Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

LCLS. Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008. Goals Radiation Surveys Manpower Organization. http://www-ssrl.slac.stanford.edu/lcls/commissioning/. Nov 2008…. Commission Jan-Aug 2008. Commission Mar-Aug 2007. LCLS Accelerator Layout.

creola
Download Presentation

Beam Commissioning Schedule and Staff P. Emma Accelerator Readiness Review Dec. 4, 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Beam Commissioning Schedule and StaffP. EmmaAccelerator Readiness ReviewDec. 4, 2008 • Goals • Radiation Surveys • Manpower • Organization http://www-ssrl.slac.stanford.edu/lcls/commissioning/

  2. Nov 2008… Commission Jan-Aug 2008 Commission Mar-Aug 2007 LCLS Accelerator Layout 250 MeV z  0.19 mm   1.6 % 4.30 GeV z  0.022 mm   0.71 % 13.6 GeV z  0.022 mm   0.01 % 6 MeV z  0.83 mm   0.05 % 135 MeV z  0.83 mm   0.10 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun L0-a,b Linac-3 L 550 m rf  0° Linac-1 L 9 m rf  -25° Linac-2 L 330 m rf  -41° 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC1 L 6 m R56 -39 mm BC2 L 22 m R56 -25 mm undulator DL1 L 12 m R56 0 DL2 L =275 m R56  0 SLAC linac tunnel research yard

  3. LCLS Commissioning Web-Page Phase-II Phase-I Phase-III http://www-ssrl.slac.stanford.edu/lcls/commissioning/

  4. Design and Typical Measured Parameters (Aug. 2008) * horizontal slice emittance likely < 1 µm

  5. Goals • Re-establish Linac Operations • Transport e- to main dump (~14 GeV, 200 pC, 10 Hz) • Verify all new components (BPMs, screens, magnets, wires, software, etc) • Verify all new photon diagnostics (FEE) • Commission MPS & BCS • Fully characterize electron beam • Align undulator using beam-based method • Characterize X-ray radiation • Establish CD-4 flux level in FEE http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/2009_commissioning-goals.doc

  6. Pre-Beam Checkout • Check magnet polarities • Check cable connections • Check component serial numbers • Check component installation orientation • Check controls function (power, motion, readback, etc) • Check water connections • Label all components, etc… 51 pages, 2000 checks, 70% done Separate list for undulator… 204 pages, 7200 checks, 10% done? http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/pre-beam-check-list-2009.doc

  7. Radiation Surveys • Beam to D2 in BSY (done) – survey BTHW, etc. • Beam to und. stopper – survey BTH head house, mazes, etc. • 14-GeV beam to main dump – survey bldg. 921, FEE-wall, etc. • 4-GeV beam to main dump - survey bldg. 921, FEE-wall, etc. DRAFT >1 week required when first beam transported into new halls (BTH, UH, Dump) http://www-ssrl.slac.stanford.edu/lcls/commissioning/documents/part1_uncominitial-11-13-08.doc

  8. Manpower • LCLS Commissioning Phase-III: Nov. 2008 through July 2009 (36 wks) • 3 shifts per day (1-2 physicists 8:00-16:00 & 16:00-24:00, with operations coverage 24:00-8:00, unless more required) 21 LCLS Physicists (all with LCLS experience) …plus new help from PEP-II and beyond Axel Brachmann (ASD) Dave Dowell (consultant - available 1 week/month) Franz-Josef Decker (ASD) Yuantao Ding (PPA) Paul Emma Joe Frisch Sasha Gilevich (laser) Steve Edstrom (laser) Greg Hays (laser) Philippe Hering (laser) Zhirong Huang (PPA) Cecile Limborg (on leave until May, 2009) Henrik Loos Rick Iverson Heinz-Dieter Nuhn Daniel Ratner (graduate student/PPA) Jim Turner Jim Welch Bill White (laser) Juhao Wu Dao Xiang (post-doc, PPA) Kirk Bertsche Sasha Novokhatski Jerry Yocky + LBNL Sasha Zholents Bill Fawley + Trieste Simone Spampanati + DESY, PSI, …? + Operations, Controls, Power-conversion, RF, engineering, etc

  9. Physicist Commissioning Shifts Schedule example

  10. Manpower and Organization With 36 total weeks, this distributes into the following weekly work load for each group (averaged over 36-week run). LCLS Physicists: ~1 shift/wk (peak is higher depending on task) Operators (3/shift): Operate accelerator and support commissioning Chief Operator (EOIC): Leads operations crew during shift Program Deputy: Makes daily decisions on program Program Coordinator: (PE)Sets long-term program, shifts, access, etc. Controls Deputy: Liaison to controls group to solve daily problems Commiss’ng Engineer: Coordinate access/repair days and direct work

  11. Important Dates for 2008/2009 Commissioning • Nov. 3, 2008: Startup (establish beam to end of linac again) • Dec. 10, 2008: Install laser-heater undulator (1 day) • Dec. 15, 2008: First beam through LTU & to dump? (survey) • Dec. 19, 2008: SLAC shuts down for holidays • Jan. 5, 2009: Startup again (establish beam in LTU & dump) • March 2, 2009: Install 25 undulators + PPS re-cert. (~2 wks) • May 14, 2009: First x-ray beam in FEE • July 2009: Photons in NEH • August 2009: Start AMO Experiment • December 2009: Downtime for holidays + PPS re-cert. (~2 mo.)

  12. LCLS Installation and Commissioning Time-Line InstallUndulators First Light in FEH PPS Cert. LTU/Dump LTU/Und Install X-Rays in NEH First Light in FEE CD-4 (7/31/2010) FEE/NEH Install FEH Hutch BO PEP-II run ends J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J D M D A 2008 2009 2010 Down Down? PPS LTU/Und Comm. NEH Ops & Commissioning Linac/BC2 Commissioning Re-establish e- to SL2 FEL/FEE Commissioning Nov. 3, 2008

  13. LTU/Undulator/FEE/FEL Commissioning H. Tompkins + heater

  14. Beam Appears Bright Enough for FEL Saturation at 0.15 nm M. Xie method, with wakes FEL Power 3D Gain Length Calculation based on measured end-of-linac projected emittance values, measured peak current, and design undulator parameters (assuming undulator alignment and 0.01% rms slice energy spread – not yet measurable)