2. Presenters and Authors
3. Summary
4. Application of Dynamic Simulation in MLNG Tiga Plant Project Acceptance of Tested Performance of the Refrigerant Compressors
To verify that the tested performance curves of the refrigerant compressors, together with other equipment meet the requirements
5. Monesting Gas Resources
6. Facts on the PETRONAS LNG COMPLEX – Shareholders (2003)
7. PETRONAS LNG COMPLEX – Production Capacity Company Train No. Current Production Capacity (Ton/Yr/Train) (Ton/Yr)
MLNG (1983)* 1,2,3 2.8 Million 8.4 Million
MLNG Dua (1995)* 4,5,6 2.6 Million 7.8 Million
MLNG Tiga (2003)* 7,8 3.4 Million 6.8 Million
Total for PETRONAS LNG Complex: 23.0 Million
* Year Operated.
8. Features: MLNG, MLNG Dua & MLNG Tiga
9. Process Train Flow Scheme
10. Evaluation of Tested Performance Curve
11. Configuration of Refrigerant Compressors in Train 7&8
13. Example of Operation (LCI Trip)
14. Example of Operation(C3 Generator Trip)
15. Plant Performance Verification
16. Conclusion Effective for analysis of risks introduced by new designs and innovation
De-bottlenecked during the plant design
Increase the effectiveness and productivity of the installed equipment
Analyze margins of the equipment and minimize the combined effect
19. Independent Operation
20. Island Operation
21. Operation with LCI
22. Virtual Plant Simulators – MUSIC with HYSYS engine