THE VIEWS AT CLARENDON

THE VIEWS AT CLARENDON. Civic Association Information Meeting. Team Introduction. Doris Topel-Gantos – Bozzuto Development Company Vicki Vaughn – Chesapeake Community Advisors Mike Green – Bozzuto Construction Company Mark Weisner – Bozzuto Construction Company

Download Presentation

THE VIEWS AT CLARENDON

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THE VIEWS AT CLARENDON Civic Association Information Meeting

  2. Team Introduction • Doris Topel-Gantos – Bozzuto Development Company • Vicki Vaughn – Chesapeake Community Advisors • Mike Green – Bozzuto Construction Company • Mark Weisner – Bozzuto Construction Company • Dale Leidich – MTFA Architecture

  3. Community Liaison • Mark Weisner – Senior Project Manager ○ mweisner@theviewsatclarendon.com ○ A phone number will be provided at a later date.

  4. Construction Hours • Weekdays - 7:00 am – 6:30 pm • Weekends & Holidays - 10:00 am – 6:30 pm • Holidays are defined as Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, New Year’s Day, Columbus Day, Veteran’s Day, Thanksgiving, and Christmas.

  5. Construction Hauling Route • Construction traffic will be routed around the perimeter of the site with access from Wilson/Clarendon.

  6. Parking Plan

  7. Parking Plan Project Site: 1210 N. Highland Street

  8. Parking Plan Offsite Parking Locations

  9. Parking Plan

  10. Parking Plan Metro Locations

  11. Projected Schedule • ●Start – November 2009 • ●Abatement - Month 0 thru Month 2 • ●Demolition – Month 3 • ●Excavation – Month 4 thru Month 7 • ●Vertical Construction– Month 8 thru Month 24 • ●Site Construction – Month 0 thru Month 4 & Month 20 thru Month 24 • ●Lease-up starts – Fall 2011

  12. Future Deliverables • ●MOT Plan – Upon Arlington County approval • ●Temporary Pedestrian & Vehicular Circulation - Upon Arlington County approval • ●Final Site Plan & Landscape Plan – Upon Arlington County Approval

  13. South Elevation

  14. East Elevation