500 likes | 589 Views
Explore the structural and architectural design considerations of a new classroom project at Central University's Engineering School in the bustling Los Angeles Metropolitan Area, addressing seismic and construction challenges. The project team reimagines the space with innovative ideas like "Sun Rise" for improved functionality and modern aesthetics. Structural alternatives, construction concerns, load paths, cost breakdowns, and team interactions are highlighted.
E N D
CENTRAL UNIVERISTY Engineering School – New Classroom Project ARCHITECTURE Joy Liu, Cal-Berkeley ENGINEERING Norm Faris, Stanford CONSTRUCTION Tim Kolaya, Georgia Tech OWNER Alex Barron, Stanford
Project Information • Central University Engineering School • Location: • Los Angeles Metropolitan Area • Busy urban location / heavy traffic • Seismic Concerns – San Andreas Fault (8 km)
SiteLocation • Site in San Francisco • Selected for accessibility by team 3rd Street & Folsom
Design Consideration Remote Team Work High Tech Neighborhood Seismic Urban Context Busy Traffic setting Warm Climate
Structural – Loading Conditions • Gravity • Live Loads(UBC) • Classroom / Offices = 50psf • Stairs/Corridors = 100psf • Auditorium seating = 50psf • Roof = 20psf • Dead Loads • Lightweight Composite Deck = 70psf • Concrete Slabs = 12psf/1” thickness • Flooring, ceiling and fixtures = 10psf • HVAC = 5psf • Partitions = 20psf • Exterior Cladding = 20psf (Vertical Surface) • Lateral • Seismic Conditions • Seismic Zone 4 • Soil Profile = SD • Near Source Effects • Occupancy Category = 1.0 • V = 0.205*W (Moment Frames) • V = 0.169*W (EBF) • Wind Loading • Design Wind Speed (70mph) = 20.2 psf
Construction Concerns • High Ground Water Level • Excavation/Shoring • Dewatering ~16 -20 Ft. • Los Angeles Traffic
Redesign • Ideas: “Sun Rise” • Explore the space from underground to top • Keep Circulation smooth • Think of the functionality of the space
Sun Rise • Old plan Cafe Gym New Plan Cafe Cafe Gym Basement 1st Floor 2nd Floor
Sun Rise • 3-D Model
Sun Rise – Structural Alternative 1 • Steel Moment Frames • Beams: W24 x 84 • Columns : W14x120 • Gravity System • Composite Slab (t = 6.5”) - W14 x 22 Beams • Columns: W12 x 50 In Context of Architectural Layout – 2nd Floor
Sun Rise – Structural Alternative 1 W12 Beams w/ 12” Channels @ Perimeter W18 Column Roof Opening Column to Mat Connection w/ Base Plate and Stiffener Beam to Concrete Wall w/ Embedded Plate and Studs LOBBY: RADIAL STEEL GRAVITY SYSTEM
Sun Rise – Structural Alternative 2 • Concrete Moment Frames • Beams: 18” x 24” • Columns : 18” x 18” • Gravity System • Post Tensioned (PT) Slab • Columns: 12” x 12” • Lobby – PT Column Beam System • Foundation System • 6’x6’ Spread Footings w/ 18” Grade Beams • 18” Post-Tensioned Mat Foundation below basement • 15” Retaining Wall
Sun Rise – Load Path (Alternative 1 & 2) • Lateral Loads • Distributed based upon rigidities • Rigid Floor Diaphragm • Gravity Loads • Post – Tension System: Slab – Column - Foundation • Composite Concrete & Steel System Deck – Beam – Girder – Column - Foundation
Sun Rise – Construction Schedule and Cost Breakdown Steel MRF w/ Composite Deck Concrete MRF w/ Post-Tensioned Deck Schedule Alt. 1 – 9 months Alt. 2 – 8 months Alt. 1 Alt. 2
Structural Design 1st Iteration Collaboration / Final Layout Attempt New Layout Adapt Old Design Updates Issues Concerns Revisions Initial Estimate Cost Concerns Detailed Estimate Sun Rise - Team Interaction
Architecture Vision of 2015 • Gaining awareness in Eco-design and sustainable architecture • Better and cheaper technology in day-lighting devices
New Design 1 - Square Plan • Design Concepts: • “Flying Eagle” In Southern Latitude: • Respond to orientation • Use Natural energy instead of artificial energy • Progression • Repetition of open and compressed space N
Flying Eagle • Model
Flying Eagle – Structural Alternative 1 • Steel Moment Frames • Beams: W24 x 84 • Columns : W18 x 211 • Gravity System • Composite Slab (t = 6.5”) w/ W12 x 26 Beams • Long Span Trusses @ 3rd Floor over Auditorium • Columns: W12 x 58 • Bending due to Lateral Loads induced in the Frame • Additional Bending in columns due to Cantilever Support System • Additional Costs to Reinforce Columns in their Weak Axis
Flying Eagle – Structural Alternative 2 • Lateral System • 2nd & 3rd Floors-Shearwall • t = 8” • Roof - Concrete MRF • Beams: 24” x 16” • Columns: 16” x 16” • Gravity System • 9” Flat Plate w/ Drop Beams 1st Floor Structural System in Context of Architectural Layout
Flying Eagle – Structural Alternative 3 • Concrete Moment Frame • Beams: 24” x 18” • Columns : 20” x 20” • Gravity System • 9” Flat Plate w/ Drop Beams between Columns • 24” Waffle Slab for 3rd floor above auditorium • Columns: 16” x 16” • Foundation System • 6’x6’ Spread Footings @ Columns • 15” Mat Foundation @ Basement Level • 4’ Continuous Footing @ Perimeter Walls • 12” Retaining Walls
Flying Eagle – Cantilever at 3rd Floor Composite Gravity System – Continuous From Main Structure TS Brace From Exterior Cantilever Columns to Frame W14 Column Struts – Welded at Frame & Connected to Column w/ Welded Base Plate
M.E.P System • Based upon 30,000 ft2 Floor Area • Cooling Capacity = 90 tons • Cooling Air Volume = 35000cfm • Total Space for Boiler Room and Chilled Water Plant = 600ft2 • Area of Main Supply or Return Ducts = 20ft2 • Area of Branch Supply or Return Ducts = 35ft2 • Area of Fresh Air Louvers = 80ft2 • Area of Exhaust Air Louvers = 70ft2 • All utilities localized at basement • Main Distribution Vertical • More Narrower Ducts • Single Excavation for Services • Centralized for efficiency
Flying Eagle – Construction Schedule and Cost Breakdown Shear Wall Concrete MRF Steel MRF Schedule Alt. 1 – 7½ months Alt. 2 – 8½ months Alt. 3 – 8 months Alt. 1 Alt. 2 Alt. 3
Flying Eagle - Team Interaction Structural Solution Propose Design Back to the Drawing Board – Revisions Finalize Design Issues Concerns Estimates/ Schedules Constraints / Constructability Structural Limitations Presented
New Design 2 - Diamond Plan • Idea: • “Pouring Stream” • The contrast of solid and void • Changes in experience • Bring the flow of vegetation to inside of the building • Recreation of Nature
Pouring Stream Old Plan New Plan
Pouring Stream Section
Pouring Stream • Material Choice • Exterior • Glass and lightweight metal with adjustable day-lighting metal panels. • Changes the personality of the building from day to night • Constant movement • Interior • Atria space will use wood(cladding) • Use concrete at other place. At Day At Night
Pouring Stream • Model
Pouring Stream – Structural Alternative 1 Steel Eccentric Brace Frame (EBF) w/ Composite Gravity System W21 x 62 Link Beam W21 ‘Outside’ Beam TS 6 X6 W12 Columns Link Beam w/ Stiffeners
Pouring Stream – Structural Alternative 1 3rd Floor Gravity System 6.5” Composite Deck w/ W12 x 26 Beams 24” Long Span Truss and Concrete Slab 8” Bearing Wall @ Elevator Shaft Cantilever Beam – Column at Central Atrium W12 x 50 Columns
Pouring Stream – Structural Alternative 2 • Steel SMRF w/ Shearwalls • Beams: W21 x 62 • Columns : W14 x 120 • Shearwall: 8” • Gravity System • Composite Deck(t=6.5) w/ W12 x 26 Beams • Columns: W12 x 50 In Context of Architectural Layout – 3rd Floor
Pouring Stream – Structural Alternative 3 • Concrete MRF w/ Shearwalls • Beams: 16” x 18” • Columns : 18” x 18” • Shearwall: 8” • Gravity System • 10” Flat Plate w/ Drop Beams • Columns: 12” x 12” Moment Frame Connection • Foundation System • 6’x 6’ Spread Footings • 4’ Cont. Footing @ Retaining Walls • 12” Mat Foundation @ Utility Tunnel • 12” Perimeter Retaining Wall
Pouring Stream – Construction Schedule and Cost Breakdown Steel EBF Steel SMRF Concrete MRF Schedule Alt. 1 – 8 months Alt. 2 – 8½ months Alt. 3 – 9 months Alt. 1 Alt. 2 Alt. 3
Pouring Stream - Team Interaction Structural Limitations Back to the Drawing Board – Revisions Propose Design Initial Estimate / Constructability Issues Cost Issues Finalize Design Structural Solutions Issues Concerns Estimates / Schedules
Equipment Selection • Hydraulic Truck Crane • Hydraulic Hammer • Backhoe Loader / Front-end Loader • Welding Machines • Cement Mixers / Dump Trucks / various others…
Original 2015 Budget Adjustment for Inflation Adjustment for Location - 1.1 New Adjusted Budget Sunrise - Alt. 1 Sunrise - Alt. 2 Flying Eagle - Alt. 1 Flying Eagle - Alt. 2 Flying Eagle - Alt. 3 Pouring Stream - Alt. 1 Pouring Stream - Alt. 2 Pouring Stream - Alt. 3 Budget Concerns • Construction in 2015 • Project Budget : $5.5 Million • Assumed 3.5% Inflation • Adjusted Budget : $3.4 Million • Cost Index for L.A. – 110%
Preferred Design Alternative ‘ POURING STREAM’ A: Effective Space Layout, Potential for Poetic Space, Good Eco-Design Development E: Steel SMRF w/ Shearwalls – Versatile – Efficient - Effective C: Within Budget and Schedule Constraints - Atrium Poses Interesting Challenge
Team Improvement • Team Dynamics • A interacts with owner the most • E is very good in informing A and C about his progress • C is very consistent in keeping group records, organization • Improvements • More interaction with Owner and Mentors • Inform each other about one’s progress more frequently • Continue education between three disciplines
Thank you! • We would like to pay our respect and gratitude to our mentors : • Brook Barrett - DPR • David Bendet -MBT • Eric Elsesser - Forell/Elsesser Engineers, Inc • Helmut Krawinkler – Stanford • Paul Chinowsky – Georgia Tech AND.. • Renate Fruchter - Stanford For contributing their valuable time and suggestions, Thank you!