Cryogenic System Design for SCLF Zhengrong OUYANG SINAP. contents. Requirements System design Main equipment Utilities Schedule. Cryo-Modules. Cryo -Modules: x 77. 1.3 GHz Cryo -Modules: x 75 Cavities: 8 Length 12 m
E N D
contents • Requirements • System design • Main equipment • Utilities • Schedule
Cryo-Modules Cryo-Modules: x 77 • 1.3 GHz Cryo-Modules: x 75 • Cavities: 8 • Length 12 m • Weight 8,000 kg • 3.9 GHz Cryo-Modules: x 2 • Cavities: 8 • Length 6 m • Weight 4,000 kg
Heat Load of Cryogenic System 3* 4 kW/2 K
Cryogenic Plant Capacity • Two plants (one for running SRF cryomodules, another for running SRF cryomodules+SCUs), three refrigerators, each : • 4 kW @ 2.0K • 1.3kW @ 5K • 15kW @ 35~40K • 15 g/s of liquefaction @ 4.5 K • Each refrigerator uses either 5 stage serial connected sub-atmospheric centrifugal compressors (cold compressors) or 3~4 stages cold compressors + warm vacuum compressors to pump up to 215 g/s of 2.0K helium gas from 0.027 atm to 1.2 atm. • The cryoplants are to be used for cooling75 sets of 1.3GHz SRF cryomodules (8 9-cell cavities in one cryostat + SC magnets+ Cold BPM), and 3-40 SC undulators .
Bird’s view of the SCLF length~ 3.2km,underground 38m Beamline Exp hall undulator 2nd plant Exp hall 1st plant Linac Injector
1st Cryo-Plant Storage & tower zone Compressor & coldbox Shaft 1
2nd Cryo-Plant CMTF Comp.&coldbox Storage.&tower Shaft 2
Cryogenics systems schematic layout Compressor Compressor Compressor Purification Purification Purification 4.5K CB 4.5K CB 4.5K CB Lhe Dewar Lhe Dewar Lhe Dewar CP1 CP2 CP3 2K CB 2K CB 2K CB Shaft #1 Dis. Box Dis. Box Shaft #2 L0 LH L1 BC1 L2(CM4-21) BC2 L3(CM22-CM51) BREAK L4(CM52-CM75)
Refrigerator (4 kW/2 K) ~18 kWeq 4.5K
Compressor For the system at Full Power ~ 13.2 MW Elec.
Utilities Cryogenic system LN2. consumption: 50 m3/day Electrical power: 13.2 MW Cooling water: 1250 m3/hour
Utilities liquid helium storage(3*10000l) • helium gas storage(15000m3) • purification and recovery(50g/s) • liquid nitrogen storage(150 m3) • guard vacuum system
Summary • Designing of cryogenic system ( 3*4 kW/2 K, cold compressor) • Arranging equipment of the system; • Infrastructure ( building, power, cooling…); • CMTF (contract of refrigerator);
1st Plant Cooling tower LN2 storage He storage compressor Cold box compressor Interface-box