1 / 15

27 March 2013

MYPD3 Briefing Session – Portfolio Committee on Energy. 27 March 2013. ESKOM MYPD3 Application in Summary. MYPD3 Decision in Summary. Approved Regulatory Asset Base. Adjustments to align with the MYPD2 phasing in of the RAB Assets commissioning dates adjusted to cater for the delays

hana
Download Presentation

27 March 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MYPD3 Briefing Session – Portfolio Committee on Energy 27 March 2013

  2. ESKOM MYPD3 Application in Summary

  3. MYPD3 Decision in Summary

  4. Approved Regulatory Asset Base • Adjustments to align with the MYPD2 phasing in of the RAB • Assets commissioning dates adjusted to cater for the delays • Depreciation rate not adjusted (Depreciation amount will change due to changes in asset base costs)

  5. Actual Return Approved • The allowed returns were calculated to allow Eskom to meet its debt obligation – see next slide • These returns were also considered to allow for affordable and gradually increasing pricings and to avoid price spikes

  6. Primary Energy • Coal Prices escalated at 10% over the MYPD3 period • Base price for 2013/14 adjusted to reflect actual history • IPP Commissioning dates and associated costs re-adjusted to reflect delays • Efficiencies on the burn rate and load factors • Renewable IPP adjusted to reflect revised dates • Electricity purchases & SBP procurement costs disallowed

  7. Depreciation

  8. Integrated Demand Management (IDM) • Operational DMP maintained • Supplemental limited to 800 MW • Power Buy Back allocation not approved • SWH & Heat pumps not approved • Compressed air, process optimisation removed or limited

  9. Operating expenditure (excl Primary Energy) • Manpower costs were adjusted in line with inflation plus a salary negotiating margin (1.4%) • Additional staff compliment for new power plants included (Benchmarked @ 1.24/MW) • Debt arrears reduced from 0.6% from 0.5% • “Other costs” limited to increase by inflation • Double counted items removed

  10. Capital Expenditure • Transmission adjustment based on detailed scope assessment and benchmarked costs/km or MVA. • Distribution capex was adjusted from Eskom unit cost of R2.18/km to R1.74/km over the MYPD3 period – projects not altered • Generation adjusted to remove excessive contingency fees and Owners Development Costs,

  11. Weighted Average Cost of Capital • The current methodology prescribes the use of 25 years average to calculate the • real risk free rate • The 12 months average reflect the current market conditions

  12. Eskom’s Financial sustainability Goals 2 Source: NERSA Rfd

  13. Eskom’s Financial Sustainability: Cash Flow Source: NERSA Rfd

  14. The Tariffs – issues considered and approved • Increase to Homelight 20A customers consuming up to 350 kWh/month limited to inflationary increase of 5.6 %. Above this consumption level customers will see an increase of 7.6 % • All residential customers will see an increase of 8 % p.a. • Eskom to ensure: • T-O-U off-peak to peak demand adjusted from a ration of 1:9 to 1:8 • Tariff cross-subsidies to be shown transparently • The use-of-system charges to be based on cost per voltage level for all large power customers • The reliability and service charge to be unbundled from the energy charge • The environmental levy to be included in the energy charge and not shown separately • Eskom to ensure alternate tariff options are made available to municipalities with a predominantly residential load mix

  15. THANK YOU

More Related