System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley

System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley. System Design Agenda. AGENDA Requirements Electrical System Overview Resource Summary Issues. Requirements. System Requirements have been documented in CINEMA_Requirements

corneliaj
Download Presentation

System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. System Design • Dave Curtis • UCB/SSL • Space Sciences Laboratory • University of California, Berkeley

  2. System Design Agenda • AGENDA Requirements Electrical System Overview Resource Summary Issues

  3. Requirements • System Requirements have been documented in CINEMA_Requirements • Subsystem designers should be familiar with requirements placed on their system and design/test to verify compliance • Deviations from requirements need to be approved by me. • More detailed requirements have been developed in some cases • For example, Flight Software requirements, CINEMA_FSW_002_Requirements

  4. Requirements Verification • For each requirement we need to identify how/when we are going to verify it • Subsystem designers need to propose verification plans for each of their requirements to me before starting tests • Requirements verification for each subsystem shall be reviewed prior to integration • Requirements which can only be verified at a lower level of assembly need to be completed prior to integration • Some requirements need to be verified or re-verified at the system level – plans for these need to be identified prior to integration • Some requirements may have to be verified wholly or partially by analysis • test preferred • A document describing the analysis is desirable • All requirements shall be verified prior to launch

  5. Interface Control Documents • By CDR some form of ICD should exist between all subsystems which interface together • Some ICD are more formal than others • Existing ICDs • CubeSat Design Specification • Purchased hardware manuals such as EPS Users Manual • MAGIC ICD • Spacecraft Mechanical Layout & Accomodations Model • Avionics backplane Specification • Harnessing Diagram • Needs connector definitions, pinouts • FPGA Specifications (preliminary)

  6. Electrical Systems Block Diagram

  7. Mechanical Layout [Obsolete]

  8. Harnessing Diagram

  9. Resources - Mass • Somewhat Obsolete [10/09] • +UHF Antennas, deployment system • +UHF Electronics • -MicroHard Antennas • -MicroHard Electronics • LVPS/Instrument Interface combined into IIB • Updates • Plenty of Margin • 4kg limit per rev 12 CDS

  10. Resources – Power Generation • 3.22W Orbit Average, Nominal Attitude • 2.14W Worst Case Attitude

  11. Resources – Battery Capacity • 26% Max DOD (once/day, mostly S-band Transmitter) • Assumes no UHF Downlink (or only 1 transmitter on at a time)

  12. Resources – Power Usage • 80% Margin, SAFE Mode • 25% Margin, ACS, Normal Modes

  13. Resources – Telemetry • 9700bps average science (and stored engineering) rate • 9600 baud real time engineering via UHF • 27bps average engineering rate if stored engineering downlinked via UHF 1 pass/day

  14. Issues • Some ICDs/Specifications need work by subsystem designers • Subsystem designers need to start thinking about Verification Plans • Need Mass update • Need more analysis if we plan to use UHF transmitter • Can we simultaneously use S-band (needs power analysis) • We need a switch or PIN-D diode • Requires simplex operation – software & MOC complications • Need GSE (Another UHF card & antennas?) • Ground station receiver/antenna • Link margin