slide1 l.
Download
Skip this Video
Download Presentation
Building Program Update March 19, 2008 Rio Hondo Community College District Board of Trustees Meeting

Loading in 2 Seconds...

play fullscreen
1 / 13

Building Program Update March 19, 2008 Rio Hondo Community College District Board of Trustees Meeting - PowerPoint PPT Presentation


  • 83 Views
  • Uploaded on

Building Program Update March 19, 2008 Rio Hondo Community College District Board of Trustees Meeting. Agenda. Construction Update DSA Closeout Design Update. Construction Update Library/LRC – Under Construction Infrastructure – Under Construction Central Plant – Under Construction

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Building Program Update March 19, 2008 Rio Hondo Community College District Board of Trustees Meeting' - ewan


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
Building Program UpdateMarch 19, 2008Rio Hondo Community College DistrictBoard of Trustees Meeting
agenda
Agenda
  • Construction Update
  • DSA Closeout
  • Design Update
slide3
Construction Update
  • Library/LRC – Under Construction
  • Infrastructure – Under Construction
  • Central Plant – Under Construction
  • Lot A Pedestrian Bridge – Under Construction
infrastructure
Infrastructure
  • Construction underway.
  • Upcoming road closures.
central plant
Central Plant
  • Construction underway.
lot a pedestrian bridge
Lot A Pedestrian Bridge

Completion Anticipated

Early Summer 2008

Steel Erection Anticipated

During Spring Break

dsa closeout
DSA Closeout

Building Panel Connection Upgrades:

  • DSA closeout letter received, project has been closed with Certification.
  • Project completed on time and within budget.
  • Evening and off-hours work, minimal impact to the Campus.
slide9
Design Update
  • Rio Hondo Parkway – Stamped by DSA, Submitted to LA County.
  • Applied Technology Renovation – Pre-Qualification Process.
  • Terraced Walks – Stamped by DSA.
  • Physical Education Complex – Submitted to DSA.
  • Administration of Justice – Submitted to DSA.
  • Student Services Building – Submitted to DSA.
  • South Whittier (STARS) – Submitted to DSA.
  • Santa Fe Springs Ph III – Submitted to DSA and City of Santa Fe Springs.
  • El Monte Center – Under Design.
  • Campus Quad Landscaping – Under Design.
el monte center12

LOT SIZE: 47,057 SF (1.08 AC)

RIO HONDO EL MONTE CAMPUS:

260 STUDENT CAPACITY

5 CLASSROOMS + 1 LAB

TOTAL NET BUILDING AREA: 12,442 SF

PARKING REQUIRED:

RIO HONDO - 260 SEATS

@ 1 STALL PER 3 SEATS: 87

RIO HONDO FACULTY: 5

COMMUNITY ROOM - 976 SF

@ 1 STALL PER 250 SF: 4

TOTAL REQUIRED: 96 STALLS

PARKING PROVIDED:

STANDARD STALLS: 85

HANDICAP STALLS

@ 1 PER 25: 4

TOTAL PROVIDED ON-SITE: 89 STALLS

TOTAL PROVIDED ON-STREET: 8 STALLS

TOTAL PROVIDED: 97 STALLS

Rio Hondo

GARVEY AVENUE

Alley

Entry

Court

TYLER AVENUE

El Monte Center
questions
Questions

March 19, 2008

BUILDING PROGRAM UPDATE

ad