1 / 9

GIST 19: GGSPS Planning

GIST 19: GGSPS Planning. GGSPS Development & Review Planning Andy Smith GGSPS software project manager. Overview of issues. With current funding, no effort is available for development work in the following areas: Data Re-Ordering Level 2 monthly averaging Data Re-Processing

frankhenry
Download Presentation

GIST 19: GGSPS Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GIST 19: GGSPS Planning GGSPS Development & Review Planning Andy Smith GGSPS software project manager

  2. Overview of issues • With current funding, no effort is available for development work in the following areas: • Data Re-Ordering • Level 2 monthly averaging • Data Re-Processing • plus a number of known non-conformances • New work has arisen due to unanticipated problems: • geolocation • stray light • The above plus • ramp-down of most development effort • continuation of product processing development and validation • leads to uncertainty over Acceptance and System Test plans GIST 19: GGSPS planning

  3. How did we get here? • Tight funding from the outset • Launch delay/IMPF delay: • loss of team members and background knowledge • extra work to deal with SEVIRI header generation • Operations: • development team effort used to support commissioning and calibration • urgent need to fix “real data” software problems • unanticipated problems, e.g. geolocation, stray light • little or no time to plan for continued development • Operational experience required to determine the scope of sub-systems such as Data Re-Ordering GIST 19: GGSPS planning

  4. Data Re-Ordering • Data Re-Ordering: • detect missing/corrupt data and order from UMARF (L0) • documented design exists for an automated system • experience shows that rate of loss of L0 data is low (~2.5%) • most L0 data loss is through isolated events • a minimal, manual ordering system would be sufficient? (would give us >99% L0 coverage for May-Aug sample period) GIST 19: GGSPS planning

  5. Data Re-Processing • Data Re-Processing: • ability to perform bulk reprocessing of the entire data set with improved algorithms or calibration • generation of a consistent archive of science products • development work was delayed from the outset - low priority pre-launch • no formal design exists at present • builds strongly on the finalised NRT processing software GIST 19: GGSPS planning

  6. L2 monthly averaging • Level 2 monthly averaging • averaging of L2 flux products into monthly and “monthly 15-minute binned” products • documented design exists • requires a change of RMIB L2 products archived by GGSPS? GIST 19: GGSPS planning

  7. Reviews: background • The planned “end point” of GGSPS software development is the Acceptance Test and Review • AT is validation of the software against User Requirements • GGSPS was reviewed in July 2002: • - based on Release 2 System Test • Following further development, Release 3 System Test took place in November 2003 • Release 3 was the operational system for “first light” data • “OR3” development has seen further changes to the Operational Release 3 system. GIST 19: GGSPS planning

  8. Current position • Most software development activity stops in Oct 2003 • - unless further funding is found • Product validation and Product Processing software development continues into 2004 • Do we need a further review? If so, when? • Review now, but exclude product validation? • Wait until validation complete? (Most GGSPS staff unavailable) • Several large areas of development require waivers • Data Re-Ordering, • L2 averaging, • Data Re-Processing, • plus known software problems that will not be tackled GIST 19: GGSPS planning

  9. Summary • Additional funding is needed to develop • Data Re-Ordering • L2 Monthly Means • Data Re-Processing • Geolocation fix • Stray light fix (?) • and to address some known software problems (NCRs) • If we don’t get extra funding, we need to consider how to handle Acceptance GIST 19: GGSPS planning

More Related