Scheduled Curtailments Cancellations. Should be received at least one business day prior to start date of curtailment Resource Availability should not reflect the curtailment Day Ahead offers can be entered. Scheduled Curtailments Modifications. Modification 1:

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Scheduled Curtailments Cancellations' - deion


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
scheduled curtailments cancellations
Scheduled CurtailmentsCancellations
  • Should be received at least one business day prior to start date of curtailment
  • Resource Availability should not reflect the curtailment
  • Day Ahead offers can be entered
scheduled curtailments modifications
Scheduled CurtailmentsModifications
  • Modification 1:
    • Delayed start date, same end date
    • Notice must be received at least 7 calendar days prior to changed start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)

Start Date

End Date

Original Curtailment

Modification 1: Later Start Date

StartDate

scheduled curtailments modifications1
Scheduled CurtailmentsModifications
  • Modification 2:
    • Same start date, earlier end date
    • Notice must be received at least 7 calendar days prior to changed end date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
    • Same requirements if curtailment extended past original end date (notice 7 / 15 calendar days prior to original end date)

Start Date

End Date

Original Curtailment

Modification 2: Earlier End Date

EndDate

scheduled curtailments curtailment schedule change
Scheduled CurtailmentsCurtailment Schedule Change
  • Change in Schedule:
    • Change to both start and end dates
    • Original curtailment will be cancelled, new curtailment entered
    • Notice must be received at least 7 calendar days prior to curtailment start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)

Start Date

End Date

Original Curtailment

Change: Different Start and End Dates

Start Date

EndDate