Post-EPS Status at PMET-7. 2015. 2007. 2008. 2009. 2010. 2021. 2012. 2011. 2014. 2016. 2017. 2018. 2019. 2013. 2020. Post-EPS Overall Programme Planning. EUM Phase 0. Phase A. Phase B. Phase C/D. Ops. Readiness of IR and MW Sounding VIS/IR Imaging Missions.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Post-EPS Status at PMET-7' - giuseppe


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
post eps overall programme planning

2015

2007

2008

2009

2010

2021

2012

2011

2014

2016

2017

2018

2019

2013

2020

Post-EPS Overall Programme Planning

EUM Phase 0

Phase A

Phase B

Phase C/D

Ops

Readiness of

IR and MW Sounding

VIS/IR Imaging Missions

All Post-EPS Missions

Prep. Programme

Development and Operation Programme

EUMETSAT

Approval Processes

ESA Programme

ESA Ministerial Conf.

go ahead for phase B/C/D

post eps programme planning timeline phases 0 and a

2007

2008

2009

2010

2011

Post-EPS Programme Planning, Timeline Phases 0 and A

EUM Phase 0

Phase A

ESA Ph. 0 Studies

Ph. A Studies

Prelim. Assessment

Review

(missions shortlist)

Mission

Definition

Review

Preliminary

Requirements

Review

MTR

PCR

2nd

User Cons.

Workshop

EUM Approval

of Preparatory

Programme

ESA C-Min-11

go-ahead for Ph. B/C/D

MTR = Mid Term Review

PCR = Preliminary Concepts Review

cooperation with noaa on jps 1 3
Cooperation with NOAA on JPS (1/3)
  • Regular meetings of the technical and high-level working groups are held with NOAA to work towards an extended cooperation past IJPS and JTA
  • A concept paper has been drafted for negotiation of a JPS and is under approval by DB
  • Model is similar to that of IJPS and JTA
    • NOAA spacecraft operate in early morning and afternoon orbits
    • EUMETSAT spacecraft operates in mid-morning orbit
    • Exchange of instruments as far as practicable
    • Collaboration on developments for data exploitation
    • Exchange of data
  • Timeline
    • Draft JPS agreement finalised in Q4 2009
    • JPS agreement to EUMETSAT Council and US authorities at end of Phase A
recent council decisions relevant to post eps 1 2
Recent Council Decisions Relevant to Post-EPS (1/2)
  • The opportunity of flying Earth observation payloads on the Iridium-NEXT constellation of satellites should not be pursued
  • Adopted the initiating resolution on the preparation of a Jason follow-on programme, authorising the DG to prepare a full Jason2 follow-on optional programme proposal and a related declaration (to be adopted)
    • All 21 member states indicated their interest in participation
    • Funding scheme needs to be secured among partners before optional programme can be proposed
  • Adopted way forward for the implementation of GMES Sentinel 5 on Post-EPS
    • Consider S-5 as PEPS baseline in terms of design and development
    • Rely on ESA provided S-5 ground processor
    • Manage delta-development within an optimised approach for GS procurement
    • Have full control of the overall process up to GS level and end-to-end system verification and validation
    • Discuss with EU about the necessary funding to cover operations costs of S-5
recent council decisions relevant to post eps 2 2
Recent Council Decisions Relevant to Post-EPS (2/2)
  • With respect to the GMES long-term governance EUMETSAT should play the role of operational agency in the areas of
    • GMES Marine Core Service
    • GMES Atmosphere Service
    • The planned GMES Service for Climate Monitoring
  • During GMES pre-operations, access by the three GMES fast track services and two pilot services to EUMETSAT data will be granted free of charge
  • For the GMES S-3 development , a third party programme will be established
current activities
Current activities
  • ESA: 2nd industrial Phase 0 study for Post-EPS (Thales Alenia Space has been kicked off) in July 2008
  • Preliminary Assessment Review was held in June 2008
  • Mid Term Reviews to be held in December 2008 (Astrium)
  • and January 2009 (Thales)
  • Follow national studies
    • DLR: METimage, Phase A completed, Phase B started in September 2008
    • CNES: IASI follow-on, Phase 0 completed
objectives of preliminary assessment review par
Objectives of Preliminary Assessment Review (PAR)
  • “to decide on the observation missions to be retained for further study”
      • ref. to “potential for implementation within the anticipated budgetary constraints” (EUM/C/63/07/DOC/46)
    • It implies
    • a review of the preliminary assessment of the candidate missions, and its consistency with mission and programmatic requirements
    • It is an opportunity to
    • give recommendations on the execution of the industrial studies
par non objectives
PAR Non-Objectives
  • The PAR is NOT expected to anticipate:
    • Specific payload options (for those missions to be retained)
    • A space or ground segment configuration
  • Available elements are too preliminary, often and on purpose limited to a “baseline” or heritage concept for a rapid programmatic/cost assessment
  • Relevant concepts are to be established in the industrial studies managed by ESA
par non observation missions services
PAR: Non-Observation Missions/Services
  • Data Collection System (PARD, TBC)
  • Search & Rescue (PARD, TBC)
  • User Services (MRD):
    • Direct Data Broadcast
    • Near Real Time Data Distribution
    • Archiving and Retrieval
    • Reprocessing
    • User Support

Space and Ground Segment impact

Ground Segment impact

Not in scope of PAR

But system impact should be taken into account

scope phase 0 studies
Scope: Phase 0 Studies

Post-EPS

Specific

Approach

“standard”

Phase 0

par outcome missions to be retained in phase 0 studies
PAR Outcome – Missions to be Retained in Phase 0 Studies
  • Infrared Sounding Mission (IRS)
    • Atmospheric Chemistry requirements must not drive the instrument
  • Microwave Sounding Mission (MWS)
  • Visible/Infrared Imaging Mission (VII)
  • Scatterometry Mission (SCA)
  • Microwave Imaging Mission for Precipitation (MWI – Precipitation)
  • Radio Occultation Mission (RO)
  • Multi-Viewing Multi-Frequency, Multi-Polarisation Imaging Mission (3MI)
  • Accommodation of Radiant Energy Mission (RER)
  • Accommodation of Ultraviolet Visible Near Infrared Shortwave Infrared Imaging Mission (UVNS) via GMES Sentinel-5
2 nd peps uc workshop objectives 1 2
2nd PEPS UC Workshop – Objectives (1/2)
  • Inform users on relevant mission requirements
    • WMO: vision and requirements of the WMO space programme in the PEPS era
    • GOS: evolution of the space-based observing system
    • EUMETSAT: lessons learnt from EPS
  • Introduce candidate observation missions, prioritisation, and down-selection process for industrial studies
    • PMET-Chair: introduction to the candidate observation missions
    • EUMETSAT: details on observation missions, their prioritisation and down-selection
  • Present the potential of the system in various application areas
    • PMET
2 nd peps uc workshop objectives 2 2
2nd PEPS UC Workshop – Objectives (2/2)
  • Inform users on programmatic assumptions and constraints
    • EUMETSAT
  • Inform users on the status of concept studies
    • EUMETSAT: notional concepts
    • ESA: Phase 0 studies outcome
    • ESA: Status of GMES S-5
  • Inform users on US approach for next generation polar system
    • NOAA: NPOESS and its follow-on
  • Inform users on status of related projects
    • CNES: IASI follow-on
    • DLR: METimage
  • Acquire users’ feedback