1 / 21

LHC Beam Dumping System (LBDS) Overview

LHC Beam Dumping System (LBDS) Overview. B.Goddard AB-BT With thanks to many including E.Carlier, L.Ducimeti è re, R.Filippini, M.Gyr, V.Mertens, W.Weterings, J.Uythoven, …. Overview - components. Main subsystems ( covered in next talks ) are:

Download Presentation

LHC Beam Dumping System (LBDS) Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Beam Dumping System (LBDS)Overview B.Goddard AB-BT With thanks to many including E.Carlier, L.Ducimetière, R.Filippini, M.Gyr, V.Mertens, W.Weterings, J.Uythoven, …

  2. Overview - components • Main subsystems (covered in next talks) are: • 30 x MKD extraction kickers → deflect beam (h) into septum gap • 30 xMSD extraction septa → deflect beam (v) over LHC machine • 8 (20) x MKBdilution kickers → sweep beam in ~circular form • 2 x TDEdump block → safely absorb full beam energy • 2 x TCDS and 2 x TCDQ diluters → protect LHC from asynchronous dump • Electronics and controls→ make the system work • (installed numbers, without spares) • Other system elements include Q4, vacuum system, beam instrumentation, • beam energy meter, post-mortem

  3. 15 UJs modified 15

  4. Civil engineering - finished TD68 UD68 Infrastructure: Steel structures in places, Cranes to be installed in 2004 UJ68

  5. Overview – planning (from EVM + LHC general) Draft under revision

  6. Comments on planning • Hardware commissioning to be done with the LHC machine: Q3 2006 & Q4 2006. • Kicker planning very tight (especially MKB). • Updating of detailed planning in progress. • Additional resources allocated to speed up design. • Resources reallocated to kicker project management and follow-up. • Should just be able to meet Q4 2006 deadline. • MSD installation to be advanced – should not pose a problem.

  7. Overview – budget and EVM

  8. System design parameters (50% until full installation) (33% until full installation) Presently still need to demonstrate SIL3 reliability for full beam-dumping system (analysis in progress).

  9. Difficulties meeting design parameters…? • Protection of MSD with TCDS • Wider TCDS required than assumed in initial MSD design. • Less aperture for circulating beam. • New MSD chamber (4mm larger diameter) to achieve design parameters. • New Beam Position interlock (2 x 2 BPMs) at ±4mm in point 6 to ensure orbit stays in tolerance. • Manage to provide n1 > 6.5 at limiting element TCDS. TCDS MSDC5

  10. Remaining system-level technical issues • Overall system reliability • Quantitative analysis now under way. • Functional dependencies on other machine protection. subsystems to be considered. • Failure frequencies to be estimated. • ‘Costs’ of serious failures to be evaluated (‘what if…’ scenarios). • TCDQ and LHC machine protection • Functional interdependency with collimation system. • How to achieve required orbit control at TCDQ - under study. • Controls system requirements • Detailed requirements to be specified (logging, post-mortem, data retrieval, applications, fixed-displays, …). • Access system interface requirements • Detailed requirements to be specified for LBDS zone for conditions of access, interfaces and interlock actions.

  11. CtC and schedule issues • Known CtC changes • BI functional specification includes equipment not foreseen in so-called ‘BI baseline’. Being dealt with now. ~260 kCHF (new interlock, BLMs, special BPM). • Known schedule issues / concerns • MKD manufacturing ‘ungrouped’ for cost reasons plus insolvency of single offer. • Kicker production affected by several quality and technical difficulties in firms – now seem OK but close and manpower-intensive follow-up needed. • New MKB/MKD kicker planning being detailed. • TCDQ also on the critical path – presently just OK.

  12. System testing – critical system reliability run • Schedule allows 3 months after HW commissioning for dry-running LBDS – the reliability run. • Opportunity to find and correct teething problems. • Full test of the subsystems integrated into the LBDS. • Measure some of the estimated reliability figures. • Should NOT be seen as ‘reserve’ in case of delays.

  13. Integration issues • UJ62/68 layouts were modified by dramatically shortening UJ caverns to save money (lots of money…) • Local modifications to tunnel wall required for extracted beam passage - just finished.

  14. UJ62/68 – cut out tunnel liner

  15. Integration : extracted beam vacuum line 2D and preliminary 3D studies made – interferences between extracted beam line and Q4-Q9 cryostats and jumpers ‘solved’. Final 3D integration study now ongoing with ‘as-built’ tunnel – tight deadline. Also interference between MSD connection box and the QRL – new connection boxes being designed.

  16. Installation planning (derived from EVM) Draft under revision

  17. Installation schedule issues • Detailed installation planning remains to be made : • Cohabitation issues. • Availability of services and transport. • Detailed sequencing. • Resource requirements and possible conflicts. • Constraints from main LHC planning and equipment level planning.

  18. Hardware baseline • Framework and some information exists: • System level information ‘sketchy’ • Subsystem parameters ‘sketchy’ • Functional specification ‘sketchy’ • Otherwise fairly complete… ! • Update needed post LHC design report

  19. Specification and documentation in Hardware Baseline / EDMS

  20. Detailed data storage and documentation • EDMS used for technical documents. • New LHC DR contains full system description. • Hardware baseline not fully defined (although information generally exists). • Some rationalisation effort clearly needed – but time, resources, priority? • Requirements for INB? E.g. full documentation of reliability analysis and corresponding technical solutions.

  21. Conclusions • Technical solutions well developed. • TCDQ main exception – conceptual design still to finalise. • Overall reliability analysis to be made. • High-level controls system and access system requirements to specify. • Costs under control. • CtC basically being respected - no major escalation expected. • Schedule causing some concern. • MKD and (especially) MKB planning tight. • Situation known and resource adjustments already made. • Detailed installation planning to be made. • Documentation needs rationalising. • Mainly HW baseline and parameters. • Will require resources to ‘back-date’.

More Related