Status on the PS/SPS  MERIT (nTOF11) interface. I. Efthymiopoulos, A.Fabich CERN AB-ATB, Switzerland http://cern.ch/proj-hiptarget ABIC, February 2006. Introduction. Project webpage: http://cern.ch/MERIT See also EDMS “MERIT experiment” presentation at 32 nd ABIC by I.Efthymiopoulos

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Status on the PS/SPS  MERIT (nTOF11) interface' - favian


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
status on the ps sps merit ntof11 interface

Status on the PS/SPS  MERIT (nTOF11) interface

I. Efthymiopoulos, A.Fabich

CERN AB-ATB, Switzerland

http://cern.ch/proj-hiptarget

ABIC, February 2006

I.Efthymiopoulos, A.Fabich, CERN

introduction
Introduction
  • Project webpage: http://cern.ch/MERIT
  • See also
    • EDMS “MERIT experiment”
    • presentation at 32nd ABIC by I.Efthymiopoulos
  • Experiment presented to AB safety committee on 25th Jan. 06
  • ISIEC available
  • Interface MERIT to PS/SPS
    • Beam line
    • N2 exhaust
    • Power supply, power line

I.Efthymiopoulos, A.Fabich, CERN

slide3

Ventilation

bat 806

  • N2 exhaust
  • Beam line
  • Power supply/line to solenoid

I.Efthymiopoulos, A.Fabich, CERN

MERIT

beam line
Beam line
  • No modifications to TT2 line
  • FTN beam line
    • Displacement/installation of quadrupoles downstream of shielding
    • Causes possible power cable installation to bat. 263
      • Not urgent, can be down in shutdown 06/07
  • Cut/stop TT2/FTN vacuum at shielding
    • install beam window just downstream of shielding.

I.Efthymiopoulos, A.Fabich, CERN

the merit cycle

and repeat

B-field

Solenoid temperature

Proton intensity

The MERIT cycle

The solenoid is operating at 80 K. A power ramping takes place about every 30 minutes.

  • Repetition rate is limited by the cooling process of the solenoid.
    • A few seconds B-field ramping
    • 20++ minutes for cooling procedure

I.Efthymiopoulos, A.Fabich, CERN

n2 exhaust
N2 exhaust
  • Principle of operation agreed with SC/RP and SC/GS
    • Release of 200 liters LN2/ 30 minutes at ambient temperature
      • 1400 m3 N2 gas/hour to a total ventilation of 27000 m3/hour
      • EDMS 700153
    • Including activated LN2 of up to 1 liter/beam cycle
      • Delayed release by >2 minutes after beam to reduce short-lived isotopes
      • EDMS 700178 and 697857
  • Currently installation of exhaust line in TT10 and TT2
    • Layout agreed on with A. Spinks, N. Gilbert, G. Robin, C. Lacroix
    • Completed before TT2 closure at end of February
  • Operation of LN2/N2 system starts in late autumn 2006
  • Impact on TT10 operation
    • Portable ODH monitoring required
    • Definition and signalization of areas concerned to be finalized
    • MERIT alarm from TT10 ventilation and radiation monitors to be installed

I.Efthymiopoulos, A.Fabich, CERN

power supply power line
Power supply, power line
  • Transformer/Converter installed at bat. 193
    • Refurbishment during spring 2006
  • AC cabling (18kV to transformer to converter)
    • Building 193 only
    • Will be done in autumn 2006; AD shutdown
  • DC
    • Currently ongoing
    • Completed before 24th February (TT2 closure)
  • Safety coordinator

I.Efthymiopoulos, A.Fabich, CERN