1 / 16

Beneficial Reuse of Sand on the Fox River Sediment Remediation Project

Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L. Blackmar, P.E. (Tetra Tech). Project Team. Client: Lower Fox River Remediation LLC Engineering Design & Construction: Tetra Tech

Download Presentation

Beneficial Reuse of Sand on the Fox River Sediment Remediation Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beneficial Reuse of Sand on the Fox River Sediment Remediation Project Neil Geevers (Stuyvesant/Boskalis) Richard J. Feeney, P.E. (Tetra Tech) Terri L. Blackmar, P.E. (Tetra Tech)

  2. Project Team • Client: Lower Fox River Remediation LLC • Engineering Design & Construction: Tetra Tech • Dredging & Capping: J.F. Brennan Co., Inc. • Desanding & Dewatering: Stuyvesant Projects Realization Inc., affiliate of Boskalis Dolman • Anchor QEA, LLC: assist with design • URS: assist with modeling • Numerous local construction subcontractors

  3. Project Scope OU 2 – 5 // 13 miles (21 km) // Combined Remedy // The goal of the project is to remediate PCB bearing sediment by dredging, capping, or covering // Hydraulic Dredging // Sediment Processing & Sand Reuse // Water Treatment // Offsite T&D

  4. Processing Facility design started in march 2008// Began processing April 2009// unique single stream process // 150-250 in-situ cy/hr (190 m3/hr) // 6000 gallon/min. (1,400 m3/hr) // 6 acre building (2.4 ha) // air quality conditioned

  5. Objective One objective of the Fox River processing facility is to minimize the contaminated volume disposed of at the landfill by beneficial use of the separated coarse fractions (sand) and by dewatering the fine (contaminated) fraction

  6. Three phase treatment 1) Pre-conditioning // 2) Sand separation and polishing for beneficial use (about 19% sand), two sand fractions are separated // 3) mechanical dewatering

  7. Why Separate Sand? • Prevent additional wear and tear on downstream process equipment • Reduce the dewatering cycle time from not having to process the sand • Avoid unnecessary expense for T&D as waste • Avoid consuming landfill space • Various beneficial reuse opportunities

  8. Separated Sand Parameters • ~ 18,000 tons of sand separated in 2009 • ~ 56,000 tons of sand separated in 2010 • ~ 22,000 tons of sand separated in 2011 • ~ 19,000 tons of sand projected for 2012 • Coarse sand ranges from 150 µm to 6 mm • Fine sand ranges from 63 µm to 150 µm

  9. Recovered sand outside of processing facility

  10. Stockpiled & covered; awaiting load-out for reuse

  11. Sampling Parameters • Fine & coarse sand sampled once each 1,000 cy for the first 10,000 cy • Then one sample/10,000 cy for 10,000 to 50,000 cy • Then one sample/50,000 cy thereafter • 2009 chemistry: 27 fine sand samples and 10 coarse sand samples • 2010 chemistry: 39 fine sand & 32 coarse sand • 2011 chemistry: 11 fine sand & 12 coarse sand

  12. Chemical Testing Criteria for Sand Proposed Constituents Project-Specific Maximum Allowable Contaminant Concentrations (mg/kg) PCB, Total . 0.49 (mg/kg) Total 2,3,7,8 TCDD 0.19 (ug/kg) Total 2,3,7,8 TCDF 0.19 (ug/kg) DDT (and its metabolites DDD & DDE) 1.0 Arsenic 9.8 Barium 500 Cadmium 7.8 Chromium 14.5 Copper 150 Cyanide 100 Iron 20,000 Lead 50 Manganese 1100 Mercury 4.7 Nickel 250 Selenium 63 Zinc 1500

  13. Additional Notes – Sand Testing Criteria • Geotechnical Properties  For information only: • Grain size • Percent solids • Total organic carbon • Moisture content • WDNR provided Project Specific Maximum Allowable Contaminant Concentrations in December 2008  The concentrations shown pertain to sand that is not capped in place, and are therefore conservative if applied to sand that will be capped.

  14. Chemical Characteristics

  15. Beneficial Reuse Process • Prepare and submit Low Hazard Waste Exemption Request naming specific offsite projects (*one Request per project) • Public works projects are preferred • Address WDNR comments to the Request • Participate in public meeting concerning the Request • Finalize commercial arrangements • Provide appropriate temporary erosion controls at the beneficial reuse site • Track and report on sand shipped for beneficial reuse.

  16. Win - Win for 2 Major Regional Projects

More Related