1 / 15

Dipole design review: outlines of talks

Dipole design review: outlines of talks. Gijs de Rijk, Francois Kircher and Jean-Michel Rifflet. Dipole design review. D ate: 20-21 January 2011 P lace: CEA Reviewers: Giorgio Ambrosio (FNAL) Lucio Rossi (CERN) Shlomo Caspi (LBNL) Akira Yamamoto & Tatsu Nakamoto (KEK)

darren
Download Presentation

Dipole design review: outlines of talks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean-Michel Rifflet

  2. Dipole design review • Date: 20-21 January 2011 • Place: CEA • Reviewers: • Giorgio Ambrosio (FNAL) • Lucio Rossi (CERN) • ShlomoCaspi (LBNL) • Akira Yamamoto & TatsuNakamoto (KEK) • Yuki Iwasa (MIT) • Pasquale Fabbricatore (INFN Genova)

  3. Draft agenda (day 1) • Introduction 9h00 I-1) EuCARD-HFM and its context.  (GdR)   15’+5’ • II) Technical part 9h20 II-1) Overview of the dipole  (J-M Rifflet)   15’+10’ 9h45 II-2) Conductor choice, properties and procurement strategy (L. Oberli) 20’+10’ 10h15 Coffee break 15’ 10h30 II-3) Conceptual design (A. Milanese)  30’+10’ 11h10 II-4) Engineering design (P. Manil)  30’+10’ 11h50 II-5) Quench protection (P. Fazilleau)  15’+10’ 12h15 Lunch break 1h45’ 14h00 II-6) SMC as preparatory project (J-C. Perez) 20’+10' 14h30 II-7) Fabrication process study (M. Durante)  30’+10’ 15h10 II-8) Winding and tooling tests and insulation choice (F. Rondeaux)  20’+10’ Coffee break 15’ 15h55 II-9) Cooling, heat transfer and cool-down issues (S. Pietrowicz )  20’+10’ 16h25 II-10) Insert interfacing (M. Devaux)  10' + 10’ • III) Scheduling and project management 16h55 III-1) Magnet design and construction schedule (GdR)  20' + 10'

  4. I-1) EuCARD-HFM and its context.  (GdR)   15’+5’ • EuCARD 11 WPs • NED heritage • HFM: 6 tasks • Task 3 dipole, the need for a Fresca (existant 10 T + HF) cable test facility, prospecting for future accelerator magnets and HFM technologies • Task 3 EuCard (only) specification for the dipole • Task 3, budget situation and explication of budget links • Work division between the partners

  5. II-1) Overview of the dipole  (J-M Rifflet)   15’+5’ • The specification (boundaries) • Size considerations: coil, yoke (scaling laws) • Conductor choice • NED heritage • 1 mm strand in 40 strand cable choice • Maximize current to minimize L (reference to Luc, Philippe) • History of the design • Basic block coil (Picture 2D baseline) • Shell bladder and key, basic reasons for this

  6. II-2) Conductor choice, properties and procurement strategy (L. Oberli) 20’+10’ • 1 mm strand (detailed explanation) • Compromise between 1.25 mm and 0.8 mm • Cable size: 40 strands, reasons • Available providers, history of strand development • Procurement strategy • Cable design parameters and cabling tests • Prototype strands: first results • Prototype cable: first results ( sample length ) • Comparison with models Jc used for the design (plot)

  7. II-3) Conceptual design (A. Milanese)  30’+10’ • Magnetic design (parameters, plots) • 2D (some optimisation reasons, mid plane etc) • 3D (max field etc) • Mechanical design • -          Présentationgénérale de la structure mécanique • -          Design mécanique global 2D  • o   dimensioning of components • o   quelquescourbes de suivi de certainsindicateurs, • Option without tube (20 Febr.) • Life cycle construction and powering • Modèle de calculmécanique 3D • Global structure

  8. II-4) Engineering design (P. Manil)  30’+10’ • Géométrie de la bobine : • Bending test • Saut de couche • Etude géométrique • Longueur de câble • Présentation de la structure • Points critiques : support des têtes, bladders… • Detailed engineering • Usinabilité / choix des matériaux : tube, tolérances, surfaces complexes…

  9. II-5) Quench protection (P. Fazilleau)  15’+10’ • Only a feasibility study not yet design decisions • Quench development, current decay, T max, T av, V max • Circuit parameters : dump resistor • Quench heaters : needed ?, test usage • Quench behaviour at 1 T, 5 T, 10 T and 13 T • Gradients T during quench (for later mechanical modeling) • Parameter space

  10. II-6) SMC as preparatory project (J-C. Perez) 20’+10' • Aim of the SMC series • SMC description • SMC program (table with magnets / coils, dates, 7 coils ) • SMC1 test results • Lessons learned up to now • SMC3 progress • Future work (SMC4 40st) and aims

  11. II-7) Fabrication processstudy (M. Durante) 30' + 10’ Question: which tooling is needed and what are the critical issues ? • Insulating • Winding • Mould mounting • Reaction • Preparation for impregnation • Island manipulations • Splicing • Instrumentation sheets • Ground insulation • Moulding • Mounting the structure • Coil pack mounting • Bladder and key operations

  12. II-8) Winding and tooling tests and insulation choice (F. Rondeaux)  20' + 10’ • First winding feasibility test April 2010 • Winding tests foreseen • Reaction mould design and tests • Insulation schemes available • Insulation scheme choice process • Moulding material and tests

  13. II-9) Cooling, heat transfer and cool-down issues (S. Pietrowicz )  20' + 10’ • Temperature and heat model of the magnet • Steady state heat deposition at 4.2 K • Steady state heat deposition at 1.9 K • Cooldownscenario • Stresses in the magnet during cooldown

  14. II-10) Insert interfacing (M. Devaux)  10' + 5’ • Insert layout • Insert mounting • Field with insert • Quench of insert • Quench of dipole • Risk scenarios

  15. III-1) Magnet design and construction schedule (GdR)  20' + 10’ • Task breakdown • Design and construction flowchart with decision points • Design and construction schedule (incl SMC4) • Potential bottlenecks

More Related