Initial Action Plan Draft. Magic Athletics Club Not-for-Profit Organization www.magicac.org. Statement of context SoC. 1. The site I am building is a Soccer Club site. (verified from the client’s first email communication.) The club is called Magic Athletics club.

1 / 14

Download Presentation

Initial Action Plan Draft

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Initial Action Plan Draft • Magic Athletics Club Not-for-Profit Organization • www.magicac.org

  2. Statement of context SoC 1. The site I am building is a Soccer Club site. (verified from the client’s first email communication.) The club is called Magic Athletics club. 2. I am as the website designer for the site has, however, never joined in a soccer club before. I have played soccer long time ago. But I say I am pretty new to the sport and also new to the GTA Soccer Club Associations as a whole. 3. Each soccer club should cater to different age groups. As I need to know the age group my client’s club is focusing on so I can cater my design and the level of readability of my site. 4. A hint from the client that he wanted “to attract young talents” as one of his focus of the having a website. It might help me to keep in mind when designing by keeping it a as a fun website in a big picture.

  3. Statement of Work (SoW) • Produce code( webmaster: layout) • QA tester • Photographer • Photo editor • Logo Designer • Copy editor (content writer) • Project Manager

  4. Statement of Scope (SoS)

  5. Statement of Deliverables • Home • News • About Us • Schedules • Registration • Gift Economy • Contact Us

  6. Communication Plan Client’s Name: Robert Ferguson Email: rferguson24@hotmail.com Phone Number: 416-671-7019 I am planning to set up a weekly Monday touch base plan via email. Phone calls for scheduling meetings. Question for him:Why does he use hotmail if he already has domain?

  7. RBA

  8. RBA

  9. RBA

  10. RBA

  11. WBS-Spiral Model • 42 days durations (6 weeks) • PLAN is to get the bulk of the work before July 16. • Phase I “Early” 21 days or 3 weeks (June 13- July 2) [44.5 hours] 20%Phase II “Middle” 14 days or 2 weeks (July 2 – July 16) 60%Phase III “Final” 14 days or 2 weeks (July 16 – July 30) 95%

  12. WBS with the break down of Time of Task Phase I • RBA [5 hours] • Layout • 1 pass [3] • 2 passes [2] • 3 passes [1] • Menu • 1 pass [4] • 2 pass [3] • 3 pass [2] • 4 pass [1] • Font [.5] • User testing [6] • Color • 1 pass [4] • 2 pass [4] • 3 pass [3] • 4 pass [3] • 5 pass [2] • 6 pass [1] • Concept [2] • Assess legacy photos and plan how to proceed [1] • Produce Shallow prototype – mockup in CCS / html [4] **

  13. Phase II • RBA [2 hours] • Layout • 1 pass [2] • Menu • 1 pass [2] • 2 pass [1] • Font [.5] • Color • 1 pass [3] • 2 pass [3] • 3 pass [2] • 4 pass [1] • Concept [.5] • Photoshop images [5] • Produce fuller (horizontal or vertical) prototype – mockup in CCS / html [6] **

  14. Phase III • RBA [2] • Layout [5] • Menu [4] • Font[1] • Color[1] • Concept[3] • Produce FINAL finished site [7] • QA Testing [3]