical test station in SM18

  13. One of the main difficult part was to design a bigger LHe / LHe exchanger by keeping a good handling. To decrease the cooling magnet time from 4.2 K to 1.9 K, the exchange’s surface has been increased from 0.3 m2 to 1.0 m2 Upgrade of the vertical test station in SM18

  14. More than 200 elements have been modelled and 120 drawings have been realised !!! There are hundreds of welds which will be done and controlled by the main workshop !!! From 600 to 700 hours of work !!! Upgrade of the vertical test station in SM18

  15. 2.2 Safety file The maximum allowable pressure (PS) of the insert has been defined. From this the opening pressure of safety valves and the pressure tests are defined. • Working pressure : around 0.2 barg • 0.9 barg : opening of the valve to the balloon • PS = 1.5 barg • 1.1 * PS = 1.7 barg (primary safety system) • 1.2 * PS = 1.8 barg (secondary safety system) • Test pressure : 2.5 barg Upgrade of the vertical test station in SM18

  16. According to the Pressure Equipment Directive 97/23/EC (PED), this insert belongs to a risk category III. Upgrade of the vertical test station in SM18

  17. Therefore a safety file need to be set up in which all the following information have to be documented. Upgrade of the vertical test station in SM18

  18. Moreover the percentage of radiographic tests on butt‐welds shall be in agreement with the following table. All non standard welds need to be calculated, and the workshop needs also to be certified for all weld types. Electron beamwelds Brazing Copper / Stainless steal Upgrade of the vertical test station in SM18

  19. For this safety file, an EDMS structure has been set up. Upgrade of the vertical test station in SM18

  20. 2.3 Follow up of the commands & the manufacturing To certify the insert, it is needed to check rigorously the material certificate of each part even if these parts are ordered on the CERN store. At the main workshop, each material pieces are identified and attached to one element of one drawing to keep the material traceability. Upgrade of the vertical test station in SM18

  21. The manufacturing has begun, and the weld process is going to start : Upgrade of the vertical test station in SM18

  22. 2.4 Synthesis It’s the first time that a such project is realised with regards to the new standards. The approach is now well defined, and based on this experience we can go ahead with the following new inserts. Upgrade of the vertical test station in SM18

  23. Part III – The future inserts 3.1 Projects progress • The insert of the Siegtalstation • The insert of the Auxiliary station • The insert of HFM • The insert of the Cluster D 11/2014 To be defined 12/2015 12/2015 Upgrade of the vertical test station in SM18

  24. 3.2 The Cluster D New cryostat New insert New cryogenics devices New power supply & equipment New rack for the acquisition and new PLC New control room Upgrade of the vertical test station in SM18

  25. A preliminary study has been done in order to choose a design strategy based on the Long test station or on the HFM test station.

  26. Based on this criteria, we estimated that HFM type design would fit better both in time and price estimate to our needs for serving HL-LHC magnet tests. Upgrade of the vertical test station in SM18

  27. Today a first design of the insert is done, to go further with the design stage we would need some inputs (design of the current leads, final geometry of the cryostat, magnet interface, …) Upgrade of the vertical test station in SM18

  28. Conclusions Upgrade of the vertical test station in SM18

  29. Design Office and Main workshop : EN-MME Vincent Maire, Emilien Rigutto, Luca Dassa Magnet Test Facilities: TE-MSC-TF Marta Bajko, Christian Giloux, Patrick Viret Cryogenic Team : TE-CRG Vladislav Benda Safety group: DGS-SEE Cecile Pinto Cryostats & Machine Integration : TE-MSC-CMI Arnaud Vande Craen On behalf of Upgrade of the vertical test station in SM18