The construction of the new water treatment facility has advanced significantly as of December 1, 2007. Following the groundbreaking ceremony held on June 29, 2006, the project has made substantial progress, with the foundation and floors completed by December 18, 2006. In February, the arrival of steel components marked a key milestone. By early March, essential equipment, including Reverse Osmosis units and Pressure Filters, commenced arrival, signaling an important phase in the development of this vital infrastructure.
E N D
1. WATER TREATMENT FACILITY CONSTRUCTION UPDATE
12/1/07
2. GROUND BREAKING CEREMONYJUNE 29, 2006
3. Back on December 18, 2006 the foundation and the floors were complete.
4. In February the steel started to arrive.
5. Early March saw the arrival of the Reverse Osmosis units and the Pressure Filters.