Seminar: Contract Types & Contract Financing. Program Management Office Course PMT 352B. Version 2.9, 2-25-14. FIXED PRICE TYPES Firm Fixed Price Fixed Price Award Fee Fixed Price Incentive (Firm Target or Successive Target) Fixed Price (Level of Effort)

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Seminar: Contract Types & Contract Financing' - flo


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
seminar contract types contract financing

Seminar: Contract Types& Contract Financing

Program Management Office Course PMT 352B

Version 2.9, 2-25-14

contract types
FIXED PRICE

TYPES

Firm Fixed Price

Fixed Price Award Fee

Fixed Price Incentive (Firm Targetor Successive Target)

Fixed Price (Level of Effort)

Fixed Price with Economic Price Adjustment

Fixed Price with Price Redetermination

COST REIMBURSEMENT

TYPES

Cost Plus Fixed Fee

Cost Plus Incentive Fee

Cost Plus Award Fee

Cost

Cost Sharing

Contract Types
factors in selecting contract type
Factors in Selecting Contract Type
  • Contractor’s
    • technical capability
    • financial responsibility
  • Adequacy of the contractor’s accounting system
  • Concurrent contracts
  • Extent and future of subcontracting
  • Acquisition history
  • Price Competition
  • Price Analysis
  • Cost Analysis
  • Complexity of the requirement
  • Urgency of the requirement
  • Period of Performance or,
  • Length of the production run
general differences
General Differences

Cost Plus

Fixed Fee

Firm Fixed

Price

Cost

Cost

+ Fee

+ Profit

Price

Price

cost risk and contract type
Cost Risk and Contract Type

Greatest Risk to the Contractor

Greatest Risk to the Government

CPFF

CPIF

CPAF

FPI (F)

FPAF

FFP

Technical Risk

Vague technical requirements;

labor and material costs uncertain

Technical requirements defined;

fair & reasonable prices determinable

cost plus fixed fee cpff
Cost Plus Fixed Fee (CPFF)

Fee

Contractor gets 100% of fee regardless of cost

Fixed Fee

Cost

Negotiated and established at contract award:

- Estimated Cost

- Fixed Fee

  • Fee shall not exceed:
  • 15% of estimated contract cost (excluding fee) for R&D contracts
  • 6% of estimated contract cost (excluding fee) for architectural & engineering contracts
  • 10% of estimated contract cost (excluding fee) for other contract types
cost plus incentive fee cpif
CostPlus Incentive Fee (CPIF)

Fee

Maximum Fee

Gov’t/Ktr Share Ratio(s)

Range of

Incentive

Effectiveness

Target Fee

Minimum Fee

Cost

Target Cost

Established at

Contract Award:

  • Fee Adjustment Formula:
  • TC - Actual Cost (AC) = over/underrun
  • Over/underrun x Ktr’s SR = Fee adjustment
  • TF +/- Fee adjustment = Adjusted Fee (AF)
  • (If AF > than MaxF or < than MinF, then use MaxF or
  • MinF, as appropriate, for AF below to determine Final
  • Contact Price)
  • Final Contract Price = AC + AF

- Target Cost (TC)

- Target Fee (TF)

- Maximum Fee (MaxF)

- Minimum Fee (MinF)

- Share Ratio(s) (SR)

slide9

CPIF Final Contract Price: Two Examples

Established at Contract Award:

Target Cost = $1000

Target Fee = $110

Maximum Fee = $130

Minimum Fee = $80

Share Ratio = 75/25

If actual cost is $1300, what is final contract price (FCP)?

(1) $1000 - $1300 = ($300)

(2) ($300) x .25 = ($75)

(3) $110 - $75 = $35

BUT $35 is < than Min Fee, so use Min Fee ($80) to determine FCP

(4) FCP = $1300 + $80 = $1380

  • If actual cost is $800, what is final contract price (FCP)?
  • (1) $1000 - $800 = $200
  • (2) $200 x .25 = $50
  • (3) $110 + $50 = $160
  • BUT $160 is > Max Fee, so use Max Fee ($130) to determine FCP
  • Final Contact Price =
  • $800 + $130 = $930
cost plus award fee cpaf
Cost Plus Award Fee (CPAF)

Government pays all allowable costs

Established at contract award:

Estimated Cost

Base Fee (0 – 3%)

Award Fee Pool Criteria

Base Fee

  • End of each award fee period:
  • Contractor performance evaluated
  • against award fee pool criteria for
  • that period
  • Contractor paid for applicable portion
  • of base fee + amount of award fee
  • pool earned for period

Award Fee Pool

2

3

4

5

1

6

Award Fee Periods

Shall not be used in lieu of CPFF or CPIF when objective measurement is feasible

slide11

Cost Plus Award Fee (CPAF) (2)

  • Advantages to the Government:
    • Subjective/Discretionary decision making
    • Control and flexibility of criteria
    • Unilateral modification to add award fee for period
  • Disadvantages
    • Very people and time intensive
    • Contractor may dispute whether Government followed its award fee plan; not whether it earned “correct” fee
firm fixed price ffp
Firm Fixed Price (FFP)

Profit

Contractor must deliver quality product;

paid negotiated price regardless of cost

C o s t

Price is negotiated and established at contract award

fixed price award fee fpaf

Award Fee Pool

1

2

3

4

6

5

Profit

Fixed Price Award Fee (FPAF)
  • Negotiated and established
  • at contract award
    • Fixed Price

Paid for satisfactory performance

    • Award Fee evaluation criteria

C o s t

  • Award Fee paid in addition to fixed price
  • Based on performance during award fee periods in accordance with Award Fee plan

Award Fee Periods

fixed price incentive firm target fpi f
Fixed Price Incentive (Firm Target) (FPI(F))

Profit

Target Price (TPr) = TC + TP (TC,TP)

Gov’t/Ktr Share Ratio(s)

Point of Total Assumption (PTA) = cost at which the contractor assumes all cost risk (0/100 share ratio from PTA to CP and beyond)

Target Profit (0,TP)

(PTA, $Y)

C o s t

Target Cost (TC,0)

Ceiling Price (CP) (CP,0)

Established at

Contract Award

  • Profit Adjustment Formula:
  • TC- Actual Cost (AC) = over/underrun
  • Over/underrun x Ktr’s SR = Profit adjustment
  • TP +/- Profit adjustment = Adjusted Profit (AP)
  • AC + AP = Final Contract Price (if < CP)
  • If >= CP, then Final Contract Price = CP

- Target Cost (TC)

- Target Profit (TP)

- Ceiling Price (CP)

- Share Ratio (SR)

slide15

FPI(F) Final Contract Price: Two Examples (Along 60/40 Share Line)

Established at Contract Award:

Target Cost (TC) = $1000

Target Profit (TP) = $140

Ceiling Price (CP) = $1290

Share Ratio (SR) = 60/40

PTA (derived) = $1250

PTA = ((CP-TPr)/Gov’t Share) + TC

= ((1290-1140)/.6)+1000 = $1250

  • If actual cost is $1200, what is Final Contact Price (FCP)?
  • (1) 1000 - $1200 = (-$200)
  • (2) -$200 x. 4 = (-$80) Profit adjustment
  • (3) Adjusted profit = $140 -$80 = $60
  • $1200 (actual cost) + $60 (adjusted profit) = $1260
  • Since $1260 is below the Ceiling Price ($1290), FCP = $1260
  • If Actual Cost is $800, what is Final Contract Price (FCP)?
  • $1000 - $800 = $200 (positive)
  • $200 x .4 = $80
  • $140 + $80 = $220
  • $800 (actual cost) + $220 (adjusted profit) = $1020
  • Since $1020 is below the Ceiling Price
  • ($1290) , FCP = $1020
slide16

FPI(F) Final Contract Price: Additional Examples

(From PTA to CP and beyond)

Established at Contract Award:

Target Cost (TC) = $1000

Target Profit (TP) = $140

Ceiling Price (CP) = $1290

Share Ratio (SR) = 60/40

PTA (derived) = $1250

  • The Final Contract Price at every point on the line between PTA and CP and beyond will equal the CP!........ Why?
  • - Every additional dollar of cost reduces profit by a dollar (constant slope of -1)
  • The Final Contract Price at any point = Actual Cost + Profit (AC, Profit), thus, when
  • Actual Cost = 1250, then Profit = 40; FCP = 1290
  • Actual Cost = 1260, then Profit = 30; FCP = 1290
  • Actual Cost = 1270, then Profit = 20; FCP = 1290
  • Actual Cost = 1280, then Profit = 10; FCP = 1290
  • Actual Cost = 1290, then Profit = 0; FCP = 1290
  • Actual Cost = 1400, then Profit = -110, FCP = 1290
  • See display of results (“points”) on next chart

If actual cost is $1250 (the PTA), what is the final contact price (FCP)?

(1) $1000 - $1250 = ($250)

(2) $250 x. 4 = ($100)

(3) Adjusted profit = $140 -$100 = $40

(4) $1250 (actual cost) + $40 (adjusted profit) = $1290

Since $1290 is the Ceiling Price, FCP = $1290 = CP (not a coincidence!!).

slide17

FPI(F) Final Contract Price: Display of Examples

As noted previously, in this case, 1250 is traditionally called the PTA even though the PTA is actually a “point” in the plane, that is (1250,40)

Profit

(0,220)

FCP2 = 1020 (800,220)

TP = 140 (0,140)

TPr = 1140 (1000,140)

FCP1 = 1260 (1200,60)

(0,60)

(0,40)

FCP at PTA = 1290 (1250,40)

FCP = 1290 (1260,30)

FCP = 1290 (1270,20)

FCP = 1290 (1280,10)

Cost

(0,0)

TC = 1000 (1000,0)

(1250,0)

CP = 1290 (1290,0)

(800,0)

(1200,0)

FCP = 1290 (1400,-110) (loss)

types of contract financing
Types of Contract Financing
  • Commercial
    • Advance payments
    • Interim payments
  • Non-commercial
    • Advance payments
    • Loan guarantees
    • Progress payments
      • Based on Costs
    • Performance based payments
progress payments dfar 232 102
Progress Payments (DFAR 232.102)
  • A form of Government financing in recognition of the need for working capital, for long lead items, and work in-process expenditures
  • Based on Costs or
    • a percentage or stage of completion (for construction or ship building/conversion/alteration/repair)
  • The customary progress payment rates for DoD contracts,
  • including contracts that contain foreign military sales
  • (FMS) requirements, are:
    • 80 % for large business concerns
    • 90 % for small business concerns, and
    • 95 % for small disadvantaged business concerns.
performance based payments pbps
Performance Based Payments (PBPs)
  • The Government’s preferred method of contract financing for fixed price contracts.
  • Payment is based on the achievement of specific events that are defined and valued in advance by the parties to the contract.
  • PBPs focus on performance rather than on incurred costs.
pbp elements
PBP Elements
  • Three pieces to defining PBP terms.

1) The Payment Event or Criteria,

2) The Definition of Successful completion

3) The Value of the event.

  • All three pieces need to be considered together to ensure :
    • Adequate cash flow to the contractor,
    • Appropriate motivation for the contractor, and
    • that achieving the payment events will lead to the successful completion of the contract.
establishing pbp events
Establishing PBP Events
  • Each event or performance criterion that will trigger a financing payment must:
    • Be an integral and necessary part of contract performance and
    • Be identified in the contract, and
    • Include a description of what constitutes successful performance of the event or attainment of the performance criterion.  
payment events
Payment Events
  • The following are a sample of payment events:
    • Receipt of material
    • Receipt of major subcontracted items
    • Product leaving a machining / tooling phase
    • Completion of first article testing
    • Machining, forging, fabricating parts
  • The best method of selecting events….
    • Diagram the process flow of the product and select the key events that lead to completing the product.
minimizing risk
Minimizing Risk
  • Contract financing is a risky proposition for the Government since we are providing payments to a contractor prior to full delivery.
    • In both commercial and non-commercial financing we must actively mitigate the risk associated with contract financing.
    • When we finance commercial contracts we require that the contractor provide some form of security or collateral in the event they fail perform.
    • With non-commercial contracts the approach is a bit different, but the bottom line is the same:

PROTECT the TAXPAYER'S INTEREST!

research development what contract type now

Cost Reimbursement

Fixed Price

1975: DoDD 5000.1

Initial preference for CR

Dev K’s noted

1989 - 2007: Title 10/FAR

preference emphasized

for almost 20 yrs

~1983 to 1989

2007 to ? (FY 2007 Authorization Act)

Research & DevelopmentWhat Contract Type Now?
  • FY 07 Authorization Act & Interim 5000.02 (Enclosure 1. Tables 1 & 6)
  • MDA shall select contract type at M/S B for MDAP
    • May select fixed-price (including FPI) or cost type
    • Cost type requires written determination that:
      • Program risk due to complexity and technical challenges too great for fixed price type
      • Complexity and technical challenges not result of failure to meet certification requirements established in section 2366a of title 10, United States Code
thoughts on contracting strategy
Thoughts on Contracting Strategy
  • Selecting the appropriate contract type, incentive package, and financing plan are part of acquisition strategy planning
  • Contracting Officer must work with Program Manager to recommend appropriate contract type to MDA for MDAP
  • A fixed price development contract may be too risky, if so:
    • MDA documents basis for contract type
    • Explanation of the level of program risk
    • If level of risk is high, steps taken to reduce risk
    • Reasons for proceeding with M/S B approval despite high risk

Remember A-12 fiasco

additional thoughts on contracting strategy
Additional Thoughts on Contracting Strategy
  • Selecting contract type, incentive package, and financing plan are part of risk mitigation planning
  • Contracting strategy for program asa whole must be thought through “up front and early”
  • Work hand-in-hand with your contracting officer throughout the entire process