Hardness of Shops and Optimality of List Scheduling

Hardness of Shops and Optimality of List Scheduling. Ola Svensson KTH Royal Institute of Technology Stockholm, Sweden. Gap Instance with r =3 and F=3. Jobs of different frequency “cannot” overlap. Key-Lemma: Jobs of different frequencies overlap at most a fraction 1/r of their length.

duncan
Download Presentation

Hardness of Shops and Optimality of List Scheduling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hardness of Shops and Optimality of List Scheduling Ola Svensson KTH Royal Institute of Technology Stockholm, Sweden

  2. Gap Instance with r=3 and F=3

  3. Jobs of different frequency “cannot” overlap Key-Lemma: Jobs of different frequencies overlap at most a fraction 1/r of their length.

  4. 0 Reduction 1 2 • Jobs corresponding to an IS can be scheduled in parallel since no short-jobs interfer with the long-jobs Jobs can be scheduled in parallel iffthey correspond to an IS • Adjacent jobs cannot overlap by Key-Lemma

  5. Completeness: If Graph is K-colorable then there is a schedule of makespan at most K*lb Soundness: If Graph has no IS of size n/Klog(K) then any schedule has makespan at least Klog(K) *lb Some point

  6. Bounding #frequencies • Take “enough” and assign random frequencies to jobs • For a fixed K the graphs have bounded degree (Color in polytime using degree+1 colors, each color only needs one frequency)

  7. Final Result SAT Graph Coloring/IS Job Shops • It is NP-hard to approximate job shops within any constant factor makespan K lb K colors no IS of size n/KlogK makespanklogK lb • Assuming NP-complete problems have no randomized quasi-polynomial then job shops have no better than log(lb) approximation.

  8. ~ ~ ~ ~ ~ ~ ~

  9. Final Comments • PTAS iff #machines and #operations per job bounded by a constant Jansen, Solis-Oba & Sviridenko’99 + Mastrolilli, S’08 • Preemptive case wide open • No non-constant gap instances • Best hardness 5/4 and no constant approx algos.

  10. Expander Not Expander Not scheduled • 0.99n machines • 0.99n machines

  11. Not Expander Expander d+1 2d • 0.99n machines • 0.99n machines

  12. Building block (an instance of 1|prec|ΣwjCj) Instance of P|prec| Cmax processing time = 0 processing time = 1

  13. Yes Case No Case d+1 2d • 0.99n machines • 0.99n machines

  14. Do not have • Two extreme cases: • almost all predecessors have been completed • almost none of them have been completed

  15. Final Result SAT Node Expansion P|prec|Cmax • Assuming 1|prec|ΣwjCj is hard to approximate within a factor less than 2 • Then P|prec|Cmax is hard to approximate within a factor less than 2 makespan d+1 makespan 2d

  16. Is 1|prec|ΣwjCj difficult? (1/2) • Special Case of Vertex Cover • Removing Fixed Cost then equivalent to Vertex Cover • No PTAS unless NP-complete problems can be solved in randomized polynomial time Correa & Schulz’04 , Ambuhl & Mastrolilli’06

  17. Is 1|prec|ΣwjCj difficult? (2/2) • Assuming a variant of the Unique Games Conjecture • It is NP-hard to approximate better than 2 Bansal & Khot’09 SAT Unique Games 1|prec|ΣwjCj P|prec|Cmax makespan d+1 makespan 2d Vertex Cover, Max Cut, Feedback arc set, rich family of CSPs…

  18. Summary • Non-constant hardness for job shops that are essentially tight for acyclic job shops and general flow shops • Grahams list scheduling algorithm is optimal assuming a variant of the unique games conjecture • Master plan has been formalized for some classes of problems • Integrality gap of an SDP for CSPsimplies UG-hardness • Integrality gap of an LP for packing and covering problems implies UG-hardness Raghavendra’08 Kumar, Manokaran, Tulsiani, Vishnoi’11

  19. Two open problems • Scheduling precedence-constrained jobs on related machines Q|prec|Cmax • log(m) approximation • No better hardness than for parallel machines • Scheduling on unrelated machines R||Cmax • 2 approximation • NP-hard to do better than 1.5 Chudak & Shmoys’97 Lenstra, Shmoys & Tardos’90