2/28: More CPM: Crashing

2/28: More CPM: Crashing. Roll call / return exams / return homework Review: Critical Path Management Creating the CPM diagram Calculating the critical path Calculating the ES & EF, the LS & LF Calculating the slack

haven
Download Presentation

2/28: More CPM: Crashing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2/28: More CPM: Crashing • Roll call / return exams / return homework • Review: Critical Path Management • Creating the CPM diagram • Calculating the critical path • Calculating the ES & EF, the LS & LF • Calculating the slack • Crashing: When you’re willing to spend money to get the project done sooner. • Small Group Exercise • Homework for the week

  2. Exam Scores • Maximum: 100% (four people) • Minimum: 63% • Mean & Median: 88% • Correct exams are available at:http://www.adbook.net/teach022/305/m.htm

  3. D 4 F 5 A 4 C 2 start finish E 7 B 5 G 1 CPM: Creating the Diagram

  4. D 4 F 5 A 4 C 2 start finish E 7 B 5 G 1 CPM: Calculating the Critical Path Possible paths from start to finish: A-C-D-F A-C-E B-G 4+2+4+5 = 15 4+2+7 = 13 5+1 = 6

  5. CPM: Calculating the ES & EF Early start: how soon it can start Early finish: ES + Duration D | 6 10 4 | F | 10 15 5 | A | 0 4 4 | C | 4 6 2 | start finish E | 6 13 7 | B | 0 5 5 | G | 5 6 1 |

  6. CPM: Calculating the LS & LF Late finish: the last possible time it must be done to not affect the overall project time. Late start: LF - Duration D | 6 10 4 | 6 10 F | 10 15 5 | 10 15 A | 0 4 4 | 0 4 C | 4 6 2 | 4 6 start finish E | 6 13 7 | 8 15 B | 0 5 5 | 9 14 G | 5 6 1 | 14 15

  7. CPM: Calculating the slack Slack: how much “wiggle room” you have for an activity Slack = LS – ES = LF - EF S=0 S=0 D | 6 10 4 | 6 10 S=0 S=0 F | 10 15 5 | 10 15 A | 0 4 4 | 0 4 C | 4 6 2 | 4 6 start finish S=2 E | 6 13 7 | 8 15 S=9 S=9 B | 0 5 5 | 9 14 G | 5 6 1 | 14 15

  8. Crashing: Buying Time • Sometimes you can buy a quicker time for an activity • Paying overtime • Paying for another worker to help • Paying for guaranteed quicker delivery (EX: FedEx) • But is it worth it?

  9. Crashing Activity Times • Things to consider: • Is the activity on the critical path? • How much will it cost to crash the activity? • Are there other activities that are more cost-effective to crash? • How much do you need to crash the project time?

  10. Crashing Activity Times: Example Shorten project by 2 days while minimizing costs.

  11. Crashing Activity Times: Example Shorten project by 2 days while minimizing costs. First, calculate the cost/day to crash each activity.

  12. Crashing Activity Times: Example Shorten project by 2 days while minimizing costs. Next, see what’s on the critical path.

  13. Crashing Activity Times: Example Shorten project by 2 days while minimizing costs. Finally, see what the cheapest way to reduce is.

  14. D 4 F 5 A 4 C 2 start finish E 7 B 5 G 1 Crashing Activities: Watch Out • If we had to crash the project by more than two days, we would have had to look again – the critical path may change. A-C-D-F A-C-E B-G 4+2+4+5 = 15 4+2+7 = 13 5+1 = 6

  15. Small Group Exercise Crash the project by 3 days while minimizing costs.

  16. Homework: Do it on PAPER • Ch. 10 #21 a & b • Ch. 10 #22 b & c • Ch. 10 #24 a, c, d (use 26 weeks), & f