1 / 12

中央大學營管所學分班 工程契約與文件管理 CHAPTER 16 TEST AFTER COMPLETION Silver Book, 2002 Clause 12.

中央大學營管所學分班 工程契約與文件管理 CHAPTER 16 TEST AFTER COMPLETION Silver Book, 2002 Clause 12. 授課教授 : 謝定亞 博士. 學員 : 陳忠正 ( 研發中心管線組 ). 2008.01.19. 12.1 Procedure for Test after Completion 12.2 Delayed Tests 12.3 Retesting 12.4 Failure to Pass Test after Completion.

hashim
Download Presentation

中央大學營管所學分班 工程契約與文件管理 CHAPTER 16 TEST AFTER COMPLETION Silver Book, 2002 Clause 12.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 中央大學營管所學分班工程契約與文件管理CHAPTER 16TEST AFTER COMPLETIONSilver Book, 2002Clause 12. 授課教授 : 謝定亞 博士 學員 : 陳忠正 (研發中心管線組) 2008.01.19

  2. 12.1 Procedure for Test after Completion 12.2 Delayed Tests12.3 Retesting 12.4 Failure to Pass Test after Completion CHAPTER 16TEST AFTER COMPLETION

  3. 12.1 Procedure for Test after Completion(1/2) • If Test after Completion are specified in the Contract, this Clause shall apply. Unless otherwise stated in the Particular Conditions: • the Employer shall provide all electricity,fuel and materials, and make the Employer’s Personnel and Plant available • the Contractor shall provide any other plant, equipment and suitably qualified and experienced staff, as are necessary to carry out the Test after Completion efficiently; • the Contractor shall carry out the Test after Completion in the presence of such Employer’s and/or Contractor’s Personnel as either Party may reasonably request.

  4. 12.1 Procedure for Test after Completion(2/2) • The Test after Completion shall be carried out as soon as is reasonably practicable after the Works or Section have been taken over by the Employer. The Employer shall give to the Contractor 21 days’ notice of the date after which the Test after Completion will be carried out. Unless otherwise agreed, these Tests shall be carried out within 14 days after this date, on the day or days determined by the Employer. • The results of the Test after Completion shall be complied and evaluated by the Contractor, who shall prepare a detailed report. Appropriate account shall be taken of the effect of the Employer’s prior use of the work.

  5. 12.2 Delayed Tests • If the Contractor incurs Cost as a result of any unreasonable delay by the Employer to the Test after Completion, the Contractor shall (i) give notice to the Employer and (ii) be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to payment of any such Cost plus reasonable profit, which shall be added to the Contract Price. • After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine this Cost and profit. • If, for reasons not attributable to the Contractor, a Test after Completion on the Works or any Section cannot be completed during the Defects Notification Period( or any other period agreed upon by both Parties), then the Works or Section shall be deemed to have passed this Test after Completion.

  6. 12.3 Retesting • If the Works, or a Section, fail to pass the Test after Completion: • sub-paragraph (b) of Sub-Clause 11.1 [Completion of Outstanding Work and Remedying of Defects] shall apply, and • either Party may then require the failed Test, and the Tests after Completion on any related work, to be repeated under the same terms and conditions. • If and to the extent that this failure and retesting are attributable to any of the matters listed in sub-paragraphs (a) to (d) of Sub-Clause 11.2 [Cost of Remedying Defects] and cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these costs to the Employer.

  7. 12.4 Failure to Pass Test after Completion(1/3) • If the following conditions apply, namely: • the Works, or a Section, fail to pass any or all of the Tests after Completion, • the relevant sum payable as non-performance damages for this failure is stated ( or its method of calculation is defined) in the Contract, and • the Contractor pays this relevant sum to the Employer during the Defects Notification Period, then the Works, or a Section shall be deemed to have passed these Tests after Completion.

  8. 12.4 Failure to Pass Test after Completion(2/3) • If the Works, or a Section, fail to pass a Test after Completion and the Contractor proposes to make adjustments or modifications to the Works or such Section, the Contractor may be instructed by (or on behalf of) the Employer that right of access to the Works or Section cannot be given until a time that is convenient to the Employer. • The Contractor shall then remain liable to carry out the adjustments or modification and to satisfy this Test, within a reasonable period of receiving notice by (or on behalf of) the Employer of the time that is convenient to the Employer. • However, if the contractor does not receive this notice during the relevant Defects Notification Period, the Contractor shall be relieved of this obligation and the Works or Section (as the case may be) shall be deemed to have passed this Test after Completion.

  9. 12.4 Failure to Pass Test after Completion(3/3) • If the Contract incurs additional Cost as a result of any unreasonable delay by the Employer in permitting access to the Works or Plant by the Contractor, either to investigate the causes of a failure to pass a Test after Completion or to carry out any adjustments or modifications, the Contractor shall (i) give notice to the Employer and (ii) be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to payment of any such Cost plus reasonable profit, which shall added to the Contract Price. After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine this Cost and Profit.

  10. Figure 16.1 Tests after completion under the FIDIC Silver Book • C carries out tests after completion as soon as reasonably practicable after taking over: • upon 21 days’ notice from E of date after which tests maybe carried out,and • within 14 days of the notified date, unless otherwise agree (12.1) C entitled to payment of costs incurred plus reasonable profit (12.2) Are the tests carried out during the defects notification Period? Does E unreasonably delay the tests after completion? YES NO NO YES Do the works or section pass the tests after completion? Is the reason attributable to C? C still obligated to carry out tests after completion. YES YES NO NO YES

  11. Has C paid relevant non-performance damages for this failure? (12.4) YES NO NO YES Does either party require retesting? (12.3) Works or section deemed to have passed tests after completion (12.2). YES NO C obligated to remedy defects in order to pass tests (12.3) NO Results of the tests after completion complied and evaluated by C, who prepare a detailed report, taking into account the effect of any prior use of the works by E (12.1). C pays E’s costs if C responsible under contract for cost of remedying defect causing test failure (12.3). Tests after completion completed. YES

  12. Test after Completion 簡報結束 敬請指教

More Related