“LA INGENIERIA Y LA INICIATIVA PRIVADA EN EL PROYECTO OLMOS”

“LA INGENIERIA Y LA INICIATIVA PRIVADA EN EL PROYECTO OLMOS”. HUMBERTO HEREDIA MORALES. PROYECTO HIDROENERGETICO Y DE IRRIGACION OLMOS.

gage
Download Presentation

“LA INGENIERIA Y LA INICIATIVA PRIVADA EN EL PROYECTO OLMOS”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “LA INGENIERIA Y LA INICIATIVA PRIVADA EN EL PROYECTO OLMOS” HUMBERTO HEREDIA MORALES

  2. PROYECTO HIDROENERGETICO Y DE IRRIGACION OLMOS • Trasvasar aguas del río Huancabamba 710’ m3, Tabaconas y Manchara 470’ en la primera etapa y llegar hasta 2,050’ en la 2ª etapa con los aportes del Huancabamba bajo. • Irrigar más de 200 mil ha de tierras de Olmos y el Alto Piura • Generar hasta 2,390 millones de kwh anuales de energía en la primera etapa y más de 5,100 millones de kwh anuales al culminarse la 2ª etapa

  3. DESARROLLO VIA CONCESIONES • Viabilizaba la ejecución del Proyecto Olmos al permitir la inversión privada, mediante esquemas rentables y atractivos.

  4. COMPONENTES PERÍODO DE CONSTRUCCIÓN EN AÑOS PERÍODO DE OPERACIÓN RECUPERACIÓN DE LA INVERSIÓN 1 2 3 4 5 DESARROLLO VÍA FASES DE CONCESIÓN 20 años Tarifa por trasvase de agua PRIMERA FASE Túnel Trasandino Presa Limón SEGUNDA FASE Central (es) Hidroeléctrica (s) Indefinida Tarifa por potencia y venta de energía TERCERA FASE Obras de Distribución de Agua Mínimo 20 años Máximo 60 años Tarifa por venta del servicio de agua Perpetuo Ingreso por Producción SUBASTA DE TIERRAS

  5. El contrato para la ejecución de las obras de trasvase se firmó en Julio del año 2004 durante el gobierno del presidente Alejandro Toledo y después que Lambayeque se movilizara masivamente reclamando la ejecución de nuestro principal proyecto de desarrollo • La segunda Fase o sea la construcción de las CCHH fracaso debido a que el gobierno central con el apoyo del gobierno Regional entregan parte de las aguas del Proyecto Olmos al Alto Piura contra todo criterio técnico. • Al firmarse el Contrato para esta primera fase ya existía una donación japonesa para elaborar los estudios para las Obras de riego, inexplicablemente recién en Junio del año pasado – 2008 - se entrega la buena pro a la empresa NipponKoei.

  6. INICIATIVA PRIVADA PARA LA EJECUCION DE LAS OBRAS DE RIEGO • IP Tiene como objetivo incentivar la inversión privada para ejecutar obras que sean de interés publico y de beneficio para el país. • Consorcio Olmos propiedad de la empresa Odebrecht, propone IP para ejecutar las obras de riego del Proyecto Olmos, ante la urgencia de contar con infraestructura de riego para utilizar la aguas que llegaran a la costa el próximo año. • Gobierno Regional debió analizar propuesta y si realmente era beneficiosa, publicar una Declaratoria de Interés con la finalidad de atraer a otros interesados

  7. CUADRO COMPARATIVO

  8. CUADRO COMPARATIVO

  9. CUADRO COMPARATIVO

  10. Se puede apreciar que los requisitos exigidos tenían como objetivo no “atraer” sino mas bien “evitar” que se presenten más postores.

  11. CONDICIONES DE LA PROPUESTA DEL CONSORCIO OLMOS • Red de canales de riego • Bocatoma en el sector “El muerto” • No construirá la Presa Olmos • Presupuesto de Obras de 185’ • “Cierre financiero (para inicio de obra)”

  12. ALTERNATIVA EL MUERTO RIO CASCAJAL CIUDAD DE OLMOS VALLE VIEJO A IRRIGAR 3,000 Ha CANAL CENTRAL ZONA CENTRAL 23,500 HA BOCATOMA EL MUERTO DIQUE DE ENCAUCE COMUNIDAD CAMPESINA A IRRIGAR 2,500 Ha BOCATOMAS VALLE VIEJO CANAL SUR RIO OLMOS AREAS DE VALLE VIEJO COMUNIDAD CAMPESINA SANTO DOMINGO DE OLMOS ZONA SUR 14,500 HA CARRETERA PANAMERICANA ANTIGUA AREAS IRRIGADAS 0 5 Km 10 Km 20 Km

  13. PRESUPUESTO ESTIMADO POR PROINVERSION Y EL GOBIERNO REGIONAL AL MOMENTO DE FIRMARSE EL CONTRATO CON LA NIPPON KOEI FUE DE $ 180’ • ODEBRETCH PLANTEA UN ESQUEMA ANTICUADO ADUCIENDO EL MAYOR COSTO DE LO PROPUESTO POR EL PEOT Y PROINVERSION, PERO PLANTEA UN PRESUPUESTO MAYOR.

  14. ANALISIS DE LOS PRECIOS QUE JUSTIFICAN SU PROPUESTA

  15. COSTO DEL M3 DE CONCRETO PREMEZCLADO, A LOS QUE HAY QUE AGREGAR FLETE CONCRETO PREMEZCLADO S/. a. Concreto de 100 Kg/cm2 (m3) 222.04 b. Concreto de 140 Kg/cm2 (m3) 230.46 c. Concreto de 175 Kg/cm2 (m3) 240.17 d. Concreto de 210 Kg/cm2 (m3) 250.37 e. Concreto de 245 Kg/cm2 (m3) 268.07 COSTO DEL ENCOFRADO PARA UN M3 DE CONCRETO • Estimando de acuerdo a las estructuras propuestas un promedio de 6 a 10 m2 de encofrado por m3 de concreto, el costo será de aproximadamente S/ 200 a S/ 300.00

  16. COSTO DEL ACERO PARA UN M3 DE CONCRETO • Asumiendo una cuantía promedio de 0.006, tenemos 60 cm2 de acero por m3 de concreto, lo que equivale a 48 kg por m3, con un costo promedio de S/ 250.00 ¡El precio total del concreto incluido colocación del concreto, encofrado, acero, fletes y gastos generales es aproximadamente $ 350.00! • ANALIZANDO OTRAS PARTIDAS POR EJEMPLO : COSTO DEL M2 DE REVESTIMIENTO DE CANALES TAMBIEN ESTA SOBREVALUADO PUES SE TRATA DE UNA LOSA DE CONCRETO SIMPLE DE 7.5 CM DE ESPESOR

  17. PROPUESTA SOLO BENEFICIARA A ODEBRETCH • NO ARRIESGAN NADA, PUES LAS OBRAS SE FINANCIARAN CON LA VENTA DE 38,000 HA DE TIERRAS, LAS CUALES DEBEN VENDERSE TOTALMENTE (CIERRE FINANCIERO) A UN PRECIO MINIMO DE $ 4,000.00 • TENDRAN EL MANEJO DE LAS AGUAS POR 25 AÑOS DE CONCESION, COBRANDO 6.125 CTVS DE DÓLAR, AGUA POR LAS QUE EL ESTADO PERUANO LES PAGARA 6.59 CTVS DE DÓLAR.

  18. PROPUESTA DE ODEBRECHT ES ANTITECNICA • SISTEMA DE CANALES ANULA VENTAJAS DEL PROYECTO OLMOS, DE LOGRAR RIEGO PRESURIZADO, EVITANDO SOBRECOSTOS A LOS DUEÑOS DE LAS TIERRAS • SE PERDERAN MAS DE 80’ DE M3 DE AGUA: PERDIDAS POR INFILTRACION, EVAPORACION, ROBO • LA NO EJECUCION DE LA PRESA OLMOS TENDRA LAS SIGUIENTES CONSECUENCIAS: • PERMITIRA LA INUNDACION DE ENORMES EXTENSIONES DE TIERRAS CON SU CONSECUENTE SALINIZACION • POSTERGARA AUN MAS LA CONSTRUCCION DE LAS CENTRALES HIDROELECTRICAS • NO CONTEMPLA MEDIDAS PARA MITIGAR LOS EFECTOS NEGATIVOS DE SU ESQUEMA

  19. El Comercio.com.pe(26 de junio del 2008) Firman contrato para estudios de PreInversión de proyecto Olmos 14:48 | La firma NipponKoei realizará los estudios de factibilidad, PreInversión y demás trabajos conexos para la conducción y distribución de agua de riego de Olmos (Andina).- El presidente regional de Lambayeque, YehudeSimon, y el director ejecutivo de la Agencia de Promoción de la Inversión Privada (ProInversión), David Lemor, suscribieron hoy el contrato para el inicio de los estudios de PreInversión de las obras de conducción y distribución de agua de riego del proyecto integral Olmos. La firma NipponKoei fue la ganadora del concurso de selección convocado por ProInversión, para realizar los estudios de factibilidad, PreInversión y demás trabajos conexos del Proyecto Obras de Conducción y Distribución de Agua de Riego de Olmos. La realización del Proyecto Olmos permitirá promover inversiones mediante la Asociación Público Privada (APP) por 180 millones de dólares en la construcción de la infraestructura hidráulica de riego del Proyectos Olmos, indicó Lemor. Asimismo, dijo que estas obras incentivarán inversiones privadas por 370 millones de dólares en la habilitación y desarrollo agrícola de 37.000 nuevas hectáreas orientadas a la agroexportación, con sistema de riego presurizado

  20. "Para ello se ha contemplado entregar en concesión la construcción, operación y mantenimiento de las obras de conducción y distribución de agua por un período de 20 años", agregó. También señaló que con la ejecución de esta infraestructura de riego se incrementará el valor bruto de la producción agrícola y agroindustrial del país en el orden de 500 millones de dólares anuales y creará alrededor de 100 mil puestos de trabajo directos en actividades agrícolas y de agroexportación. NipponKoei tendrá un plazo de nueves meses para realizar el estudio de factibilidad para la concesión de la infraestructura mayor de riego, el plan maestro y el marco institucional nacional para la zona de influencia del Proyecto Olmos (cuenca de Cascajal, Olmos, Motupe y La Leche) para el sistema de riego y plan de Comunicaciones y Sensibilización. También deberá actualizar el Estudio de Impacto Ambiental (IEA) y el Plan de Manejo Ambiental y Social. El presupuesto base para la ejecución de los estudios asciende a un millón 925 mil dólares, con una contrapartida nacional de 645 mil dólares y de un millón 280 mil dólares que el Banco Interamericano de Desarrollo (BID) otorga como fondo de cooperación técnica no reembolsable. El fondo otorgado por el BID es con cargo a los recursos del Fondo Especial Japonés de Reducción de la Pobreza, previsto para financiar los estudios del preinversión del componente de riego del Proyecto Olmos. Asimismo, indicó que en la negociación de la cooperación técnica llevada a cabo entre el BID y el Ministerio de Economía y Finanzas (MEF) se designó como organismo ejecutor de la cooperación Técnica a ProInversión.