1 / 26

HF Radar Systems Engineering Plan

HF Radar Systems Engineering Plan. Define performance Objectives for Multi-Static Operation Define system requirements for Large Scale Deployment Architecture Define Interfaces and Requirements for Second Shore Station and at sea bistatic transmitter

hmclaughlin
Download Presentation

HF Radar Systems Engineering Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HF Radar Systems Engineering Plan Define performance Objectives for Multi-Static Operation Define system requirements for Large Scale Deployment Architecture Define Interfaces and Requirements for Second Shore Station and at sea bistatic transmitter Deliverable “Codar HF Radar Functional Specification” LEAP2-RUT-T1 TASK 1: November 2, 2010 – February 24, 2011 75days

  2. U.S. National HF Radar Network Segment Color Key Red > 90 km 70 km < Orange < 90 km 70 km > Green http://ioos.gov/hfradar/

  3. Existing and Proposed HF Radars for the United States

  4. Google Earth Map: Existing Sites Alaska - 3 Puerto Rico - 2 CONUS - 104 Hawaii - 3

  5. Google Earth Map: Proposed Sites Alaska - 17 Puerto Rico - 20 CONUS - 262 Pacific Islands - 21

  6. LEAP2-RUT-T2 TASK 2: Purchase Shore Station Components November 2, 2010 – April 7, 2011 105 days • Purchase SeaSonde SSRS-100 13 MHz • GPS Synchronization • Lightning Protection Package • Bistatic Software Package • Shore Station Infrastructure (shed, enclosure, communications, power, UPS)

  7. LEAP2-RUT-T2

  8. LEAP2-RUT-T2 TASK 2: Install Shore Station March 25, 2011 – June 17, 2011 60 days • Specify Shore Location • Obtain Necessary Approvals and Permits • Install and Calibrate System • Initial System Testing in MonoStatic Mode

  9. LEAP2-RUT-T2 Existing Medium Range Network

  10. LEAP2-RUT-T2 Future Medium Range Network

  11. LEAP2-RUT-T2 Belmar Fishing Club

  12. LEAP2-RUT-T3 TASK 3: Association Requirements Analysis March 25, 2011 – June 17, 2011 60 days • Define Performance Requirements for Association Algorithms • Develop Preliminary Implementation Plan for Association of Data from Multiple Shore Stations

  13. Processing Matrix Threshold (dB) FFT Points

  14. Processing Time and Velocity Resolution

  15. LEAP2-RUT-T4 TASK 4: Develop Implementation Plan November 2, 2010 – February 24, 2011 75days • Assist OPT in defining data structure, protocol and hardware configuration required for LEAP Regional Server Network

  16. Portals, Nodes, Sites

  17. LEAP2-RUT-T5 TASK 5: Design Vessel Detection Architecture April 8, 2011 – July 1, 2011 60 days • Optimize threshold levels, background levels and integration times for vessel detection

  18. LEAP2-RUT-T6 Multi-Static Operations TASK 6: April 8, 2011 – August 4, 2011 83 days • Add second to multi-static processing • Configure Software and Hardware for multi-static operation • Produce data from BRNT, BELM, • Continue multi-static operation, testing and optimization

  19. LEAP-R-T4 Radial Current Vectors

  20. Totals from Radials

  21. LEAP-R-T4 Elliptical Current Vectors

  22. Totals from Radials & Ellipticals

  23. LEAP2-RUT-T7 Bistatic Interface Development TASK 7: November 2, 2010 – April 28, 2011 120 days • Support OPT with Tx/Buoy interface • Provide detailed mechanical/ electrical specifications for shock and vibration, positional stability criteria • Support systems integration and testing at OPT • Analyze performance of Vessel detection based on bistatic operation

  24. LEAP2-RUT-T7 Bistatic Transmitter Package Transmit Antenna Atop Buoy

  25. LEAP2-RUT-T8 Refinement of Multistatic Detection Technologies TASK 8: August 5, 2011 – September 16, 2011 30 days • Develop Improved Detection Methodologies • Report on detection improvements

  26. LEAP2-RUT-T9 Real Time Transition Studies TASK 9: August 5, 2011 – September 16, 2011 30 days • Update Shore Stations to automate production of Detection files at the shore station • Implement ftp or equivalent to provide detection files to regional node • Make real time architecture recommendations

More Related