html5-img
1 / 12

Planned FCC Power Outage

Planned FCC Power Outage. July 11, 2011. ARRA Construction @ Feynman. ARRA construction project requires completion by September 30 th. This constraint requires a outage window on Saturday August 13 th to enable subsequent deliverables and activities.

hung
Download Presentation

Planned FCC Power Outage

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Planned FCC Power Outage July 11, 2011

  2. ARRA Construction @ Feynman • ARRA construction project requires completion by September 30th. • This constraint requires a outage window on Saturday August 13th to enable subsequent deliverables and activities. • Date negotiated with experiment D0, CDF and CMS spokespersons to minimize impact.

  3. ARRA Construction @ Feynman • Cooling Upgrade project requires an outage • Electrical work associated with cooling system for the FCC2 computer room • EPO upgrade to new system on FCC2 (including commissioning and testing) • Opportunistic Work • Installation of power monitoring for the original FCC 480V service (DOE requirement) • Small electrical upgrades & work

  4. Impact to Services • Core Services will be unavailable with the exception of network for the duration. • Shared Scientific Computing Services will be either unavailable or impacted for the duration. • We are working in the interim to mitigate the impact on the network and scientific services.

  5. Outage Schedule • Saturday, August 13 • Scheduled for 8 hours • Tentative start of work is 6:00AM • All power and cooling in Feynman is impacted except for the FCC3 HACC computer room

  6. Questions

  7. Appendix GCC Cooling Outage

  8. GCC Cooling Outage • June 7 loss of cooling in Computer Room B • Ambient air to condensers to hot > 120F • Heat build up on condenser pad Record Setting Temperatures @ Dupage Airport

  9. Short Term Actions • Understand indicators or predicators • Computing load shed plan • Cooling in the room reviewed • Increased cooling setpoint from 73F to 77F • Review of existing monitoring data • Water cooling under condensers at the pad • Reduction of vegetation around the pad • Augmentation of monitoring at the pad

  10. FESS Engineering Study • Engineering Review of the cooling system • Determine Root Cause • Recommendations & proposals • Deliverables from study in late summer • Implement any modifications • Prior to Summer, 2012

More Related